Change Order Request Breakdown
ProjectNamel Bridge Repair&Rehabilitation @ S.Main(2013-24) CitySec# 1 45086
Client Project#(s) GG01-539590-0202003
Change Order Submittal# Date 11/20/2014
Contract Time
Dept. T/PW Totals CD
Original Contract Amount $766,875.00 $766,875.00 120
Extras to Date $35,812.00 $35,812.00 9
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $802',687.00, $802,687.00 129
Amount of Proposed Change Order99,895.a9 $99,895.59 101
Revised Contract Amount $902,582.59 $902,582.59 230
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary) $99;895.59 $99,895.59
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 17.70%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $958,593.75
JUSTIFICATION (REASONS)FOR CHANGE ORDER
IBC is requesting additional Mob/Re-Mob/rental equipment standby costs for IBC and it's Driller S&W Foundation due to the delay of the
approval of the temporary shoring by the railroads and the need for a crossing permit by the BNSF railroad to complete the work on their side of
the project. We will be requesting 101 calendar days as well as 14 railroad flagger days be added to the project which will extend contract time
and the required flagger days till 11/21/14.We will also be requesting the additional quantities that have over run for the project. these
quantities have been quantified by the inspector of the City of Fort Worth and were OK'd by him to continue with said increases as we were
completeing the work. Her is the break down by line item.GENRERAL-1A New- Railroad Coordintaion-This is the time costs IBC has spent
working with the railroads,above and beyond what was required in the original contract.(Crossing Permit). 2 INC-Railroad Flagmen-The
extra flagger days required to complete the project due the delay from the aquisition of the crossing permit. 3 INC-CL C Conc(Crash Wall)-
This is the amount of extra concrete needed to raise the top of the crash walls to meet the 12'minimum for the top of the crash wall to be
above the rail elevation. TXDOT 1 INC-Temp Spl Shoring-This quantity is measured in place quantity,and approved by the city inspector,
of the shoring required to install the crash walls to the appropriate elevation per plan. 2 INC-30"Drill Shaft-This is the extra quantity needed
to be drilled to get to the required penetration into the hard gray shale. 4 INC-Conc Str Rep(Horiz)-This is the extra quantity for the conc
repair as directed by the city and engineer. 5 INC-Clean&Seal Existing Joints-This is the extra quantity for the cleaning&sealing of
existing joints as directed by the city and engineer. 10 INC-Conc Rep at Abutment backwall-This is the quantity for the additional concrete
repair at the south bridge abutment backwall as directed by the city and engineer. 11 New-IBC&Subs(MOB/DE-MOB)-This is a new item
to cover IBCs'and our drilling sub-contractors de-mobilization and re-mobilization due to the required crossing permit that was not discussed at
the pre-construction meeting or part of the original contract. 12 New-The cost of the required crossing permit from BNSF to complete the
planned work. We are also requesting the additional day to the contract to get us to November 21st,2014. This will be the day we will be
substantially complete.
rn
C-) �• °
rn
mo $ �' OFFICIAL RECORD
Y CITY SECRETARY
A FT. WORTH, TX
J' er,
,t
PO r WORTH City of Fort Worth
Change Order Additions
Project Name I Bride Repair&Rehabilitation S.Main 2013-24 City Sec# 45086
ClientProject# I GGOI-539590.0202003
Change Order Submittal# 0 Date 11/20/2014
ADDITIONS
ITEM DESCRIPTION DEPT ry Unit Unit Cost Total
ew Railroad Coordinabon
2 INC Railroad Flagmen T/PW 14.00 F 900.00
3 IN CL one(CrashWafl) TIPW 10.3 CY 475.00
TXDOT /PW
1 INT--Temp SpI Shoring T/PW 861.00 SF $50.00
2 INC 30"Drill Shaft T/PW 4.00 LF $300.00
--T-INC Conc Str Rep(Horizontal) /PW 76.78 SF 100.00
5 INC Clean-&Seal Exist Joints T/PW 35.00 LF $75.00
1 IN Conc Repair at Abutment Backwall T/PW 21.00 F $200.00
11 New IBC Mob/DeMob T/PW 1.00 L 16,112.09
12 New BNSF Crossing Permit T/PW 1.00 LS $1,000.00
T/PW $99,895.59
Sub Total Additions 99,895.59
Change Order Additions Page 1 of 1
9UR_ T�H City of Fort Worth
Change Order Deletions
Project Name I Bridge Repair&Rehabilitation @ S.Main 2013.24 City Sec# 45086
Client Project# I GG01-539590-0202003
Change Order Submittal# �J Date 11/20/2014
DELETIONS
ITEM UESCRIPTION DEPT ry Unit Unit Cost I ota
T/PW $0.00
Sub Total Deletions
Change Order Deletions Page 1 of 1
}
M/SBE Breakdown for this Change Order
MISBE Sub Type of Service Amaunt for#his CO
N/A N/A N/A
Total $Q.'00 .
Previous Change Orders
C0# DATE AMOUNT
1 5/28/2014 $35,812.00
Total $351312.04
,g
City of Fort Worth
Departmental Request for Waiver
Of MBE/SBE Subcontracting/Supplier Goal
V-7
rri
TPW $99,895.59 11/2M42014
DEPARTMENT NAME: ESTIMATED COST / P POSAL DATE
IZ
BRIDGE REPAIR AND REHABILITATION AT SOUTH MAIN ST(2013-24) GG01 959M202003
NAME OF PROJECT/BID: DCA/PROJECT NO.
a
Tariqul Islam =~:-^^-- 2486 12/24/2014 00
SIGNATURE OF/PROJECT MANAGER EXTENSION DATE NIGP CODE
Prior to advertisement, the contracting/managing department shall determine whether the bid/proposal is one which MBE/SBE
requirements should not be applied. MBE/SBE requirements may be waived upon written approval of the M/WBE Manager. If one
of the conditions listed below exists,the contracting/managing department shall notify the Manager via this form,stating the specific
reason(s)for requesting a waiver.
If the contracting/managing department and the Manager are in conflict over the granting of a waiver, either
may appeal to the City Manager, or designee, and his/her decision is final.
Please Check Applicable Reason:
A. MWBE Office: A waiver of the goal for MBE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the public or administrative emergency exists which requires the goods or
services to be provided with unusual immediacy; or
X B. MWBE Office: A waiver of the goal for MBE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the purchase of goods or services from source(s) where subcontracting or
supplier opportunities are negligible; or
C. MWBE Office: A waiver of the goal for MSE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the application of the provisions of this ordinance will impose an economic
risk on the City or unduly delay acquisition of the goods or services; or
D. MWBE Office: A waiver of the goal for MBE/SBE subcontracting requirements was requested
by the Department and approved by the MWBE Office, in accordance with the M/WBE or BDE
Ordinance, because the MWBE Waiver is solicited based on the sole source information
provided to the MWBE Office by the managing department's project manager.
Justify Commodity or Service Waiver Request:
This is a waiver request for change order.The majority of additional work(mobilization,railroad co-ordination,temporary special shoring etc)Included in this change order needs to be
accomplished by the prkne contractor by Its own crew.Railroad flagman and railroad crossing pemdt fees to be pail directly to Union Padnc and aNSF.There is minknal opportunity to have sub contractor
to perform other additional works included In this change order.
Please use additional sheets,if needed
M/W E OFFICE USE ONLY: `
a4 iL z'SI
Approved Signature o M/ BE Authorized Personnel Date
Not Approved Signature of M/WBE Authorized Personnel Date
Rev.2-20.11
CFW Change Order Approval St-COApp02 Page 1 of 3
r
Routin4
Assigned To: Due Date:
Assigned By: Due Time:
Links 2
fortworthgov/Infrastructure Projects/Bridge Repair and Rehabilitation at South Main (2013-24)/Contractor/Change
Orders/141120 Change Order 2 Breakdownrl.xls
fortworthgov/Infrastructure Projects/Bridge Repair and Rehabilitation at South Main (2013-24)/Contractor/Change
Orders/MWBE Waiver South Main St Bridge (2013-24).Ddf
Aftchme[ft(u►
No Attachments have been added to this form
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 2/9/2015
CFW Change Order Approval St-COApp02 Page 2 of 3
FORT WORTH. city of Fort Worth
�--.�• �---- Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: .COSub02
Change Order No.: St-CO_App�02_ Date Started: ;2015-01-12
.......................... _........................................ ................... _.. ........................................................................_....
__...
City Sec. No.: 45086........._......... ......._.......................................... .....
......_ Date Due: :2015-01-24
-._m..__.._.._._.___...____-...._____.....___...______...
Project Name: Bridge Repair and Rehabilitation at South Main (2013-24)
GG01-539590-0202003 DOE Numbers:
Project Numbers: _.____._____.......................__.....______._.
`DOE No. 7181
---___...._ _ .....................
Project South Main Street Bridge Repair and Rehabilitation
Description: .
Project Manager: Tariqul Islam City Inspector: Richard Salazar _
Contractor: IowaBridge & Culvert, LC
COUNCIL ACTION (If Required):
..................._........................................................................................................._.......................-........._............... _...._...--
M&C Log Name: . _....._._..._.. _
._......._............................. ......_
M&C Number: M&C Date: :
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
-rpyy $ 99,895.59 GG01 539590-0202003 101
_..._.... .........., . _......_.._ .........
Il
Total Cost:'.�.._99 $95•59 _s Total Requested Days: 101
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Forms/Formprint.aspx?SiteId=51500&ProcessId... 2/9/2015
CFW Change Order Approval St-COApp02 Page 3 of 3
Approved: Yes
Comments:
User: Chris Kumnick
Date: 2015-01-14 12:50 PM
Approved: Yes
Comments: This change order is for additional work needed to complete the contract.
User: Tariqul Islam
Date: 2015-01-14 12:55 PM
Approved: Yes
Comments:
'User: Najib Fares
Date: 2015-01-14 1:21 PM
,Approved: Yes
Comments:
User: Andy Anderson
Date: 2015-01-15 4:52 PM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2015-01-30 2:23 PM
Approved: Yes
Comments:
User: Doug Black
Date: 2015-02-06 12:22 PM
Approved: Yes
Comments:
User: Fernando Costa
Date: 2015-02-09 2:23 PM