STANDARD AGREEMENT FOR ENGINEERING RELATED DESIGN SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home-rule
municipality (the "CITY"), and Kimley-Horn and Associates, Inc., authorized to do business
in Texas, (the "ENGINEER"), for a PROJECT generally described as: E. Lancaster Traffic
Signal Bid Package and Construction Phase Services.
Article I
Scope of Services
A. The Scope of Services is set forth in Attachment A.
Article II
Compensation
A. The ENGINEER's compensation shall be in the amount not-to-exceed
$36,745.00 as set forth in Attachment B.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT, Invoices are due and payable within 30 days of receipt.
(3) Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
RevisePage 1 of Date:: 9/24/2014 OFFICIAL RECORD
CITY SECRETARY
SFT.WORTH9 TX RECEIVED FEB 12 2015
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5) If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The standard of care applicable to the ENGINEER's services will be the
degree of skill and diligence normally employed in the State of Texas by
professional engineers or consultants performing the same or similar
services at the time such services are performed.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 2 of 16
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on-site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
the agreement between CITY and ENGINEER be construed as requiring
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9(24/2014
Page 3 of 16
ENGINEER to make exhaustive or continuous on-site inspections to
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on-site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
(3) When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on -the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9124/2014
Page 4 of 16
matters at issue between the CITY and the construction contractor that
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was Finally constructed. The ENGINEER is not responsible for
any errors or ornissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity Ordinance No.
20020-12-2011, as amended, the City has goals for the participation of
minority business enterprises and/or small business enterprises in City
contracts. Engineer acknowledges the MBE and SBE goals established for
this contract and its accepted written commitment to NIBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of Fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 5 of 16
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
(3) ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an insured under the CGL, using
ISO additional insured endorsement or a substitute providing
equivalent coverage, and under the commercial umbrella, if any.
This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the
CITY. The Commercial General Liability insurance policy shall
have no exclusions by endorsements that would alter or nullify.-
premises/operations,
ullify:premises/operations, products/completed operations, contractual,
personal injury, or advertizing injury, which are normally contained
within the policy, unless the CITY approves such exclusions in
writing.
ii. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
liability arising out of "any auto", including owned, hired, and non-owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non-owned is
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 6 of 16
acceptable.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation —ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — the ENGINEER shall maintain professional
liability, a claims-made policy, with a minimum of $1,000,000.00 per
claim and aggregate. The policy shall contain a retroactive date prior to
the date of the contract or the first date of services to be performed,
whichever is earlier. Coverage shall be maintained for a period of 5 years
following the completion of the contract. An annual certificate of
insurance specifically referencing this project shall be submitted to the
CITY for each year following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be delivered to the CITY prior to ENGINEER
proceeding with the PROJECT.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, as its interests may appear. The term CITY shall
include its employees, officers, officials, agents, and volunteers as
respects the contracted services.
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 7 of 16
d. Any failure on part of the CITY to request required insurance
documentation shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A-V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first-dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims-made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims-made.
k. Coverages, whether written on an occurrence or claims-made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
final payments.
I. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 8 of 16
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER. When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date: 9/24/2014
Page 9 of 16
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City-Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights-
of-way, and access necessary for the ENGINEER's services or PROJECT
construction.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 10 of 16
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto -the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third-Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 11 of 16
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third-party beneficiaries.
(3) The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third-party beneficiary rights under this Agreement.
(4) Nothing contained in this section V.H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY will ensure that Builders Risk/Installation insurance is maintained
at the replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3) The CITY will specify that the Builders Risk/installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of -the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 12 of 16
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed From the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the Final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated only by the City for convenience on
30 days' written notice. This AGREEMENT may be terminated by either the
CITY or the ENGINEER for cause if either party fails substantially to perform
through no fault of the other and does not commence correction of such
nonperformance with in 5 days of written notice and diligently complete the
correction thereafter.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 13 of 16
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
C.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses. The
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify, hold harmless, and defend the CITY
against liability for any damage caused by or resulting from an act of
negligence, intentional tort, intellectual property infringement, or
failure to pay a subcontractor or supplier committed by the ENGINEER
or ENGINEER's agent, consultant under contract, or another entity
over which the ENGINEER exercises control.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Interpretation
Limitations on liability and indemnities in this AGREEMENT are business
understandings between the parties and shall apply to all the different
theories of recovery, including breach of contract or warranty, tort including
negligence, strict or statutory liability, or any other cause of action, except for
willful misconduct or gross negligence for limitations of liability and sole
negligence for indemnification. Parties mean the CITY and the ENGINEER,
and their officers, employees, agents, and subcontractors.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 14 of 16
I. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
J. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
K. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
Article VII
Attachments, Schedules, and Signatures
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. The following attachments
and schedules are hereby made a part of this AGREEMENT:
Attachment A— Scope of Services
Attachment B — Compensation
Attachment C —Amendments to Standard Agreement for Engineering Services
Attachment D — Project Schedule
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014
Page 15 of 16
Executed and effective this the i'_� ay ofO, 20)
BY: BY:
CITY OF FORT WORTH ENGINEER
Kimley-Horn and Associates, Inc.
Fernando Costa Glenn Gary, P.E.
Assistant City Manager Senior Vice President
Date:T Date: / - 30- 201S
APPROVAL RECOMMENDED:
By:
CJDI
s W. Wiersig, P.E.
`� r, Department of
sportation/Public Works
APPROVED AS TO FORM AND M&C No.: N
LEGALITY
M&C Date:
By:
Dou . Black
Assistant City Attorney
ATTEST:
Vg O
8 X
a
lQl
aryJ. Kays i' �
City Secreta d�$
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:9/24/2014 OFFICIAL RECORD
Page 16 of 16 CITY SECRETARY
FT. WORT14 TX
ATTACHMENT "A"
Scope for Engineering Design Related Services for
E. Lancaster Traffic Signal Bid Package and Construction Phase Services
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
OBJECTIVE
The objective of this project is to prepare a bid package for the construction of three (3)
traffic signals and for construction phase services.
WORK TO BE PERFORMED
Task 1. PLAN SET PREPARATION.
1.1. Prepare Plan Set
• ENGINEER will prepare the following sheets to develop the final plan set for
bidding:
- Cover Sheet
- Sheet Index
- General Notes
- Quantity Summary Sheet
- Applicable City standard details
1.2. DWF Files
ENGINEER will prepare DWF files of the plan set to upload to BuzzSaw for
bidding.
ASSUMPTIONS
0 Paper copies of the plans will not be made available to potential bidders, only
.pdf versions will be distributed.
DELIVERABLES
A. PDF Plan Set (22" x 34").
B. Paper Plan Set (22" x 34"), as requested by CITY.
Task 2. PROJECT MANUAL PREPARATION.
2.1. ENGINEER will prepare the preliminary Project Manual for the project and submit to
the CITY for review.
2.2. ENGINEER will meet with the CITY to review comments on the Project Manual and
Plan Set, and make the necessary changes. The final Plans and Project Manual will
then be uploaded to BuzzSaw for advertisement.
City of Fort Worth,Texas
Attachment
PMO Release Date:07.23.2012
Page 1 of 6
ASSUMPTIONS
• None.
DELIVERABLES
C. PDF Project Manual.
D. Paper copy of project manual, as requested by CITY.
Task 3. BIDDING PHASE SERVICES.
3.1. Bid Support
• ENGINEER will upload the plans and project manual onto BuzzSaw for
access to potential bidders.
— Proposal Form will be uploaded in .xIs format.
— Plan sets will be uploaded to BuzzSaw in two formats, pdf and Awf files.
The pdf will consist of one file of the entire plan set. The dwf will
consist of individual files, one for each plan sheet, and will be numbered
and named in a manner similar to that of the plan set index.
• ENGINEER will maintain a Plan Holder List on BuzzSaw.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and
requests and the response thereto. The log shall be housed and maintained
in the project's Buzzsaw folder titled Request for Information. The
ENGINEER will provide technical interpretation of the contract bid documents
and will prepare proposed responses to all bidders' questions and requests,
in the form of addenda. The ENGINEER shall upload all approved addenda
onto Buzzsaw and mail addenda to all plan holders.
• Attend the prebid conference in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of
prospective contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid opening in support of the CITY.
• Incorporate all addenda into the contract documents and issue conformed
sets.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23,2012
Page 2 of 6
ASSUMPTIONS
• The project will be bid only once and awarded to one contractor.
• Paper copies of the plans or project manual will not be made available to
potential bidders.
• PDF and DWF files will be uploaded to BuzzSaw.
DELIVERABLES
A. Addenda
B. Bid Tabulations
C. Recommendation of award
D. Conformed contract documents, if applicable.
Task 4. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
4.1. Construction Support
• The ENGINEER shall attend the preconstruction conference.
• After the pre-construction conference, the ENGINEER shall provide project
exhibits and attend public meeting to help explain the proposed project to
residents. The CITY shall select a suitable location and mail the invitation
letters to the affected customers.
• The ENGINEER shall visit the project site at requested intervals as
construction proceeds to observe and report on progress.
• The ENGINEER will attend weekly construction progress meeting during the
duration of construction. The ENGINEER will prepare meeting notes with
action items and distribute these to the project team.
• The ENGINEER shall review shop drawings, samples and other submittals
submitted by the contractor for general conformance with the design
concepts and general compliance with the requirements of the contract for
construction. Such review shall not relieve the Contractor from its
responsibility for performance in accordance with the contract for
construction, nor is such review a guarantee that the work covered by the
shop drawings, samples and submittals is free of errors, inconsistencies or
omissions. The ENGINEER shall log and track all shop drawings, samples
and other submittals in Buzzsaw.
• As requested by the CITY, the ENGINEER shall provide necessary
interpretations and clarifications of contract documents, review change
orders, and make recommendations as to the acceptability of the work.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 3 of 6
• The ENGINEER shall attend the "Final" project walk through and assist with
preparation of final punch list.
• The ENGINEER will meet with the CITY and Contractor at the conclusion of
the project to discuss any lessons learned during the project.
42 As-Built Drawings
• The ENGINEER shall prepare as-built drawings from information provided by
the CITY depicting any changes made to the Final Drawings during
construction. The following information shall be provided by the CITY:
- As-Built Survey
- Red-Line Markups from the Contractor
- Red-Line Markups from City Inspector
- Copies of Approved Change Orders
- Approved Substitutions
• The ENGINEER shall modify the Final Drawings electronically and shall place
a stamp on the plans indicating that they represent As-Built Drawings of the
project as constructed. The stamp shall be signed and dated by the
ENGINEER and shall be placed on each plan sheet, whether there are any
revisions on the sheet or not. Each sheet shall clearly indicate all changes
which apply to that sheet by clouding and numbering, or other suitable
means.
• The following disclaimer shall be included with the As-Built stamp:
- These As-Built Drawings were prepared using information provided by
others and represent the as constructed conditions to the extent that
documented changes were provided for recording. The ENGINEER
assumes no liability for undocumented changes and certifies only that
the documented changes are accurately depicted on these drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as As-Built Drawings, on Mylar for record storage. The ENGINEER
may keep copies of the information provided by the CITY for their files, but all
original red-lined drawings shall be returned to the CITY with the Mylars.
• As-Built Drawings shall also be submitted as an Adobe Acrobat PDF format
(version 6.0 or higher)file and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set. Each PDF and DWF file shall
contain all associated sheets of the particular plan set. Singular PDF and
DWF files for each sheet of a plan set will not be accepted. PDF and DWF
files shall conform to naming conventions as follows:
- TPW file name example-W-11 956 1 org47.pdf' where "W-1956" is the
assigned file number obtained from the CITY, "_org" designating the file
is of an original plan set, "47" shall be the total number of sheets in this
file. Example: W-0053-Org3.pdf and K-0320_org5.pdf.
City of Fort Worth,Texas
Attachment
PMO Release Date:07.23.2012
Page 4 of 6
• Both PDF and DWF files shall be uploaded to the project's As-Built Drawing
folder in Buzzsaw.
ASSUMPTIONS
• Ten (10) site visits are assumed.
• Sixteen (16) weekly construction meetings are assumed.
• Two (2) submittal reviews are assumed.
• Five (5) RFI's are assumed.
• Two (2) Change Orders are assumed.
• One copy of full size (22"x34") Mylars will be delivered to the CITY.
DELIVERABLES
A. Public meeting exhibits
B. Response to Contractor's Request for Information
C. Review of Change Orders
D. Review of shop drawings
E. Final Punch List items
F. As-Built Drawings
Task 5. PERMITTING.
ENGINEER will provide permitting support for the CITY to obtain any and all Permits
normally required for a project of this size and type, as follows.
5.1. Texas Department of Transportation (TxDOT) Permit
• Meet, negotiate and coordinate to obtain approval of the agency issuing the
agreement and/or permits.
• Completing all forms/applications necessary.
• Submitting forms/applications for CITY and TxDOT review.
• Submitting revised forms for agency review.
• Responding to agency comments and requests.
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services
described in the tasks above. However, ENGINEER can provide these services, if
needed, upon the CITY's written request. Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be
City of Fort Worth,Texas
AffachmentA
PMO Release Date:07.23.2012
Page 5 of 6
agreed upon in writing by both parties before the services are performed. These
additional services include the following:
• Easement or right-of-way take documents.
• Negotiation of easements or property acquisition.
• Construction management and inspection services
• Performance of materials testing or specialty testing services.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project
as requested by the CITY.
City of Fort Worth,Texas
Attachment A
PMO Release Date:07.23.2012
Page 6 of 6
ATTACHMENT B
COMPENSATION
Design Services for
E. Lancaster Traffic Signal Bid Package and Construction Phase Services
City Project No, 02336
Time and Materials with Rate Schedule Project
1. Compensation
A. The ENGINEER shall be compensated in an hourly amount not to exceed
$36,745 00 as summarized in Exhibit B-1 — Engineer Invoice and Section IV —
Summary of Total Project Fees in performing services enumerated in Attachment
A as follows:
i. Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by the appropriate Labor
Category Rate for the ENGINEER's team member performing the work and
includes all direct salaries, overhead, and profit.
Labor Category Rate as presented in the rate schedule table below is the rate for
each labor category performing the work and includes all direct salaries,
overhead, and profit.
Labor Category Rate
($/hour)
Project Director $225
Project Manager $175
Project Engineer $120
EIT $105
CADD $90
Administrative $75
ii. Non-Labor Expenses. Non-labor expenses shall be reimbursed as Direct
Expenses at invoice or internal office cost.
Direct Expenses (non-labor) include, but are not limited to, mileage, travel
expenses, mail, supplies, printing and reproduction services, other direct
expenses associated with delivery of the work; plus applicable sales, use, value
added, business transfer, gross receipts, or other similar taxes.
iii. Subcontract Expenses. Subcontract expenses and outside services shall
be reimbursed at cost to ENGINEER plus a markup of ten percent(10%).
iv. Budgets. ENGINEER will make reasonable efforts to complete the work
within the budget and will keep the City informed of progress toward that end so
that the budget or work effort can be adjusted if found necessary.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 4
B-1
ATTACHMENT B
COMPENSATION
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may
be adjusted, nor is the City obligated to pay ENGINEER beyond these limits.
ENGINEER may exceed individual task budgets provided the total contract
amount is not exceeded.
If ENGINEER projects, in the course of providing the necessary services that the
PROJECT cost presented in Article 2 of this Agreement will be exceeded, whether
by change in scope of the project, increased costs or other conditions, the
ENGINEER shall immediately report such fact to the City and, if so instructed by
the City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs expended prior
to such increase will be allowable to the same extent as if such costs had been
incurred after the approved increase.
B. The ENGINEER shall be paid monthly payments as described in Section 11 -
Method of Payment.
III. Method of Payment
A. The ENGINEER shall be paid by the City based upon an invoice created on the
basis of statements prepared from the books and records of account of the
ENGINEER, based on the actual hours and costs expended by the ENGINEER
in performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
C. ENGINEER shall prepare and submit invoices in the format and including content
as presented in Exhibit B-1. The cumulative sum of each monthly partial fee
payments shall not exceed the total current project budget including all approved
Amendments.
D. Payment of invoices will be subject to certification by the City that such work has
been performed,
Ill. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department monthly progress reports and
schedules in the format required by the City.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09,2012
Page 2 of 4
B-2
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Kimley-Horn and Bid package, construction $36,745.00 100%
Associates, Inc. phase services
.............
Proposed MBE/SBE Sub-Consultants
Non-MBE/SBE Consultants
TOTAL $ 36,745.00 100%
Project Number& Name Total Fee MBE/SBE Fee MBE/SBE
to
02336 — E. Lancaster Traffic
Signal Bid Package and $ 36,745.00 $0 0%
Construction Phase Services
City MBE/SBE Goal = n/a Consultant Committed Goal = n/a
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09,2012
Page 3 of 4
B-3
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across desired work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 4 of 4
B-4
G 4,
m m
E Rf
0
CD
in
> .2
>
fL
0
>
2 C.
ol 0 V)
IL
o 0 (D
CL
cn
E
P -c
= , f� CL
- v 4tE
0 C3
>
E
E
0 w
C
o c
Z 0 4)
32 >
0
0
IN 12 col I�q
< 0 0 0 N `chi
h h- d
N J CL
00 ED
.16 4) V
2 Q 0
0 9 E
0 E 2m 0
IL -0
c
ti tr
ca
0 4)
CD
m
m CL
CL
cr :or
4) ib ~ 4)
j6
E
IL
U)
E
:E
Co
(0) fn LL
(D E
c c
EJ
cq 4
uj
cn coo
E
m to CL
E z .2 rr
(A 0 4)
z %, >
c c r
. . .
O0 CL
E E
C
il 2cn 11
0 0
CL 9L 5 G 0>a.U.12 tn333333
C�
C!
C,
zz
;$ | ■� f § 40
0
6 <
Z E
IL > LL Q 0
CL
0
ol C,4 a,
IL CN
0
CL 0
'o
m
0
c
L6
ui +z
C� Lu 0 d)
Ln I I F-�
- .9
Ln C3 U) g
1) c
T k } ! 0
Ln k6 ox
n th j)
0
\ e { 7 t , \ 2 to
r
k j
CL
cu 0 a
a E x
E C
o- 0 E 0
,41 f -X 2 m 9 :M, T
.f m m 0
U,
E Z
80 < 0
U)I u u _j EL 0-EL LLJ C-)< w ez
0.
o §
£ 2 -
�
r0
J £
) >
§IL
� ®
) k E
Jf «
22 J-
0
C
E
CL CL
■ ! 3 = q$ E
> 2
C
) k0 8
ui /
\
m a
u ®a / E
« u
0 s
a0 L-
§ ;g ( E 3
,a o5 2E
0( ; ; E
0 - _ «
; ■ ;_ /# ;
E ) k 6a `e E
{ {)7 ! E
2 _ �§ . o §§ m f«
/ c ) (J ) 222 (
0 .� 0 2
5 2 {
CD LL k0
17
a) ƒ \
� \
E a ) §
M § �\ \ `
� A\ :
v § LL
/ 04Q\ « 0
2 � gn« : m
■
0
2$/; E
r § � !
��@�g E | E a�
L.Ake/� 2 k)/LLQ/ a \
0 w
E
e
Jr
\ )
\J
r
4)
0 ®
C
0 0
E
>
0
C,
® o
r
< Ev =
V
>
00
E rn
0 M
> t!
4)
E
0 IL
c
\ /�k � 2 �
E <
ol
4)
<
.0 a! E z
� . \ �o
} ��
f\\
E
E
CL
CL L) § 0
CL
in
)kms)
4, 4) E U.
Er
IL
Fa
a
66, C
0
E, i
U4
CL
r
\ ; \ A
4) uj 05
C, r=72
=0
z
. >.'
� l�3 2 [ )
0 w
'S o a
CL On
0
E 'A-0 E E
c r- :" >
0 (D 2
0> o
0- CLU o .s CL
8
16N-6`- o �+ "Nvmrn nao.n�s o`a � - n� 'www w "wo��l�-w
www w eooar�oi�n L`Npo�c+xrnm w���4 vn
.Ma ti w oe°t
w w w
to
a
F
m O O LO
Wy}x UGp wOa O O wn�yioyyo wwu'iw �y tOw wO wO mC nG�i aLOsi
G
wcoo
RR°o
u'02 ap0mmuwuO ww w
t° Ln U) yOa�
LIJ mm m o
p w w w O W N
p In co
Lu Lu
C
p z
po Qp
N YOi R r a
V4 w M w r n ww M
d w w w w
aY ti
C ~
R
x
Lu O i09 fON w O W
tl7 W
� m
U �
C
2
N U 01
O i40 K N
O}
m
s �
a
e> a to N-$ w 8 :3w m$98 8108 o uass w�( ww 92wnw 1 0 2 M C4
www ww w M90
Z4.
s O o } O O V N N O O
En Q'
� � � --
O
d p to nNus N N N N m o N o u aN�
� � W
a
jj.U� � mets as�D N a6 N N N N � m m o Ln ua us m m Lo�a n
a`t
V
C O C
w N o
U O
m �
a o
wm+ y
O
ver
t6 N
Oy O 2t G r O J
c
c c
R J R N Q U Q G C_ U G di O G"a 61
ggq�ii R C,5 V) y N m V N 6@ as 0 O O R a> EE N
C _ O O O y C G ryys td O O as.y..:La $ L g M
a y U U y C L.4 R aY U CU a a ai to 3
d R tp V L y'g'iq U7 O
F atm aG3ama t- oc o � c 'y > LES _
a m c RC7mo op R R ttJ c a' N Rg r�
G G = _ a) G m..R. O O .IC CLI a
Q
�-
a ar .a c•� 3 �m ro
00
c � m ro 9 IIs.L j vii m N ,�m aci o m acs u o rc
� � La�i $ cGE � mdcasm p ~ im
ao ca acs to mm c_°tt°3¢¢a 3tn� u
m
d ,-Lvrsv, In�r�m rn .-Nr;v u',
V'"e'It v 5t V'RN O Ql
y�.' E 0
rj O'�U
R
0 d tL
ATTACHMENT 9VI
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
E. Lancaster Traffic Signal Bid Package and Construction Phase Services
City Project No. 02336
There are no proposed changes to the Standard Agreement
City of Fort Worth,Texas
Attachment C
PMO Release Date:05,19,2010
Page 1 of I
Consulting Contract Schedule Specifications F00"RT WORTH
City of Fort Worth Capital Improvement Program 770F,71-
Attachment D -Project Schedule
This PROTECT requires a Tier 3 schedule as defined herein and in the Citil's Schedule Guidance
Document.
D1. CONSULTING SERVICES SCHEDULE DEVELOPMENT: The CONSULTANT shall
prepare schedules for consulting services that meet the requirements described in this
specification, showing by Critical Path Method (CPM) the planned sequence and timing of
the Work associated with the Agreement. All submittals shall be submitted in PDF format,
and schedule files shall also be submitted in native file format (i.e. file formats associated
with the scheduling software). The approved scheduling software systems for creating the
schedule files are:
- Primavera (Version 6.1 or later or approved by CITY)
- Primavera Contractor (Version 6.1 or later or approved by CITY)
- Microsoft Project(Version 2003/2007 or later or approved by CITY)(PHASING OUT)
D2. BASELINE CONSULTING SERVICES SCHEDULE: Following notice-to-proceed, the
CONSULTANT shall develop, submit and review the draft detailed baseline consulting
services schedule with the CITY to demonstrate the CONSULTANT's understanding of the
Agreement requirements and approach for performing the work. The CONSULTANT will
prepare the final detailed baseline consulting services schedule based on CITY comments, if
any,and submit to the CITY no later than the submittal of the first project invoice.
The following guidelines shall be adhered to in preparing the baseline schedule, and as
described in further detail in the CITY's Schedule Guidance Document.
a. The scope shall be subdivided by work breakdown structure (WBS) representing the
tasks,subtasks, and activities associated with delivering the work.
b. The schedule shall accurately describe the major work activities,key milestones, and
dependencies/relationships as appropriate to the work.
c. The schedule should include appropriate meetings, review periods, critical decision
points,including third party utility dependencies and reviewing agencies.
D3. PROGRESS CONSULTING SERVICES SCHEDULE: The CONSULTANT shall prepare
and submit monthly to the CITY for approval the updated schedule in accordance with D1
and D2 and the CITY's Schedule Guidance Document inclusive. As the Work progresses,
the CONSULTANT shall enter into the schedule and record actual progress as described in
the CITY's Schedule Guidance Document.
The updated schedule submittal shall also include a concise schedule narrative that
highlights the following,if appropriate and applicable:
• Changes in the critical path,
• Expected schedule changes,
• Potential delays,
• Opportunities to expedite the schedule,
• Coordination issues the CITY should be aware of or can assist with,
City of Fort Worth,Texas
Attachment D
PMO Release Date:02,15,2011
Page 1 of 2
• Other schedule-related issues that the CONSULTANT wishes to communicate to the
CITY.
D4. PERFORMANCE AND CONSULTING SERVICES SCHEDULE: If the work
accomplished falls behind that scheduled due to factors within the CONSULTANT's
control, the CONSULTANT shall take such action as necessary to improve the progress of
the Work. In addition, the CITY may require the CONSULTANT to submit a revised
schedule demonstrating the proposed plan to make up the delay in schedule progress and
to ensure completion of the Work within the allotted Agreement time.
D5. SCHEDULE TIERS SPECIAL INSTRUCTIONS:
The requirements for the schedule are determined based on the nature and needs of the
project. The schedule tier for this project is stated at the top of this document.
CONSULTANT shall submit each schedule relying on the CITY's current Schedule
Guidance Document.
D6. SCHEDULE SUBMITTAL AND PAYMENT:
As stated in III.A.(1). of the Agreement, CONSULTANT shall provide the information
required by Attachment D. CONSULTANT's monthly invoices will not be accepted and
processed for payment witho u* t monthly schedule updates that are submitted in the time
and manner required by Attachment D and the CITY's current Schedule Guidance
Document.