HomeMy WebLinkAboutContract 44417-A1 CITY SECRETARY AMENDMENT NO. I TO COffrpAcT ljo._4411_ A k SOUTH MAIN STREET DESIGN PROCUREMENT AGREEMENT WHEREAS, Fort Worth South, Inc., ("Developer") and the City of Fort Worth, ("City"), entered into a Design Procurement Agreement (City Secretary No. 44417, M&C C-26214) regarding certain improvements to South Main Street from Vickery Blvd. to Magnolia Avenue in the City of Fort Worth, including the realignment of water and sanitary sewer facilities, roadway reconstruction, installation of streetscape amenities in a context sensitive approach and related drainage improvements (the"Project"); and WHEREAS, Developer engaged the services of Dunaway Associates, L.P. ("Dunaway" or "Engineer") to complete a detailed conceptual design study, working closely with City Staff, to provide for the final design and preparation of construction plans for the Project; and WHEREAS, as design of the Project has progressed, additional water and sanitary sewer facilities and infrastructure improvements have been identified; and WHEREAS, Developer has executed an amendment with Engineer to provide for the design of the additional water and sanitary sewer facilities and infrastructure improvements ("Amendment"); and WHEREAS, Staff has reviewed both the scope, fee, and schedule for the work for the additional water and sanitary sewer facilities and infrastructure improvements design and find them to be fair and reasonable; and WHEREAS, City and Developer intend to amend the Infrastructure Construction Agreement to provide for the reimbursement to Developer from the City for the additional costs related to the Amendment. NOW, THEREFORE, for and in consideration of the covenants and conditions contained herein, the City and the Developer do hereby agree as follows: General Requirements A. The Amendment will generally consist of the design of the additional water and sanitary sewer facilities and infrastructure improvements as described on m C-) m Attachment A hereto. mB. Developer has amended its Engineering Contract with Dunaway to reflect v the Amendment attached hereto as Attachment B. C. City agrees to reimburse Developer for all additional engineering drawings, Cz o studies, renderings, contract specifications, estimates, and other documents, EOFFICIAL ECORD CFW-EFFW, I nc. Amendment 1 to Design Procurement Agreement ETARY ge 1 of 3 HS TX related to the Amendment in an amount not to exceed $39,980.00. Upon payment to Developer, all designs, drawings, specifications, documents, related to the Amendment whether in hard copy or in electronic form, shall become the property of the City. D. All other terms of the original Design Procurement Agreement not specifically amended or altered herein remain in full force and effect. ACCORDINGLY, the City, through its Assistant City Manager, and Developer, through its President, have each caused this instrument to be executed in multiple counterparts to be effective as of the date subscribed by the Assistant City Manager. FORT WORTH SOUTH, INC. CITY OF FORT WORTH By: Paul F. Paine Fernando Costa President Assistant City Manager Date: 2_��^ Date: ! /3 0 0°°x`2► ° ATTEST: o (� `g 070 $0- Mary J. Kayser 0-.' °°�. City Secretary �xAS Recommended by: Water Department Transportation& Public Works Department �0�' a N/A Andrew T. Cronberg, I eri Director Douglas W. Wiersig, P.E. Water Department Director Approved as to Form & Legality: M&C No. Date: Douglas W. Black Assistant City Attorney OFFICIAL RECORD CITY SECRETARY FT.WORTH,TX CFW-EFFW, Inc. Amendment 1 to Design Procurement Agreement Page 2 of 3 List of Attachments to this Agreement Attachment A—Description of Amendment Features Attachment B—Amendment to Engineering Contract [follows] CFW-EFFW, Inc. Amendment 1 to Design Procurement Agreement Page 3 of 3 DUNAWAY/ IATTACHMENT "A" DA No. 6000417.003 October 9, 2014 Mr. John Kasavich, P.E. Project Manager City of Fort Worth Water Department Fort Worth, Texas 76102 Reference: Amendment No. 2 South Main Street—Additional Water& Sewer Design Services City Project No. 02113 Dear Mr. Kasavich: Dunaway Associates, L.P. (Dunaway) is pleased to present this Amendment No. 2 for the following additional services that are beyond our original scope of services. Dunaway proposes to provide additional water and sewer design services for South Main Street. Based on our e-mail correspondence and meetings,we believe the following scope of services will meet your needs for this project. SCOPE OF WORK 1. Extension of 16-inch Water Line A. north to 30-inch Water Line at Vickery Boulevard — Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway revised the water layout for final construction plans at South Main Street and Vickery Boulevard. This area was not included in the original water design scope of work and the original scope only included connecting to existing 12-inch water line on South Main Street. 2. Proposed 20 LF of 30-inch and 24 LF of 12-inch Water Line at Vickery Boulevard to the North—Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway revised the water layout for final construction plans at South Main Street and Vickery Boulevard. This area was not included in the original water design scope of work and the original scope only included connecting to existing 12-inch water line on South Main Street. 550 Bailey Avenue,Suite 400 F Fort Worth,lexos 76107 N lel:817.335.1 121 N Fox:817.336 7437 4c cP!navm_yascr 'ate-.�­rn • Amendment No. 2 South Main Street—Additional Water & Sewer Design Services October 9, 2014 Page 2 3. Proposed 152 LF of 10-inch DIP Sanitary Sewer Line G East on Vickery Boulevard — Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, and conflicts with the proposed extended 16-inch Water Line A, Dunaway revised the sewer layout for final construction plans at South Main Street and Vickery Boulevard. This area was not included in the original sanitary sewer design scope of work and the original scope only included connecting to existing 10-inch sanitary sewer line on Vickery Boulevard. 4. Proposed 267 LF of 8-inch Sanitary Sewer Line F. East on Leuda Street— Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, and conflicts with the existing 30-inch Water Main on Leuda Street, Dunaway revised the sewer layout for final construction plans at South Main Street and East Leuda Street. This area was not included in the original sanitary sewer design scope of work and the original scope only included connecting to existing 8-inch sanitary sewer line on East Leuda Street. The construction plans, and specifications are included with the South Main Street plan submittal currently under advertisement by City staff. 5. Conflicting Review Comments — Multiple conflicting comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth are listed below. - Relocating proposed 16-inch gate valves - Removal of proposed 12-inch ring connection at Leuda Street - Removal of proposed 16-inch Blow Off and Air Release Valves - Proposed additional pressure plugs for testing at all east/west water line connection - Pipe material modifications (PVC to DIP) (SDR-26 to DIP) Dunaway revised all items for final construction plans. 6. Proposed Traffic Detour Plans as part of Construction Sequencing — Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway provided traffic detour plans for final construction plans of South Main Street construction sequencing. This item was not included in the original scope of work and the original scope only included traffic control to be followed by City of Fort Worth specification 34 71 13. 7. Revisions to City of Fort Worth Embedment and Trench Repair Details for Water and Sewer_Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway combined City of Fort Worth details D-520, D001, D003, D101, D102, D103, D201 for final construction plans of South Main Street. This revision was not included in the original scope of work and the original scope only included using the provided City of Fort Worth details as provided on Buzzsaw. 550 Bailey Avenue,Suite 400&Fort Worth,Texas 76107 0 Tel:817,335.1121 B Fox:61 7.335.7d37 @ dunowayossociotes.com • Amendment No. 2 South Main Street—Additional Water& Sewer Design Services October 9, 2014 Page 3 8. Additional Meetings with the Water Department and Water/Sewer Field Op Crew — Additional meetings with the Water Department and Water/Sewer field op crew with the City of Fort Worth. Dunaway addressed above items 1 thru 7 as a result of additional meetings for final construction plans of South Main Street. FEE Dunaway proposes to provide the above described scope of work for a LUMP SUM fee of $39,980. Only those services specifically mentioned in the Scope of Work section are offered as a part of this proposal. A summary of the total project is as follows: Fort Worth South, Inc. $487,210 Water Department $160,000 Original Contract Total $647,210 Amendment#1 (Fort Worth South, Inc.) $207,000 Amendment#2 (Water Department) $39,980 Total Project with Amendments 1 &2 $894,190 Please review the enclosed information and do not hesitate to call me if you have any questions or require additional information regarding this proposal. Sincerely, DUNAWAY ASSOCIATES, L.P. Jeff Davis, P.E. Jason A.Williamson, P.E. Associate/Director Vice President of Operations Collin and Denton County Operations 550 Bailey Avenue,Suite 400 4 Fat Worth,texas W07 4 iel.817.335.1121 0 Fax.817.335.7437 R dun0W0yQSS0dotes.c0m South Main Street Contract Amendment No. 2 Water&Waste Water Design Services Task Proposed Water Dept. Revised Markup 1 $5,400 $5,400 $5,400 2 $5,230 $5,230 $5,230 3 $5,280 $5,280 $5,280 4 $7,500 $7,500 $7,500 5 $9,420 $0 $7,420 6 $6,540 $0 $3,270 7 $1,130 $1,130 $1,130 8 $6,500 $3,000 $4,750 $47,000 $27,540 $39,980 Total 58.60% 85.06% % of Calculated Fee 41.40% 14.94% % Reduction of Calculated Fee Note: Water Dept. reduced base design contract by $60K in 2013. 0 0 0 0 p O O O 0 0 0 O m W O N t- M to M 0000 tf N N L!1 'd' N --� r, 01 O1 01 �n m ui t- t- m H V m ai ci a a vi. <n in vl� vl� vl� vl� vl� m m m a ai LL ❑ 03 m m m C3 r4 m -4 H O) v Q n U y 61 0o O V M lA N N � W O O w r011 N rr4 H O -:r kq y� m 07 x to M M Ln Lo oo l!1 Ln O to O 0 O p p CN O L ❑ CL -:r O U R p O C r,4 O d 01 �o f0 Y 4! 01 dD an 3 m � v v an > m 3 3 m v Y � Y W N U U_ d U y 0 O. > U > In Y O � Y 00 W A Y 7 U C O7 0) O w J O C 7 OJ Q 3 o L m c L v O U O) O N t M C Vogl vYi f0 N O N c Y Y Z u t a m 3 u E w E LL N E °c �n Z. C 'o c d N a m o. E y C bun; != vi of 'O N C c m L QJ f0 L N Y c O N i d a0+ U C U N O 3 3 a`i 3 m c . p o� � E � Y m m oo E o M w o o LL 3 {A 06 U 0 O U N 00 C C 01 C O LL LL v T Y 0 .O `+ l0 LL J J Y 4! N N n L U 01 Q �- O Ln t0 0 E L O q N m Y Y Y y 0 G O v d v u d o O ❑ N i+ C O O 0 y M N 0_ CL 0- Q C QX O O O U O w LL d d a I o! I Q E ri - a 00 .� ry m v �n to n oo w 0 o m Z m LL ATTACHMENT "B" 4 DUNAWAY AUTHORIZATION FOR CONTRACT AMENDMENT No. 2 Date: October 9,2014 Amendment No.: 2 Dunaway No.: 8000417.003 Project Name: South Main Street—Plan Design—City Project No.02113—City Secretary Contract No.44417 Attn: Mr.Paul F.Paine Client: Fort Worth South,Inc. Address: 1606 Mistletoe Boulevard, Fort Worth,TX 76104 Hereby requests and authorizes Dunaway Associates, L.P. (Dunaway)to perform the following additional services: A. Scope of Work 1. Extension of 16-inch Water Line A. north to 30-inch Water Line at Vickery Boulevard — Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway revised the water layout for final construction plans at South Main Street and Vickery Boulevard.This area was not included in the original water design scope of work and the original scope only included connecting to existing 12-inch water line on South Main Street. 2. Proposed 20 LF of 30-inch and 24 LF of 12-inch Water Line at Vickery Boulevard to the North— Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway revised the water layout for final construction plans at South Main Street and Vickery Boulevard.This area was not included in the original water design scope of work and the original scope only included connecting to existing 12-inch water line on South Main Street. 3. Proposed 152 LF of 10-inch DIP Sanitary Sewer Line G. East on Vickery Boulevard — Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, and conflicts with the proposed extended 16-inch Water Line A, Dunaway revised the sewer layout for final construction plans at South Main Street and Vickery Boulevard.This area was not included in the original sanitary sewer design scope of work and the original scope only included connecting to existing 10-inch sanitary sewer line on Vickery Boulevard. 4. Proposed 267 LF of 8-inch Sanitary Sewer Line F. East on Leuda Street—Per comments from mthe review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, and conflicts with the existing 30-inch Water Main on Leuda Street, Dunaway revised KI the sewer layout for final construction plans at South Main Street and East Leuda Street. This C area was not included in the original sanitary sewer design scope of work and the original scope rM only included connecting to existing 8-inch sanitary sewer line on East Leuda Street. The construction plans, and specifications are included with the South Main Street plan submittal _ currently under advertisement by City staff. Z G:1Pmdudbn1 000400180004171Correspondenoe 1003\Final Submitted Proposat1B000417.003-South Main St.-Plan Design-Revised CA No.2-2014- iQ011.docu 550 Bailey Avenue,Suilo 400 F Foil Wodh,lrixas 76107!;lol:817.335.1121 A,Fox:817.335 7437 B dunorrayussocialos.com f Authorization for Contract Amendment October 9,2014/Page 2 5. Conflictina Review Comments—Multiple conflicting comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth are listed below. - Relocating proposed 16-inch gate valves - Removal of proposed 12-inch ring connection at Leuda Street - Removal of proposed 16-inch Blow Off and Air Release Valves - Proposed additional pressure plugs for testing at all east/west water line connection - Pipe material modifications(PVC to DIP)(SDR-26 to DIP) Dunaway revised all items for final construction plans. 6. Proposed Traffic Detour Plans as part of Construction Sequencing — Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway provided traffic detour plans for final construction plans of South Main Street construction sequencing.This item was not included in the original scope of work and the original scope only included traffic control to be followed by City of Fort Worth specification 34 71 13. 7. Revisions to City of Fort Worth Embedment and Trench Repair Details for Water and Sewer— Per comments from the review meeting with the Water Department and Water/Sewer Field Op crew with the City of Fort Worth, Dunaway combined City of Fort Worth details D-520, D001, D003, D101, D102, D103, D201 for final construction plans of South Main Street. This revision was not included in the original scope of work and the original scope only Included using the provided City of Fort Worth details as provided on Buzzsaw. 8. Additional Meetings with the Water Department and Water/Sewer Field Op Crew—Additional meetings with the Water Department and Water/Sewer field op crew with the City of Fort Worth. Dunaway addressed above items 1 thru 7 as a result of additional meetings for final construction plans of South Main Street. Additional Services(not included in this contract amendment): The following is a list of some, but not necessarily all, of the services that can be useful or required tior a project of this type.The listed services have not been included in the scope of work. Dunaway can provide or sub-consult many of these services if desired by the Client.If the Client determines any of these services is desired, Dunaway can either amend this document to incorporate the desired service or services or recommend other actions to cover the needs as expressed. 1. Bid phase services. 2. Construction administration. 3. Subsurface utility engineering drawings are not included. 4. Construction staking. 5. Surveying services such as as-built surveys, easements by separate instrument, and construction surveys. 6. Soil Investigation/Laboratory testing is not included. The City will provide this service. 7. Dunaway does not provide construction inspection services,so this task is not included. 8. Construction surveying. 550 Bailey Avenue.Suite 400 0 Fcxl Wodh.lexos 76107 @ lei.017.335.1121 Q Fax.817.335.7437 @ dunawayassouales.com Authorization for Contract Amendment October 9,2014/Page 3 Compensation: $39,980.00 Lump Sum Services Notes: Services covered by this authorization shall be performed in accordance with the Dunaway "Standard Terms&Conditions,"under the original Agreement dated May 1,2013. PRIOR CONTRACT AMOUNT $854,210.00 Lump Sum&Hourly NTE Services CONTRACT AMENDMENT AMOUNT: $39,980.00 Lump Sum Services REVISED CONTRACT AMOUNT: $894,190.00 Lump Sum&Hourly NTE Services B. Fee Breakdown Summary Fort Worth South,Inc. $487,210 Water Department $160,000 Original Contract Total $647,210 Amendment#1(Fort Worth South,Inc.) $207,000 Amendment#2(Water Department) $39.980 Total Project with Amendments 1 &2 $894,190 Respectfully submitted, DUNAWAY ASSOCIATES, L.P., Agreed&Accepted a Texas limited partnership FORT WORTH SOUTH,INC. C_" By: -r�F. Jeff Davis,P.E. / F Na jyo Asso ' to 1 'rector Name: I Colli enton County Operations JeN Title: na T Date: 19— J4iqn A.Williamson, P.E. tic(e President JMD/mlb/th 550 Bailey Avenue.Suite 400 4 Forl Wcntn,lexos 76107 a fel:811.335A 121 a Fax:817.335.7437 D duxnvoWssociotes corn