HomeMy WebLinkAboutOrdinance 17494-04-2007Ordinance No. 17494-04-2007
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE NEW DEVELOPMENT FUND IN THE AMOUNT OF
$407 414 70 FROM A SPECIAL ASSESSMENTS FUND TRANSFER, FOR THE
PURPOSE OF EXECUTING A COMMUNITY FACILITIES AGREEMENT WITH
JABEZ DEVELOPMENT L.P FOR THE INSTALLATION OF COMMUNITY
FACILITIES TO SERVE PALMILLA SPRINGS PHASE I PROVIDING FOR A
SEVERABILITY CLAUSE, MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES IN CONFLICT HEREWITH AND PROVIDING AN EFFECTIVE
DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH
TEXAS
SECTION 1
That in addition to those amounts allocated to the various City departments for Fiscal Year 2006-
2007 in the Budget of the City Manager there shall also be increased estimated receipts and
appropriations in the New Development Fund in the amount of $407 414 70 from a Special
Assessments Fund transfer for the purpose of executing a Community Facilities Agreement with
Jabez Development, L.P for the installation of community facilities to serve Palmilla Springs,
Phase I
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid,
inoperative or void for any reason by a court of competent jurisdiction such decision, opinion or
judgment shall in no way impair the remaining portions, sections, or parts of sections of this
ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No 17142 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance
are in direct conflict with such other ordinances and appropriations, in which instance said
conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4
This ordinance shall take effect upon adoption.
APPR AS TO FORM N L ALITY
A ~ ant Ci orn
ADOPTED AND EFFECTIVE. Aoril 10. 2007
0
0
0
N
G!
2
-'~
r
C
C^
~-'
m
~_
m
X
~
~
M u
o
mm
W ~ ~
U N
~`g~. T~ ~
~
~ ~ ~ ~i
r X
w Y ^
^ t
,
uJ u, O~
O O ~"
~
~
;~ ~ 0
a~
'?
r~
`~'O CO N o0
` a
OC ~,
~ ~ ~ `I~ co ~
O ) ,~ ~'
E° ANN O
'°
®o
`~ o- o- z
~
~~ o
o owz
~ _
~ ~ zZ
o ~
~ ~ ~ U U ~ LL
~ ~ ~ _~
U ~ O O
~~
~
~ ~
~
-~-~
p
~~
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION Approved on 4/10/2007 Ordinance No 17493-04-2007 ~ 17494-04-2007
DATE Tuesday April 10 2007
LOG NAME 20CFAPALMILLA REFERENCE NO G 15673
SUBJECT
Authorize Execution of a Community Facilities Agreement with Jabez Development, L.P for the
Installation of Community Facilities to Serve Palmilla Springs Phase I and Adopt Appropriation
Ordinances
RECOMMENDATION
It is recommended that the City Council
1 Adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in the
Special Assessments Fund in the amount of $407 414 70 from prior developer contributions
2. Authorize the transfer of $407 414 70 from the Special Assessments Fund to the New Development
Fund
3 Adopt the attached appropriation ordinance increasing the estimated receipts and appropriations in the
New Development Fund in the amount of $407 414 70 from available funds, and
4 Authorize the City Manager to execute a Community Facilities Agreement (CFA) with Jabez
Development, L.P for the installation of community facilities to serve Palmilla Springs, Phase
DISCUSSION
Jabez Development, L.P the developer of Palmilla Springs Phase I has executed a proposed contract
for community facilities to serve a single family (114 lot) development located in west Fort Worth bounded
on the north by Chapin Road and on the south by Interstate 30 (see attached map) The project includes
construction of the full (55-feet) section of Chapin Road adjacent to Palmilla Springs, and a half (39 5-feet)
section from the development boundary to Chapel Creek Boulevard The City collected future-
improvement funds for the northern half of Chapin Road through the CFAs of three adjacent
developments Trail Ridge Estates Westview Addition Phase 1 and Westview Addition Phase 2 Jabez
Development, L.P is requesting reimbursement from the City for construction of the northern half of
Chapin Road from the previously collected CFA funds
The estimated costs of all community facilities for Palmilla Springs, Phase 1 including construction of
Chapin Road are as follows.
ITEM
A. Construction
1 Streets
2. Storm Drainage
3 Street Lights
4 Street Name Signs
Logname 20CFAPALMILLA
DEVELOPER COST CITY COST TOTAL COST
$488 142.25 $488 142.25
$108 804 74 $108 804 74
$57,200 00 $57,200 00
$1 960 00 $1 960 00
Page 1 of 2
5 Streets (Chapin Rd )
6 Storm Drainage (Chapin Rd )
B Engineering Design
C Construction Engineering and Management by DOE (4%)
D Materials testing by DOE (2%)
TOTALS
Execution of this CFA would entail the allocation of previously collected developer contributions as City
cost in the amount of $407 414 70
$367 831 00 $277 087.20 $644 918.20
$119 638 50 $130.327.50 $249 966 00
$43 376 66 $43 376 66
$21,688.33 $21,688.33
$1,208 641 48 $407 414 70 $1 616 056 18
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance funds will be available in the current capital budget, as appropriated of
the New Development Fund
TO Fund/Account/Centers
1) GS94 488100 020941369010 $407.414.70
1) GS94 538070 020941369010 $407,414.70
2) C202 472094 203760055183 $407.414.70
3) C202 541200 203760055183 $407.414.70
FROM Fund/AccountlCenters
2) GS94 538070 020941369010
4)C202 541200 203760055183
X407,414.70
$407.414.70
Submitted for City Manager's Office ~• Marc Ott (8476)