HomeMy WebLinkAboutContract 42933-CO2 `.I T Y,ECRET'A FORT WORTH: City of Fort Worth Change Order Request Project Name South Pipeline Road Bridge at Post Oak Creek City Sec# 1 42933 Client Project#(s) 00258 Project Description Reconstruction of South Pipeline Road Bridge at Post Oak Creek Contractorl Humphrey&Morton Construction Co., Inc. Change Order# 0 Date F 12/15/2014 City Project Mgr.1 Michael Weiss, P.E. City Inspector FMark Owen Dept. TPW Water Sewer Contract Time Totals CD Original Contract Amount $499,836.55 $0.00 $0.00 $499,836.55 150 Extras to Date $17,519.98 $0.00 $0.00 $17,519.98 22 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $517,356.53 $0.00 $0.00 $517,356.53 172 Amount of Proposed Change Order $0.00 $10,755.91 $0.00 $10,755.91 Revised Contract Amount $517,356.53 $10,755.91 $0.00 $528,112.44 172 Original Funds Available for Change Orders $0.00 $0.00 Remaining Funds Available for this CO $0.00 $0.00 $0.00 Additional Funding(if necessary) $10,755.91 $10,755.91 CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 5.66% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $624,795.69 JUSTIFICATION (REASONS) FOR CHANGE ORDER Repair Existing Valve Stack on east side of bridge(DOE#5406). V OP 0 OFFICIAL RECORD Mary 0XA CWY SECRETARY J. f , City Secretary �. FT. WORTHS TX It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an actor nd satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's Company Name Co tact r Name nit a Date Humphrey&Morton Construction Co., 11 1 it Z-1 I / YI Prq ec Mqn_ er/Progra Ma er Date .Assst __,,Date_ Direc _.,C,. a ent(Dept) Date A ' to AtWr gey Date Assistant City Manager Date VEX Council Action if required) M&C Number N/A M&C Date Approved 0 / Q # \ # \ G . 8 - CO 3 \ Cl / 0 Its \ / / a 0 � / U / / m o \ / CL 2 Q� :1) 0 o � \ z » � 0 / ƒ @ LL ® \ o0 \ \ � \ / 5 4 0 \ 2 \ \ / \ Q / / \ ! \ \ 2 � \ \ / \ ® \ m / ca- f / C:) 4 7 y = r e o # / \ \ c �_ G - w a (D/ / * m ' y$ c � e � ® 6 Co C° - o ui o LO 69, ti 61!)-ti LO 0 c 0 ICL CU � Q N 4- O N N OA m a c 0 Q L OD c U e m ° G Q # \ # % � S ~ E Cl) \ \ c H ƒ 0 # \ \ 6 � « ° ° y co C v @ 9 e / t 2 / § o ¢ )R \ 2 � \ % / LL \ d / 4- o oa \ e ƒ \ / z » 3 U o \ 0 / 0 % 5 \ m \ \ f \ o co % / @ / 0 \ \ k \ ® _ / a ® _ (D \ ) ƒ y 4 7 2 _ e # § a g / (D ± / x ? / �5 2 Co Co Co 0 0 0 c 0 F- 3: CO CO0 .o c N 4- O N N 0.0 m d N C i-+ N v OA c M .0 U HUMPHREY&MORTON PO BOX 8057 FORT WORTH,TEXAS 76124 PHONE:(817)478-8088 FAX:(817)561-2368 JOB NAME: RECONST OF SOUTH PIPELINE RD @ POST OAK CREEK JOB DESCRIPTION: INSTALLATION 2 BBL BOX CULVERT,PAVING CITY&STATE: FORT WORTH,TX DATE: NOVEMBER 3,2014 VALVE STACK REPAIR COST BREAKDOWN INVOICE ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL 1 PVC VALVE STACK LS 1.00 $ 1,795.00 $ 1,795.00 2 FLOWABLE FILL CY 8.00 $ 245.25 $ 1,962.00 3 CONC PAVING CY 4.00 $ 491.00 $ 1,964.00 4 ROTO ROOTER VACUUM EXCAV LS 1.00 $ 3,924.06 $ 3,924.06 5 TRAFFIC CONTROL LS 1.00 $ 1,110.85 $ 1,110.85 TOTAL BID $ 10,755.91