WHEREAS, the City of Fort Worth (City) and LopezGarcia Group
formerly Wendy Lopez & Associates, Inc. , (Engineer) made and
entered into City Secretary Contract No. 26994, (the Contract)
which was authorized by the City Council by M&C C-18701 on the 9th
day of August, 2001 and subsequently revised by seven previous
amendments; and
WHEREAS, the Contract involves engineering services for the
following project:
Water and Sanitary Sewer Extension for the Bryson Tract Area
(Annexation A-00-23)
WHEREAS, it has become necessary to execute Amendment No. 8 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
1 .
Article I, of the Contract is amended to include the addition-
al engineering services specified in M&C C-21119, adopted by the
City Council on the 1st day of November 2005, and further amplified
in a proposal letter dated August 31, 2005, copies of which are
both attached hereto and incorporated herein. The cost to City for
the additional services to be performed by Engineer total
$1,615.25.
2.
Article II, of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $138,458.61.
3.
All other provisions of the Contract which are not expressly
amended herein shall remain in full force and effect.
l
EXECUTED on this the day of � 2005, in
Fort Worth, Tarrant County, Texas.
ATTEST: ,~` � 1
Contract Authorization
Marty Hendri9t
Date
City Secretary
APPROVAL RECOMMENDED: D:
A. bouglas Rademaker, P.E . Marc A. Ott
Director, Department of Engineering Assistant City Manager
LopezGarcia Group formerly
Wendy Lopez & Associates, Inc.
Engineer
,�,�
By:
Name:Luis A. Villamil, P.E . , Manager
100 E . 15th Street, Suite 200
Fort Worth, TX 76102
APPROVE AS TO FORM AND LEGALITY:,
AssistangZCiAttorney
-2-
L ' D P E Z G A R C I A G R O U P
August 31, 2005
Mr. Mike A. Domenech, P.E.
Project Manager
City of Fort Worth
Department of Engineering
900 Monroe Street, Suite 201
Fort Worth, Texas 76102
RE: Request for Amendment No. 8
Water and Sewer Extension for Bryson Tract, D.O.E. 3312
LGGROUP Project No. 210069.00
Dear Mr. Domenech:
This letter is written in response to your request for additional engineering design and special
services for the above referenced project. The additional design services are as described
below. A detailed breakdown of the proposed fees for these additional services is also
attached.
Our proposed engineering fee for the additional work includes the following:
1. Prepare one (1) private service sheet identifying the transfer of water service for
Bryson Elementary School from the City of Saginaw water line located along Old
Decatur Rd. to the recently constructed City of Fort Worth water line located in
Bryson Ln. Please note that in order to minimize cost, no additional field survey will
be performed. Instead, the plan sheet will be created from aerial photography with
typical measurement call-outs from existing surface features.
2. Prepare an Engineer's Opinion of Probable Construction Cost for the water service
transfer.
3. Attend one (1) City of Fort Worth coordination meeting.
Please note that the proposed fee does not include the following work items:
✓ Acquisition of additional topographical survey data,
✓ Preparation of easements or property descriptions,
✓ Submission of anytype of electronic file, except as specifically indicated,
✓ Preparation of permits for various local, state, or federal authorities,
✓ Environmental documents or wetland determinations,
✓ Geotechnical studies or subsurface investigations,
✓ Storm Water Pollution Prevention Plan,
✓ Additional meetings, site visits, or reviews, except as specifically indicated,
✓ Construction layout surveying, or
✓ Other items not specifically identified within this document.
1.rQf��,l' �1 l'1�r f. �h. .•
Iggroupinc.com Water Gardens Place,100 East 15th Street,Suite 200,Fort Worth,Texas,76102 (817)390-1000 1Z�&2--%2.Fax
L O P E Z G A R C I A G R O U P
Mr. Miguel A. Domenech, P.E.
City of Fort Worth
August 31, 2005
Page 2
These additional efforts are considered outside our original scope of work, and we therefore
request a contract amendment to increase the lump sum fee amount by $ 1,615.25 (See
attached Cost Proposal Summary).
Original Lump Sum Amount: $ 67,830.00
Amendment No. 1 $ 8,077.00 — Approved 3/12/02
Amendment No. 2 $ 17,172.05 — Approved 8/20/02
Amendment No. 3 $ 14,305.55 — Approved 1/15/03
Amendment No. 4 $ 6,748.88— Approved 9/3/03
Amendment No. 5 $ 2,831.70 — Approved 2/2/04
Amendment No. 6 $ 15,554.08 — Approved
Amendment No. 7 $ 4,324.10 — Approved
Amendment No. 8 $ 1,615.25 — Requested Herein
Total Revised Amount: $138,458.61
If you have any questions or need additional information concerning this request, please feel
free to contact me or Brent E. Lewis, P.E. at (817) 390-1000.
Sincerely,
LOPEZGARCIA GROUP
(i(- "O'oj
Luis A. Villamil, P.E.
Manager, Fort Worth Municipal and Site Civil
LAV:bel
Enclosures
P:\FW\210069.00\Doc\Contract-Amendment\Amendmend No. Rev(08-31-05).doc
.T1
- Page 1 of 2
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 11/1/2005
DATE: Tuesday, November 01, 2005
LOG NAME: 30BRYSON8 REFERENCE NO.: **C-21119
SUBJECT:
Authorize Execution of Amendment No. 8 to Engineering Agreement with LopezGarcia Group for
Water and Sanitary Sewer Extension for-the Bryson Tract Area (Annexation A-00-23)
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 8 to City
Secretary Contract No. 26994 with LopezGarcia Group, formerly Wendy Lopez and Associates, Inc., in the
amount of$1,615.25 for additional design, thereby increasing the contract amount to $138,458.61.
DISCUSSION:
On August 9, 2001, (M&C C-18701) the City Council authorized an engineering agreement with Wendy
Lopez and Associates, Inc. (now LopezGarcia Group) in the amount of $67,830.00 for the design of Water
and Sanitary Sewer Extension for the Bryson Tract Area (Annexation A-00-23).
The project consists of the preparation of plans and specifications for the extension of City water and
sanitary sewer mains to serve an annexed area south of Bailey-Boswell Road and west of Old Decatur
Road.
The agreement was subsequently revised by seven previous amendments in the amount of $69,013.36 as
follows:
. Amendment No. 1 (City Secretary No. 27541) in the amount of $8,077.00 and administratively
approved by the City Manager on March 12, 2002, provided for the change in the alignment of the
project sewer main.
. Amendment No. 2 (City Secretary No. 27921) in the amount of $17,172.05 and administratively
approved by the City Manager on August 20, 2002, provided for the design of additional water and
sanitary sewer lines to provide service to new residents within the annexed area.
. Amendment No. 3 (City Secretary No. 28316) in the amount of $14,305.55 and administratively
approved by the City Manager on January 15, 2003, provided for the redesign of a project sewer
main to provide additional capacity to accommodate a proposed development located west of this
project.
. Amendment No. 4 (City Secretary No. 29043) in the amount of $6,748.88 and administratively
approved by the City Manager on September 3, 2003, provided for the preparation of a storm water
pollution prevention plan and additional easements on the project.
. Amendment No. 5 (City Secretary No. 29489) in the amount of $2,831.70 and administratively
approved by the City Manager on February 2, 2004, provided for revisions to the contract documents
http://www.cfwnet.org/council_packet/Reports/mc�_print.asp 11/2/2005
F Page 2 of 2
to accommodate the most recent city specifications.
. Amendment No. 6 (City Secretary No. 30417) in the amount of $15,554.08 and administratively
approved by the City Manager on August 26, 2004, provided for the preparation of a traffic control
plan for the project and the design of additional water and sanitary sewer mains.
. Amendment No. 7 (City Secretary No. 31173) in the amount of $4,324.10 and administratively
approved by the City Manager on January 13, 2005, provided for the preparation of plans to allow for
the reroute of seven residential sanitary sewer service lines from a City of Saginaw sewer main into
the new Fort Worth sewer main.
This agreement may be administratively amended up to an additional $25,000.00.
This amendment will allow for the preparation of drawings for the reroute of the water service line for Bryson
Elementary School from a City of Saginaw water main, to the recently completed City of Fort Worth water
main located on Bryson Lane. Prior to Annexation A-00-23, Bryson Elementary School was located in the
county and was provided water service by the City of Saginaw water main located on Old Decatur Road.
LopezGarcia Group proposes to provide the necessary additional engineering services for a lump sum fee
of$1,615.25. Staff considers this amount to be fair and reasonable.
This project is located in COUNCIL DISTRICT 2, Mapsco 33P.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of the
Water Capital Projects Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
11 1
P160 531200 060160151600
615.25
Submitted for City Manager's Office by: Marc Ott (8476)
Originating Department Head: A. Douglas Rademaker(6157)
Additional Information Contact: A. Douglas Rademaker (6157)