HomeMy WebLinkAboutContract 45039-CO5 F0 R-r VV0 RT H City of Fort Worth CIS SECRETARY
Change Order Request CONTRACT NO.
Project Name:I Sanitary Sewer Rehabilitation Contract 75, Part 2 City Sec No.: 1 45039
Project No.(s): P253-609170148083&P258-709170148083 I DOE No. 6973 CiVProj.No.:l 01480
Project The replacement of water and sanitary sewer mains on Medford Road from Chelsea Road to Stratford Park Drive
Description:
Contractor: Tejas Commercial Construction, LLC. Change Order# 0 Date: 10/29/2014
City Project Mgr. Roberto C.Sauceda City Inspector: John Crowley
Phone Number: 817-392-2387 Phone Number: 817-994-0975
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $199,488.50 $523,195.00 $722,683.50 180
Extras to Date $143,944.20 $9,475.20 $153,419.40 0165
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $343,432.70 $532,670.20 $876,102.90 345
Amount of Proposed Change Order 79,104.00 -$70,067.50 9,036.50 045
Revised Contract Amount $422,536.70 $462,602.70 $885,139.40 390
Original Funds Available for Change Orders $10,000.50 $25,000.00 $35,000.50
Remaining Funds Available for this CO $15,524.80 $15,524.80
Additional Funding(if necessary) $79,104.00 $79,104.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 22.48%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25 916) 1$903,354.38
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The change order will provide increased and additional pay item quantities that were necessary on the
roj ect.
• Additional water services to install and rerouting private water line.
Staff concurs with the contractor's request for 45 additional calendar days be provided on the project.
. OR =:
o �
OFFICIAL RECORD
CITY SECRETARY
��Maly A 5 See, FT.WORTH,TX
rn
It is understood and agreed that the acceptance of this Change Oder by the contractor constitutes an accord and satisfaction and represents
z payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Contractor Signature Date
Tejas Commercial Construction, LLC. Charles Allen
Inspect Inspectw Date Projec a Date
�-/, - 9/is
As ' a t ' `ct ter pt) Date (Opnstrujqtion Supervisor(TPW Dept) Date
1 ?�t�,.
Assistant gWttomey D6 Assistant City Manager Date
Council Action(If Required)
CHECKED JAN 07 2015
F_ O RT WORTH City of Fort Worth
Change Order Request
M&C Number N\A M&C Date Approved MA I
F_ O RT WORTH City of Fort Worth
Change Order Additions
Project Name Sanitary Sewer Rehabilitation Contract 75, Part 2 City Sec No.: 45039
Project No.(s): P253-609170148083&P258-709170148083 DOE No. 6973 City Proj. No.: 01480
Project The replacement of water and sanitary sewer mains on Medford Road from Chelsea Road to Stratford Park Drive
Description
Contractor Teas Commercial Construction, LLC, Change Order:=5 Date: 10!29/2014
City Project Mgr. I Roberto C.Sauceda City Inspector FJohn Crowley
ADDITIONS
DEPT Qty Unit Unit Cost Total
1 1"WATER SERVICE Water 20.00 EA $900.00 $18,000.00
12 1"WATER SERVICE METER RELOCATION Water 17.00 EA $250.00 $4,250.00
29-New Flowable fill Water 30.00 CY $110.00 $3,300.00
30-new Cut&Plug Water 28.00 EA $800.00 $22,400.00
31-new 1"Water Service, Private Reroute Water 196.00 LF $25.00 $4,900.00
32-new High Early Concrete Water 15.00 CY $120.00 $1,800.00
33-new 1"Taps Water 14.00 EA $600.00 $8,400.00
34-new 1"Copper Service Water 398.00 LF $22.00 $8,756.00
35-new.Class A Meter Boxes Water 14.00 EA $200.00 $2,800.00
36-new 1.5"Copper Water 173.00 LF $26.00 $4,498.00
13 4 inch Sewer Service Sewer 21.00 EA $850.00 $17,850.00
36-New Additional for sewer services on Junuis Street Sewer 1.00 LS $6,702.50 $6,702.50
Water $79,104.00
Sewer $24,552.50
Page 1 of 2
Additions Sub Total 1$103,656.50
Page 2 of 2
FORT WO RT H City of Fort Worth
Change Order Deletions
Project Name FSanitary Sewer Rehabilitation Contract 75, Part 2 City Sec No.: 45039
Project No.(s): P253-609170148083&P258-709170148083 DOE No. 6973 City Proj. No,: 01480
Project The replacement of water and sanitary sewer mains on Medford Road from Chelsea Road to Stratford Park
Description Drive
Contractor Tejas Commercial Construction, LLC. Change Order: El Date 10/29/2014
City Project Mgr. Roberto C. Sauceda City Inspector: John Crowley
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
7 Epoxy Structure Liner Sewer 1845.00 LF $12.00 $22,140.00
23 6 Foot Wide Asphalt Pvmnt Repair Sewer 1510.00 LF $48.00 $72,480.00
Water
Sewer 1$94,620.00
Page 1 of 2
Deletions Sub Total 1$94,620,00
Page 2 of 2
M1WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00;
Previous Change Orders
Co# DATE AMOUNT
Total $0.00