AMENDMENT NO. 1
STATE OF TEXAS 3 CITY SECRETARY CONTRACT
(No M&C Needed)
COUNTY OF TARRANT 3
WHEREAS, the City of Fort Worth (City) and BLACK & VEATCH, L.L. P. ,
(Engineer) made and entered into City Secretary Contract No. 24590, (the
Contract) which was authorized by the City Council by M&C C-17213 on the
12TH day of JANUARY, 1999; and
WHEREAS, the Contract involves engineering services for the following
project :
CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR NORTHSIDE III WATER
TRANSMISSION MAINS.
WHEREAS, it has become necessary to execute Amendment No. l to said
Contract to include an increased scope of work and revised maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through their
duly authorized representatives, enter into the following agreement which
amends the Contract :
1.
Article I of the Contract is amended to include the additional
engineering services specified in a proposal letter dated March 9, 2000, a
copy of which is attached hereto and incorporated herein. The cost to City
for the additional services to be performed by Engineer total $14, 740 . 00.
2.
Article II of the Contract is amended to provide for an increase in
the maximum fee to be paid to Engineer for all work and services performed
under the Contract, as amended, so that the total fee paid by the City for
all work and services shall not exceed the sum of $65, 280 . 00 .
REC00,E/D
�ll� 5E�c ► °U
3.
All other provisions of the Contract which are not expressly amended
herein shall remain in full force and effect.
EXECUTED on this the ��f day of
2000, in Fort Worth, Tarrant County, Texas .
APPROVAL RECOMMENDED: APPROVED:
c,
�1A� f kA
Vv- —40t —E
A. Douglas Rademaker, P.E. Mike Groomer
Director, Department of Assistant City Manager
Engineering
B1acK & Veatch, L.L. P.
ENGINEER
*oriTa
Pearson, City Secretary
0-17-00By: �-y� r
Name: Randy McIntyre P.E.
100E. 15TH Street
Suite 600 Contract Authorization
Fort Worth, Tx. 76102
Date
APPROVED AS TO FORM AND LEGALITY:
Gary Steinberger
Assistant City Attorney
2 PERU
r-.
BLACK & VEATCH
100 E.15th Street Black&Veatch Corporation
Suite 600
Fort Worth,Texas 76102 USA
City of Fort Worth B&V Project 62603.500
Northside III Water Main B&V File A-1.0
PW77-060770140340 March 9, 2000
Ms. Dena Johnson, P.E.
Fort Worth Department of Engineering
1000 Throckmorton
Fort Worth, Texas 76102
Subject: Contract Amendment 1 - City Contract
24590
Dear Ms. Johnson:
We are respectfully requesting a contract amendment for the above referenced project in the
amount of$14,740.00. The amendment request is for additional construction management,
field inspection and conflict resolution that was required to address design discrepancies,
unknown underground conditions and operational problems encountered with existing water
utilities. In addition, the City has requested that Jackson Construction Company extend this
waterline from the intersection of Bowman Roberts Road and Bailey Boswell Road to Lake
County Estates west of Boat Club Road.
This amendment is required due to changes in our scope of work during execution of this
contract. The change in the nature of the work required more construction management and
field inspection. Resolution of conflicts also required additional hours by more experienced
and higher compensated staff than budgeted in the original scope of work.
The following is a summary of the major project impacts:
1. The engineering design omitted 150 feet of 30-inch tunnel bore from the bid proposal
form. In an effort to reduce the impact of this omission, we sought approval for
alternative construction methods from Tarrant County and processed required
change orders with the construction contractor.
2. The engineering design included incorrect coordinates for the new fencing
boundaries on the McNeil and Elkins properties. Installation of the fencing as shown
on the design drawings would have resulted in the inclusion of property boundaries
that were intended but not obtained by boundary documents. Identifying this land
rights discrepancy and determining the differences from intended boundaries and
actual boundaries obtained required additional project management time.
3. Service lines for the Kenneth Reed property were not included in the engineering
design drawings. We negotiated many proposal cycles with the contractor before
agreeing to get this work completed.
the imagine•build company-
I(,��
,. J4PP� Yeo
City of Fort Worth B&V Project 62063.500
W.D. No. PW77-060770140340 March 9, 2000
Page No.2
4. The pipe at the terminus of the 16-inch line on Bob Hanger St. was found to be
ductile iron pipe (DIP) rather than reinforced concrete cylinder pipe (RCCP) as
indicated on the drawings. The pipe connection was redesigned in the field.
5. The location of utilities at the tie-in at the intersection of Old Decatur and Boswell
Road was different than indicated on the drawings resulting in change orders and
field design changes.
6. An existing water line that was connected to the new line was found to be
stagnate and required significant coordination of activities to clean, flush,
chlorinate, sample, test and re-testing to improve conditions in the existing line
and new line. This work had to be coordinated between Fort Worth Water
Department field operations, plant operations and laboratory, and the contractor.
In addition Black & Veatch conducted the field sampling activities to resolve this
issue.
7. Significant Construction Management time was required to address damage
claims at the Walton property for allegations of improper drainage conditions due
to construction activities. Our preconstruction videotape of the property indicated
no property impacts from construction activities. Several meetings were required
regarding the final restoration of this property.
8. Construction management and construction inspection for the extension of the
water line to Lake Country Estates.
The detailed breakdown of the additional labor charges for Items 1 through 7 is contained in
the attached table.
Actual Actual Budgeted Budgeted Actual
Employee Billing Hours
Name Title Rate to Date Cost to Hours Cost Verses
Date Budgeted
D. Cherry PIC $140/hr 0 $0 4 $560 <$560>
R. McIntyre PM $100/hr 25 $2,500 16 $1,600 $900
C. Haynes CM $90/hr 221 $19,890 120 $10,800 $9,090
G. Bishop& Field $60/hr 355 $21,300 420 $25,200 <$3,900>
C. Dormier Insp.
Subtotal $43,690 $38,160 $5,530
05FR"C�_V"f�A FI�C��D
��o C+IL�J.'Ii�lIl14 ULSi��o
City of Fort Worth B&V Project 62063.500
W.D. No. PW77-060770140340 March 9, 2000
Page No.3
We have attached a copy of our initial proposal letter for corroboration with the budget letter
amount shown in the previous table. As-Built redline drawings, copies of our documentation
and project files need to be produced and submitted in addition to the above hours.
The detailed breakdown of projected labor charges for the extension of the waterline to Lake
Country Estates is as follows.
Employee Title Billing Rate Budgeted Hours Total Cost
Name
C. Haynes Const. Mgr. $90/hr. 20 $1,800
C. Dormier or Const. Inspector $75/hr 75 $5,625
Gene Bishop
Total 95 $ 7,425
We estimate that approximately $400 worth of vehicular and other expenses will be required
for Item 8. In addition, we are required to provide 15% MWBE participation. We propose
Terra Mar for testing services and Accuracy Plus for clerical services to fulfill the additional
obligations for Item 8, in the amount of $1,385.00
Thus, the total charges shall be as follows:
Items 1 — 7: $ 5,530.00
Item 8 $ 9,210.00
Total $14,740.00
Construction contract change orders will be approximately $500,000 or 25% of cost for this
water transmission main project. Our additional time and contract amendment request on
this project represents approximately 3% of the construction contract change orders.
Thank you for your consideration of this contract amendment request, and should you have
any questions, please feel free to contact us.
Sincerely,
BLACK & VEATCH
Randy McIntyre, P.E.
Project Manager
Cc: Doo Kim, P.E., Fort Worth Water Department
Clay Haynes, B&V
FOP,TWOF,TH
TO: A.Douglas Rademaker,P.E.
FROM: Dena Johnson,P.E.
DATE: March 14,2000
RE: NORTHSIDE III WATER TRANSMISSION MAINS
/As requested by the Water Department Black&Veatch Corporation,has submitted a proposal to provide
J/cconsstttructtio�n management and inspection services for Northside III Transmission Mains.
Black&Veatch Corporation,has submitted a proposal to perform the additional services for a fee not to
exceed $14,740.00 increasing the contract fee amount to $65,280.00.
Staff considers this fee to be fair and reasonable for the scope of services proposed. Please authorize this
additional design by your signature on the attached Contract Amendment form.