HomeMy WebLinkAboutContract 25775 CIN SECRET SPECIFICATIONS OITY SEC
ARS CONTRAC-i No Y
D.O.E. FILE AND
CONTRACTOWS BONDING 6NTRACT DOCUMENTS
CONSTRUCTION'S COPY FOR
CLIENT DEPARTMENT
NORTH BEACH STREET
N.S. III PUMP STATION EXPANSION
WATER DEPARTMENT PROJECT NO. PW77-060770140490 O
DEPARTMENT OF ENGINEERING PROJECT NO. 2923 1'U
BOB TERRELL KENNETH BARR
CITY MANAGER MAYOR
HUGO A. MALANGA, P.E. LEE C. BRADLEY
DIRECTOR DIRECTOR
TRANSPORTATION AND WATER DEPARTMENT
PUBLIC WORKS
MIKE GROOMER A. DOUGLAS RADEMAKER, P.E.
ASST. CITY MANAGER DIRECTOR
DEPARTMENT OF ENGINEERING
NOVEMBER 1999
orm 111 4055 INTERNATIONAL PLAZA,
SUITE 200
FREESE-NICHOLS FORT WORTH, TEXAS 76109-
4895
(817) 735-7300
F&N No. FTW99425
OFFICIAL HCORD
C6"SEC °ff
City of Fort Worth, Texas
"01601f Andcommunication
Coundt
DATE REFERENCE NUMBER LAG NAME PAGE
4/4/00 C-17971 3000NTROL 1 of 2
SUBJECT AWARD OF UNIT 1 CONTRACT TO CONTROL SPECIALISTS, INC. AND UNIT 2
CONTRACT TO B&H UTILITIES, INC. FOR NORTH SIDE III NORTH BEACH STREET
PUMP STATION EXPANSION AND 36-INCH WATER LINE INSTALLATION
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute construction contracts
with Control Specialists, Inc. for $713,790 and B&H Utilities, Inc. for $368,000 for a total project amount
of $1,081,790. These awards are for the construction of North Side III North Beach Street Pump
Station Expansion and 36-Inch Water Line Installation.
DISCUSSION:
On October 19, 1999 (M&C C-17702), the City Council authorized the City Manager to execute an
amended engineering services agreement with Freese & Nichols, Inc. for design of the City of Fort
Worth North Side IIYI North Beach Street Pump Station expansion and 36-inch water line installation.
These improvements provide a means of supplying additional water to the North Side III pressure plane
to meet the increasing water service demands. The improvements are as follows;
Unit I - improvements include yard piping, 1,400 linear feet of 36-inch water line and water
line connections.
Unit 2 - improvements include the expansion of the pump station.
This project was advertised for bid November 18 and 24, 1999. On December 23, 1999, the following
bids were received:
F
BIDDER UNIT 1 AMOUNT TIME OF COMPLETION
Control Specialists, Inc. $713,790.00 40 Calendar Days
B&H Utilities, Inc. $828,616.00
Architectural Utilities, Inc. $913,458.00
Oscar Renda Contracting, Inc. $953,213.00
BIDDER UNIT 2 AMOUNT TIME OF COMPLETION
Architectural Utilities, Inc." $292,000.00
Oscar Renda Contracting, Inc." $246,300.00
B&H Utilities. Inc. $368.000.00 100 Calendar Days
Control Specialists, Inc. $383,000.00
" Oscar Renda Contracting, Inc. and Architectural Utilities, Inc. failed to submit their M/WBE utilization
forms within the prescribed time as set forth in the City's bid package. Failure to do so resulted in their
bids being considered as non-responsible and therefore disqualified them from being awarded this
project.
City of Fort Worth, Texas
"floor And council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
4/4/00 C-17971 3000NTROL 2 of 2
SUBJECT AWARD OF UNIT 1 CONTRACT TO CONTROL SPECIALISTS, INC. AND UNIT 2
CONTRACT TO B&H UTILITIES, INC. FOR NORTH SIDE III NORTH BEACH STREET
PUMP STATION EXPANSION AND 36-INCH WATER LINE INSTALLATION
Staff recommends that this project be awarded as described so that the work can be completed prior to
this summer's high water demand.
The project is located in COUNCIL DISTRICT 2.
In addition to the contract cost, $75,725 is required for inspection and survey and $32,453 is provided
for project contingencies.
Control Specialists, Inc. is in compliance with the City's M/WBE Ordinance by committing to 35%
M/WBE participation. The City's goal for Unit 1 is 14%.
B&H Utilities, Inc. is in compliance with the City's M/WBE Ordinance by committing to 10% M/WBE
participation. The City's goal for Unit 2 is 10%.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of
the Commercial Paper Water Fund.
MG:j
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
Mike Groomer 6140 APQROVFO
Originating Department Head: CITY COUNCIL
A.Douglas Rademaker 6157 (from) APR 4 20M
PW77 541200 060770140490 $1,081,790.00 ��11
Additional Information Contact:
City Secretary of the
A.Douglas Rademaker 6157 City of Fort Worth.Texas
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
FOR
NORTH BEACH STREET
N.S. III PUMP STATION EXPANSION
WATER DEPARTMENT PROJECT NO. PW77-060770140490
DEPARTMENT OF ENGINEERING PROJECT NO. 2923
BOB TERRELL KENNETH BARR
CITY MANAGER MAYOR
a
HUGO A. MALANGA, P.E. LEE C. BRADLEY
DIRECTOR DIRECTOR
TRANSPORTATION AND WATER DEPARTMENT
PUBLIC WORKS
MIKE GROOMER A. DOUGLAS RADEMAKER, P.E.
ASST. CITY MANAGER DIRECTOR
DEPARTMENT OF ENGINEERING
PSE�F j�Xgs�1
*5�• r� NOVEMBER 1999
PWO .Y E:CAMPS L
0- 8101 81011 �;
'1��' 4055 INTERNATIONAL PLAZA,
V\t
E•N HOLS SUITE 200
F
FORT WORTH, TEXAS 1 76109-
4895
(817) 735-7300
- =' 'a ` F&N Ng� __X99425
F
.> .d t
. . '9lGISTE`'"
JOHN F.DEWAR
.
80059 �• / !W'
— r
CITY OF FORT WORTH
NORTH BEACH STREET NS III PUMP STATION EXPANSION
WATER DEPT. PROJECT NO. PW77-060770140490
DEPT. OF ENGINEERING PROJECT NO. 2923
FREESE AND NICHOLS PROJECT NO. FTW99425
OF rZ,4Ztt
ADDENDUM NO. 1 5;.. •. .s It
December 10, 1999
THOMAS W.HASTER o
The time for the submission of Bids has been changed to Thursday,Decemb�"�3;19
GIST.........
The location for the submission of bid is unchanged. tti'���C)NAI.
BID DATE: Thursday,December,23, 1999, 2:00 pm
The following additions, deletions,modifications, or clarifications shall be made to the appropriate
sections of the plans and specifications and shall become apart of the Contract Documents. Bidders
shall acknowledge receipt of this Addendum in the space provided on the Bid form.
r BIDDING REQUIREMENTS:
Al-1 PART B -PROPOSAL
Modification: Delete this section and replace it with the PROPOSAL included with this
Addendum. The revised form is to be attached to the contract documents and submitted with the
Bid.
Al-2 PART C-GENERAL CONDITIONS
Addition:Insert"SECTION Cl:SUPPLEMENTARY CONDITIONS TO PART C-GENERAL
CONDITIONS"included with this Addendum.
Al-3 PART D-SPECIAL CONDITIONS
Modification:Modify SPECIAL CONDITIONS by deleting the"City of Fort Worth Highway
Construction Prevailing Wage Rate for 1995", and adding the following "City of Fort Worth
Highway Construction Prevailing Wage Rate for 1999" included with this Addendum.
TECHNICAL SPECIFICATIONS:
A1-4 SECTION 11210-INSTRUMENTATION
A. Reference Page 1,Paragraph 1.02,A.
Addition: Include Peerless Pumps as an acceptable pump manufacturer.
Al-5 SECTION 16900-INSTRUMENTATION
Addendum No. 1 00900-1
FTW99425
e
A. Reference Page 5,Paragraph 2.05,E.
Modification: Delete paragraph E in its entirety and replace with the following, "E. The
chlorine residual analyzers shall be Capitol Controls."
Al-6 ADD THE FOLLOWING SECTIONS:
15078 MISCELLANEOUS PIPING AND APPURTENANCES
15136 MISCELLANEOUS VALVES
16111 CONDUITS
y DRAWINGS:
Al-7 SHEET 6 OF 33
A. Reference: Section A.
Modification: Delete the Y-9" dimension call-out from the centerline of the existing 24"
gate valve to the buried joint,and replace with a single joint of pipe from the connection to
existing piping to the new 24" 90 degree bend.
Addition:Add the following as Note 15 of the General Notes-"Contractor shall field verify
the location,line,and grade of the existing piping connections and will be responsible for
removal of existing concrete blocking as required to connect to the existing piping".
B. Reference: General Notes
Addition:Add Note 15,"All exposed discharge piping for the pump station shall be ductile
iron pipe".
Al-8 SHEET 23 OF 33
A. Reference: Foundation Plan
Modification:Change dimension of penetration through the floor of discharge piping from
wall from T-4" to 6'-4".
Al-9 REPLACE THE FOLLOWING SHEETS
REPLACE SHEET WITH SHEET
2 of 33 Site Plan 2A of 33 Site Plan
3 of 33 Piping Layout-Stage I 3A of 33 Piping Layout- Stage I
4 of 33 Piping Layout-Stage II 4A of 33 Pump Station Expansion -Stage II
5 of 33 Pump Station Plan 5A of 33 Pump Station Plan
7 of 33 Profiles Water Line `A' and 7A of 33 Profiles Water Line `A' and
Water Line `B' and Misc. Water Line `B' and Misc.
Details Details
8 of 33 Concrete Overflow Structure 8A of 33 Concrete Overflow Structure
9 of 33 21"Waterline Modification 9A of 33 21"Waterline Modification
12 of 33 Plan &Profile -24"Water 12A of 33 Plan&Profile-24" Water
Line-Sta 0+00 to Sta 10+00 Line-Sta 0+00 to Sta 10+00
13 of 33 Plan &Profile -24"Water 13A of 33 Plan&Profile-24" Water
Line-Sta 10+00 to Sta Line-Sta 10+00 to Sta
Addendum No. 1 00900-2
FTW99425
•- r
15+05.22 14+56
15 of 33 Miscellaneous Details 15A Of 33 Miscellaneous Details
26 of 33 Electrical Site Plan 26A of 33 Electrical Site Plan
30 of 33 Electrical Details 30A of 33 Electrical Details
END OF ADDENDUM NO. 1
Addendum No. 1 00900-3
+� FTW99425
PART B - PROPOSAL
(This Proposal must not be removed from this book of Contract Documents)
TO: Mr. Bob Terrell
City Manager
City of Fort Worth, Texas
r FOR: NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
WATER DEPARTMENT PROJECT NUMBER PW77-060770140490
DEPARTMENT OF ENGINEERING PROJECT NUMBER 2923
Includes the furnishing of all materials (except as specified to be furnished by the City),
equipment and labor for the installation of all improvements and appurtenant work shown
in the plans and specification, all necessary appurtenances and incidental work to provide
a complete and serviceable project.
Pursuant to the foregoing "Notice to Bidders", the undersigned bidder, having thoroughly
examined the contract documents, including plans, special contract documents, and the
General Contract Documents and General Specifications for Water Department Projects,
the site of the project and understanding the amount of work to be done, and the
prevailing conditions, hereby proposes to do all the work, furnish all labor, equipment and
material except as specified to be furnished by the City, which is necessary to fully
complete the inspection and approval of the Director of the City Water Department of the
City of Fort Worth, Texas; and binds himself upon acceptance of this proposal to execute
a contract and furnish an approved Performance Bond, Payment Bond, and Maintenance
Bond, and such other bonds, if any, as may be required by the Contract Documents for
the performing and completing of the said work.
Contractor proposes to do the work within the time stated and for the following sums:
(Furnish and install, including all appurtenant work, complete in place, the following
items):
lop
A
FTW99425 B-1
V.
r
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
UNIT ONE - YARD PIPING, 36-INCH WATERLINE, WATERLINE CONNECTIONS
1. 1 LS Yard Piping for Pump Station
Including Piping, Fittings and
Appurtenances for Pump Station Site
Dollars
T and
Cents
per LS $ $
2. 1 EA 16" Gate Valve and Valve Vault
Including Appurtenant Piping and
Equipment
Dollars
and
Cents
per EA $ $
3. 1 EA Remotely Operated Motor Operated
16" Butterfly Valve and Operator
Stand Installed with NS II / ES II
Transfer Meter Vault Including
Appurtenant Piping and Equipment
Dollars
and
Cents
per EA $ $
4. 2 EA Meter Vaults Including 8" Bypass
Piping, 2 - 16" Isolation Gate Valves
and Vaults, Fire Hydrant Assembly,
Appurtenant Piping and Equipment
Dollars
and
Cents
per EA $ $
FTW 99425 B-2
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
_* PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
5. 1 LS For Chlorine Analyzer, Water
Sample Station, Ph/Temperature
Meter and Pressure Transmitter and
Appurtenances to be Installed in the
New NS III Meter Vault on Discharge
Side of Pump Station
-, Dollars
and
Cents
per LS $ $
6. 1 LS Tie-In to Existing 24" Waterline and
Existing 16" Discharge Piping with
New 16" x16" Tee and New 16" x
24" Reducer (Sheet 3A)
Dollars
and
Cents
per LS
7. 1 LS For.Connection to Existing 30"
Suction Header at Line "A" Sta 2+48
(Sheet 3A)
Dollars
and
Cents
per LS $ $
8. 1 LS For Connection to Existing 24"
Waterline at Line "B" Sta 0+00
(Sheet 3A)
Dollars
and
Cents
per LS $ $
FTW 99425 B-3
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
9. 1 LS For Modifications to the 21"
Waterline (Sheet 9A) Including All
Piping, 12" Gate Valve, Fire Hydrant
T Assembly, Fittings and
Appurtenances
Dollars
and
Cents
per LS $ $
10. 1,403 LF 36" Waterline Including Piping,
Fittings, Closure Pieces, Joint
Restraint, and Appurtenances
Dollars
and
Cents
per LF $ $
11. 1 LS Work Performed by H.S.Q. to
Complete Stage One - Piping Plan
as Specified and Shown on the
Drawings
Dollars
and
Cents
per LS $ $
12. 1 LS For Electrical Work Required to
Complete the Stage One - Piping
Plan as Specified and Shown on the
Drawings Including All Provisions for
Temporary Power
Dollars
and
Cents
per LS $ $
13. 1,738 LF Trench Safety System
Dollars
and
Cents
per LF $ $
FTW 99425 B-4
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
14. 1 LS Install and Maintain Erosion and
Sediment Control During Entire
Construction Period
Dollars
and
Cents
per LS $ $
15. 1 LS Post Construction Hydro-Mulch
Seeding For All Areas Disturbed
During Construction Activities
Dollars
and
Cents
per LS $ $
16. 1 LS ADD/<DEDUCT> For All Additional
Work Required to Complete Stage
One Piping Plan as Specified and
Shown on the Drawings but Not
Included in Other Items
Dollars
and
Cents
per LS $ $
FTW 99425 B-5
,
r
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
UNIT TWO - N.S. III PUMP STATION EXPANSION
17. 1 LS New Pump Building Including Precast
Concrete Panels, Roofing, Concrete
Slab, Pump Bases, Tie-Ins to
Existing 4" Sanitary Sewer and
Appurtenances
Dollars
and
Cents
per LS $ $
18. 1 LS New Pumps, Piping, Pump Control
Valves, Motors and Appurtenances
Dollars
and
Cents
per LS $ $
19. 1 LS Overflow Structure for Drain Line at
Existing 5 MG Ground Storage Tank
Dollars
and
Cents
per LS $ $
- 20. 1 LS Work Performed by H.S.Q. to
Complete Stage Two - Pump Station
Plan as Specified and Shown on the
Drawings
Dollars
and
Cents
per LS $ $
i
FTW99425 B-6
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
-- PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
21. 1 LS ADD/<DEDUCT> For All Additional
Work Required to Complete Stage
Two Pump Station Plan as Specified
and Shown on the Drawings but Not
Included in Other Items
Dollars
and
Cents
per LS $ $
ALTERNATE BID ITEM
22. 1 EA 30" Butterfly Valve and Valve Vault
Including Appurtenant Piping and
Equipment
Dollars
and
Cents
per EA $ $
BID SUMMARY FOR NORTH BEACH N.S. III PUMP STATION EXPANSION
TOTAL FOR UNIT ONE (Bid Items 1 through 16) $
TOTAL FOR UNIT TWO (Bid Items 17 through 21) $
ALTERNATE BID ITEMS (Bid Item 22) $
BASE BID TOTAL (Bid Items 1 though 21) $
ALTERNATE BID TOTAL (Bid Items 1 through 22) $
" 36" waterline pipe shall be in accordance with City of Fort Worth Water Department
specification E1-4 or E1-6.
Bidder/Contractor shall check the pipe material to be used for 36" diameter waterline pipe and
yard piping.
[ ] E1-4 Concrete Pressure Pipe and Fittings
[ ]
E1-6 Ductile Iron Pipe
FTW99425 B-7
a
� 1
i
PART B - PROPOSAL (continued)
Within ten (10) days after acceptance of this Proposal, the undersigned will execute the formal
contract and will deliver an approved Surety Bond and such other bonds as required by the
Contract Documents, for the faithful performance of the Contract. The attached bid security in
the amount of five (5%) percent is to become the property of the City of Fort Worth, Texas, in
the event the contract or bonds are not executed and delivered within the time above set forth,
�- as liquidated damages for delay and additional work caused thereby.
The undersigned bidder certifies that he has been furnished at least one set of the General
Contract Documents and General Specifications for Water Department Projects dated
January 1, 1978, and that he has read and thoroughly understands all the requirements and
conditions of those General Documents and these specific Contract Documents and
appurtenant plans.
The undersigned bidder certifies that he agrees the OWNER reserves the right to award
either Unit 1 or Unit 2, or both Unit 1 and Unit 2, or neither Unit 1 or Unit 2, and that individual
line items may be deleted from the Proposal from either Unit 1 or Unit 2 to arrive at the most
advantageous bid total for the OWNER. Alternate bid items may be added to or deleted from
the contract by the Owner. The work includes furnishing all materials, tools, equipment,
transportation, services and all labor and superintendence for the construction as indicated in
the Contract Documents.
The undersigned assures that its employees and applicants for employment and those of any
labor organization, subcontractors or employment agency in either furnishing or referring
employee applicants to the undersigned are not discriminated against as prohibited by the
terms of City Ordinance No. 7278 as amended by City Ordinance No. 7400.
The Bidder agrees to begin work on the Contract and to complete all work on the Contract
within the time set forth in Part D - Special Conditions, "Completion Time".
(Complete A or B below, as applicable:)
[ ] A. The principal place of business of our company is in the State of
1�
[ ] Nonresident bidders in the State of , our principal place of
business, are required to be percent lower than resident bidders
by state law. A copy of the statute is attached.
[ ] ' Nonresident bidders in the State of , our principal place of
business, are not required to underbid resident bidders.
[ ] B. The principal place of business of our company or our parent company or
majority owner is in the State of Texas.
P
FTW99425 B-8
+� r
Receipt is acknowledged of the following addenda:
Addendum No. 1
Addendum No. 2
Addendum No. 3
Respectfully submitted,
(SEAL) By:
If Bidder is Corporation Title:
Address:
„
FTW99425 B-9
WP
SECTION Cl:
SUPPLEMENTARY CONDITIONS TO PART C- GENERAL CONDITIONS
A. General
These Supplementary Conditions amend or supplement the General Conditions of the
f` Contract and other provisions of the Contract Documents as indicated below. Provisions
G which are not so amended or supplemented remain in full force and affect.
B. C3-3.2 MINORITY BUSINESS ENTERPRISE/WOMEN-OWNED BUSINESS
ENTERPRISE COMPLIANCE: Page C3-3 (1), should be deleted in its entirety and
replaced with the following:
Upon request, Contractor agrees to provide to Owner complete and accurate information
regarding actual work performed by a Minority Business Enterprise (MBE) and/or a
Woman Business Enterprise (WBE) on the contract and payment therefore. Contractor
further agrees to permit an audit and/or examination of any books, records or files in its
possession that will substantiate the actual work performed by an MBE and/or WBE. The
misrepresentation of facts (other than a negligent misrepresentation) and/or the
commission of fraud by the Contractor will be grounds for termination of the contract
and/or initiating action under appropriate federal, state or local laws or ordinances relating
to false statements; further, any such misrepresentation (other than a negligent
misrepresentation) and/or commission of fraud will result in the Contractor being
determined to be irresponsible and barred from participating in City work for a period of
time of not less than three(3)years.
C. C3-3.7 BONDS: Page C3-3 (3), the paragraph after subparagraph d. Change the
paragraph to read as follows:
"No sureties will be accepted by the owner which are at the time in default or delinquent
on any bonds or which are interested in any litigation against the Owner. All bonds shall
be made on the forms furnished by the Owner and the surety shall be acceptable to the
owner. In order for a surety to be acceptable to the City, (1) the name of the surety shall
be included on the current U.S. Treasury List of Acceptable Sureties (Circular 870), or
(2) the surety must have capital and surplus equal to ten times the amount of the bond.
The surety must be licensed to business in the state of Texas. The amount of the bond
shall not exceed the amount shown on the Treasury list or one-tenth (1/10) of the total
capital and surplus. If reinsurance is required, the company writing the reinsurance must
be authorized, accredited or trusteed to do business in Texas."
D. C8-8.5 PARTIAL ESTIMATES AND RETAINAGE: Page C8-8 (2), should be deleted in
its entirety and replaced with the,following:
Partial pay estimates shall be submitted by the Contractor or prepared by the City on the
5th day and 20th day of each month that the work is in progress. The estimate shall be
proceeded by the City on the 10th day and 25th day respectively. Estimates will be paid
within 25 days following the end of the estimate period, less the appropriate retainage as
set out below. Partial pay estimates may include acceptable nonperishable materials
delivered to the work place which are to be incorporated into the work as a permanent
part thereof, but which at the time of the pay estimate have not been so installed. If such
Revised Pg. 1
6/04/99
materials are included within a pay estimate, payment shall be based upon 85% of the net
voice value thereof The Contractor will furnish the Engineer such information as may be
reasonably requested to aid in the verification or the preparation of the pay estimate.
For contracts of less than$400,000 at the time of execution, retainage shall be ten per cent
(101/6). For contracts of$400,000 or more at the time of execution, retainage shall be five
percent(5%).
Contractor shall pay subcontractors in accord with the subcontract agreement within five
(5) business days after receipt by Contractor of the payment by City. Contractor's failure
to make the required payments to subcontractors will authorize the City to withhold future
payments from the Contractor until compliance with this paragraph is accomplished.
It is understood that the partial pay estimates will be approximate only, and all partial pay
estimates and payment of same will be subject to correction in the estimate rendered
•- following the discovery of the mistake in any previous estimate. Partial payment by
Owner for the amount of work done or of its quality or sufficiency or acceptance of the
work done; shall not release the Contractor of any of its responsibilities under the
Contract Documents.
The City reserves the right to withhold the payment of any partial estimate if the
Contractor fails to perform the work in strict accordance with the specifications or other
provisions of this contract.
E. C3-3.11 INSURANCE: Page C3-3 (5): Delete subparagraph "a. COMPENSATION
INSURANCE"
F. C3-3.11 INSURANCE: Page C3-3 (6): Delete subparagraph "g. LOCAL AGENT FOR
INSURANCE AND BONDING"
G. C6-6.12 CONTRACTOR'S RESPONSIBLITY FOR DAMAGE CLAIMS: Page C6-6
(8), should be deleted in its entirety and replaced with the following:
Contractor covenants and agrees to indemnify City's engineer and architect, and their
personnel at the project site for Contractor's sole negligence. In addition, Contractor
covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
Owner, its officers, servants and employees, from and against any and all claims or suits
for property loss, property damage, personal injury, including death, arising out of or
alleged to arise out of the work and services to be performed hereunder by Contractor, its
officers, agents, employees, subcontractors, licensees or invitees, whether or not any such
injury, damage or death is caused, in whole or in partby the negligence or alleged
negligence of Owner, its officers, servants, or employees Contractor likewise covenants
and agrees to indemnify and hold harmless the Owner from and against any and all injuries
to Owner's officers, servants and employees and any damage, loss or destruction to
property of the Owner arising from the performance of any of the terms and conditions of
this Contract, whether or not any such injury or damage is caused in whole or in part
by the negligence or alleged negligence of Owner, its officers, servants or employees.
In the event Owner receives a written claim for damages against the Contractor or its
subcontractors prior to final payment, final payment shall not be made until Contractor
Revised Pg. 2
�„ 6/04/99
either (a) submits to Owner satisfactory evidence that the claim has been settled and/or a
release from the claimant involved, or (b) provides Owner with a letter from Contractor's
liability insurance carrier that the claim has been referred to the insurance carrier.
The Director may, if he deems it appropriate, refuse to accept bids on other City of Fort
Worth public work from a Contractor against whom a claim for damages is outstanding as
a result of work performed under a City Contract.
Revised Pg. 3
6/04/99
CITY OF FORT WORTH
HIGHWAY CONSTRUCTION
PREVAILING WAGE RATE FOR 1999
CLASSIFICATION HOURLY RATE
AIR TOOL OPERATOR $9.00
ASPHALT RAKER 9.55
lo` ASPHALT SHOVELER 8.80
BATCHING PLANT WEIGHER 11.51
CARPENTER 10.30
CONCRETE FINISHER-PAVING 10.50
` CONCRETE FINISHER-STRUCTURES 9.83
CONCRETE RUBBER 8.84
ELECTRICIAN 15.37
FLAGGER 7.55
FORM BUILDER-STRUCTURES 9.83
FORM LINER-PAVING&CURB 9.00
FORM SETTER-PAVING&CURB 9.24
FORM SETTER-STRUCTURES 9.09
LABORER-COMMON 7.32
LABORER-UTILITY 8.94
MECHANIC 12.68
OILER 10.17
SERVICER 9.41
PAINTER-STRUCTURES 11.00
PIPE LAYER 8.98
BLASTER 11.50
ASPHALT DISTRIBUTOR OPERATOR 10.29
ASPHALT PAVING MACHINE 10.30
BROOM OR SWEEPER OPERATOR 8.72
BULLDOZER 10.74
CONCRETE CURING MACHINE 9.25
CONCRETE FINISHING MACHINE 11.13
CONCRETE PAVING JOINT MACHINE 10.42
CONCRETE PAVING JOINT SEALER 9.00
CONCRETE PAVING SAW 10.39
CONCRETE PAVING SPREADER 10.50
SLIPFORM MACHINE OPERATOR 9.92
s CRANE,CLAMSHELL,BACKHOE,DERRICK,DRAGLINE,SHOVEL 11.04
FOUNDATION DRILL OPERATOR CRAWLER MOUNTED 10.00
FOUNDATION DRILL OPERATOR TRUCK MOUNTED 11.83
FRONT END LOADER 9.96
.. MILLING MACHINE OPERATOR 8.62
• MIXER 10.30
MOTOR GRADER OPERATOR FINE GRADE 11.97
MOTOR GRADER OPERATOR 10.96
PAVEMENT MARKING MACHINE 7.32
ROLLER,STEEL WHEEL PLANT-MIX PAVEMENTS 9.06
ROLLER,STEEL WHEEL OTHER FLATWHEEL OR TAMPING 8.59
ROLLER,PNEUMATIC,SELF-PROPELLED SCRAPER 8.48
.. SCRAPER 9.63
TRACTOR-CRAWLER TYPE 10.58
TRACTOR PNEUMATIC 9.15
TRAVELING MIXER 8.83
r• �
CITY OF FORT WORTH
HIGHWAY CONSTRUCTION
PREVAILING WAGE RATE FOR 1999
CLASSIFICATION HOURLY RATE
WAGON-DRILL,BORING MACHINE 12.00
REINFORCING STEEL SETTER-PAVING 13.21
REINFORCING STEEL SETTER-STRUCTURES 13.31
STEEL WORKER-STRUCTURAL 14.80
SPREADER BOX OPERATOR 10.00
.3 WORK ZONE BARRICADE 7.32
TRUCK DRIVER-SINGLE AXLE LIGHT 8.965
TRUCK DRIVER-SINGLE AXLE HEAVY 9.02
TRUCK DRIVER-TANDEM AXLE SEMI TRAILER 8.77
TRUCK DRIVER-LOWBOY/FLOAT I0.44
TRUCK DRIVER-TRANSIT MIX 9.47
TRUCK DRIVER-WINCH 9.00
VIBRATOR OPERATOR-HAND TYPE 7.32
WELDER 11.57
4
y 15078 MISCELLANEOUS PIPING AND APPURTENANCES
1.00 GENERAL
1.01 WORK INCLUDED
Furnish labor,materials,equipment and incidentals necessary to install miscellaneous piping,
fittings, and appurtenances.
1.02 QUALITY ASSURANCE [Not Used]
1.03 SUBMITTALS
Submittals shall be in accordance with Section 01300, SUBMITTALS and shall include:
1. Shop drawings
1.04 STANDARDS [Not Used]
1.05 DELIVERY AND STORAGE [Not Used]
1.06 JOB CONDITIONS [Not Used]
1.07 OPTIONS [Not Used]
1.08 GUARANTEES [Not Used]
2.00 PRODUCTS
- 2.01 MATERIALS [Not Used]
2.02 MIXES [Not Used]
2.03 FABRICATIONS [Not Used]
2.04 MANUFACTURED PRODUCTS [Not Used]
2.05 COPPER PIPE AND FITTINGS
A. Copper pipe for water service shall be Type "K" hard-drawn copper tubing. Connections
shall be made using cast brass or copper sweat fittings and Sil-Fos or approved equal
hard solder. Union adaptors shall be used at ends of copper lines and at connections to
equipment so that piping can be disconnected without unsoldering the joints.
B. Joints in copper piping shall be soldered with ANSIIASME B32, Grade 95TA solder.
Before making up joints,copper shall be cleaned to bright metal with emery cloth and
treated with nonacid type flux.
Miscellaneous Piping and Appurtenances 15078-1
FTW99425
" r
2.06 PIPE COUPLINGS
A. Dresser style pipe couplings where shown on the Plans shall be Dresser Industries or
approved equal, for same pressure rating as adjoining pipe. Couplings shall comprise a
steel center band, steel gland rings, gaskets,and bolts. Provide thrust harness as detailed
where shown on the Plans.
2.07 FLOOR DRAIN
Floor drains shall be cast iron of the sizes indicated. Drain design shall allow height adjustment
prior to concrete slab placement. Floor drains shall installed at the locations indicated on the
drawings. Contractor shall install P-trap for connections to existing drain lines and sewer lines.
2.09 PIPE SUPPORTS
Adjustable pipe supports under valves and piping shall be Grinnell Figure 264 or approved
equal,comprising cast iron saddle, threaded nipple, and reducer assembly with extra strength
steel pipe and floor flange. For special sizes and shapes of valves, saddle shall be fabricated
steel to fit valve or piping being supported.
3.00 EXECUTION
3.01 PREPARATION [Not Used]
y 3.02 INSTALLATION
Piping shall be carefully handled and installed to prevent damage to the pipes. Potable water
lines shall be disinfected in accordance with Section 01656, DISINFECTION.
y
3.03 FIELD QUALITY CONTROL
Lines shall be tested for leaks. Leaks and defects shall be repaired or replaced, and re-tested
until no leaks or defects are discovered.
3.04 CLEAN AND ADJUST [Not Used]
3.05 SCHEDULES [Not Used]
END OF SECTION
Miscellaneous Piping and Appurtenances 15078-2
FTW99425
s
15136 MISCELLANEOUS VALVES
1.00 GENERAL
1.01 WORK INCLUDED
Furnish labor,materials,equipment and incidental necessary to install miscellaneous valves.
1.02 QUALITY ASSURANCE [Not Used]
1.03 SUBMITTALS
Submittals shall be in accordance with Section 01300, SUBMITTALS and shall include:
1. Shop drawings
2. Operation and Maintenance Manuals
1.04 STANDARDS [Not Used]
1.05 DELIVERY AND STORAGE [Not Used]
1.06 JOB CONDITIONS [Not Used]
1.07 OPTIONS [Not Used]
1.08 GUARANTEES [Not Used]
2.00 PRODUCTS
2.01 MATERIALS [Not Used]
2.02 MIXES [Not Used]
2.03 FABRICATIONS [Not Used]
2.04 MANUFACTURED PRODUCTS [Not Used]
2.05 FLAP VALVES
A. Flap valves shall be circular flange framed, with machined back flange for attachment to
flanged piping. Body and flap shall be cast iron,ASTM A-126-B. Resilient seat shall be
'. neoprene or Buna-N bonded in a groove machined in the body. Hinge arms shall be high-
tensile bronze, ASTM B-584-CA865 with two pivot points, an adjustable lower pivot
with limited rotation and a threaded upper hinge post to adjust flap valve sensitivity. A
lubrication fitting shall be supplied for each pivot. Hinge pins shall be silicon bronze,
ASTM B-98-CA655 or Type 304 Stainless Steel.
Miscellaneous Valves 15136-1
l+rW99425
v e
_ B. Equip flap valve with a lever arm with an adjustable counter weight to securely seat flap
in the closed posistion with the valve installed with the back flange facing in the vertical
direction. Flap valve shall be designed to.open when differential head across the flap is
0.3'or less.
C. Flap valve shall be Rodney Hunt Series FV-AC,Waterman Equal Model, or equal.
3.00 EXECUTION
-- 3.01 PREPARATION [Not Used]
3.02 INSTALLATION
Carefully handle and install valves in a manner that prevents damage to any part of the valves.
Install valves in accordance with the Manufacturer's instructions.
3.03 FIELD QUALITY CONTROL [Not Used]
3.04 CLEAN AND ADJUST [Not Used]
3.05 SCHEDULES [Not Used]
END OF SECTION
Miscellaneous Valves 15136-2
FTW99425
- - 16111 CONDUITS
1.00 GENERAL
1.01 WORK INCLUDED
Furnish labor,materials, equipment and incidentals necessary to install a complete conduit
system for each type of electrical system. Electrical work shall be in accordance with Section
16010, GENERAL ELECTRICAL REQUIREMENTS.
1.02 SUBMITTALS
No submittals required.
1.03 STANDARDS
The applicable provisions of the following standards shall apply as if written here in their
entirety:
ANSI C80.1 Rigid Steel Conduit,Zinc-Coated
i
ANSUNEMA FB 1 Fittings and Supports for Conduits and Cable Assemblies
N.
NEMA RN 1 PVC Extemally-Coated Galvanized Rigid Steel Conduit and
Electrical Metallic Tubing
NEMA TC 3 PVC Fittings for Use with Rigid PVC Conduit and Tubing
2.00 PRODUCTS
2.01 MANUFACTURED PRODUCTS
A. RIGID ALUMINUM CONDUIT: Heavy wall, aluminum alloy 6063; low temper
number,tube, free from defects and manufactured in accordance with ANSI C80.5
standards and U.L. listed. Acceptable manufacturers shall be Vaw, Western, and
Alumax.
i
B. PVC COATED RIGID STEEL: Meeting the requirements of rigid steel conduit, 40 mil
PVC,exterior coating and 2 mil red urethane interior coating. Acceptable Manufacturers
shall be Rob Roy Plastibond Red, Ocal and Perma-Cote.
C. FLE)UBLE METAL CONDUIT:
1. FOR USE WITH GALVANIZED CONDUIT: Single strip, helically wound,
interlocking, galvanized steel, in accordance with Fed. Spec. WW-C-566 and U.L.
listed. Liquid tight conduit shall have an extruded, polyvinyl jacket over the
Conduits 16111-1
�" FTW99425
S q
- flexible metal. Acceptable product shall be Anaconda Type U.A.
D.. RIGID NONMETALLIC CONDUIT: Schedule 40 and Schedule 80 high impact,
.. polyvinylchloride, in accordance with Fed. Spec. W-C-1094 and U.L. listed. Acceptable
manufacturers shall be Carlon, Cantex, and Certainteed.
E. FITTINGS AND CONDUIT BODIES:
1. RIGID METAL CONDUIT: Threaded type material to match the conduit, in
accordance with ANSI/NEMA FBI and as manufactured by Appleton Foran 35,
Killark"O" Series, Crouse Hinds, OZ Gedney, or RACO.
2. FLEXIBLE AND LIQUID TIGHT FITTINGS: In accordance with ANSI/NEMA
FB 1; cadmium-plated,malleable iron body and nut; cadmium steel ferrule;
insulated throat; integrally-cast, external ground lugs, as manufactured by
Appleton "ST" series, Hubbel, OZ Gedney Type 4QL, or RACO.
3. PVC CONDUIT: Solvent-welded,slip-on joints, in accordance with NEMA TC3,
as manufactured by Carlon, CertainTeed.
F. ELBOW AND BENDS: Rigid,nonmetallic conduit system shall use PVC-coated rigid
steel for conduits 2" and larger for all bends greater than 45 degrees. Other conduit
systems shall use the same material as the conduit with which they are installed.
G. BUSHINGS: High impact,thermosetting,phenolic insulation; 150 degrees C.; as
manufactured by Appleton "BBUH",Blackburn, or OZ Gedney type A.
H. GROUNDING BUSHINGS: Conduit grounding bushings shall consist of a malleable
iron,insulated throat conduit bushing with an attached aluminum set screw lug.
Grounding bushing shall comply with Fed. Spec. W-F-408b and W-W-C-581 d, UL
Standards 514B and 467, and shall be Crouse Hinds Lazy Lug or approved equal.
I. LOCKNUTS: Zinc-plated or cadmium-plated,malleable iron, as manufactured by
Appleton "BL", OZ Gedney, RACO, or Steel City.
J. HUBS: STEEL CONDUIT: Cadmium-plated,malleable iron with tapered threads, a
neoprene "O"ring and an insulated throat, as manufactured by Appleton "HUB", Myers
type St., OZ Gedney,type CH-T.
K. CONDUIT THROUGH-WALL AND FLOOR SEAL: Malleable iron body with
oversized sleeves, sealing ring,pressure clamp and rings and sealing grommet; hex head
cap screw, as manufactured by OZ Gedney,type FSK.
L. SMOKE AND FIRE SEALS: Material shall be intumescent, one (1) part(requiring no
mixing) and capable of expanding up to a minimum of eight(8) times. Material shall be
U.L. classified with a fire rating equal to or greater than the penetrated number. Products
Conduits 16111-2
- FTW99425
s
to be in caulk,putty,wrap strip,sheet, or access kit form and shall be 3M "Fire Barrier".
M. END BELLS: Hot-dipped,galvanized,threaded,malleable iron, as manufactured by OZ
Gedney type TNS.
N. EXPANSION FITTINGS: Hot-dipped,galvanized, malleable iron with bonding
' jumpers. Linear expansion fittings shall be OZ Gedney Zx for rigid, metal conduit or
Appleton "XJ" series. Combination linear and deflection expansion fittings shall be OZ
Gedney type AXDX.
O. THREADED NIPPLES: As manufactured by Allied, Triangle or Steel Duct. Conduit
nipples shall have two(2) independent sets of threads. Running threads shall not be
used. Utilize the conduit union when joining two (2) fixed conduits in a continuous run.
P. ESCUTCHEONS: Chrome-plated, sectional floor and ceiling plates, as manufactured
by Crane No. 10.
Q. ACCESSORIES: Reducers,washers, etc.,shall be cadmium-plated,malleable iron.
R. IDENTIFYING TAPE FOR BURIED CONDUITS: 6"wide,polyethylene with
continuous printing along the length of the tape, as manufactured by Brady "Identoline"
or Sentry Lin "Terra Tape". Use red with black letters for buried electrical power
conduits. Use green with black letters for buried electric instrumentation and
communication conduits.
S. WEATHERHEADS: Weatherheads shall be threaded aluminum for threaded rigid
conduit application and shall not be clamp type. Weatherheads shall be Crouse Hinds
series F, O-Z type 17 or Appleton Series F.
T. CONDUIT DRAINS: Conduit drains shall be Crouse Hinds ECD Universal, or
approved equal.
U. BURIED CONDUIT: PVC Schedule 40 or PVC coated rigid steel.
V. ABOVE GRADE CONDUIT: Rigid Aluminum,unless noted otherwise.
W. ALUMINUM CONDUIT IN CONCRETE: Aluminum conduit shall not be used in
concrete.
X. Conduit in concrete shall be Rigid Steel or PVC-coated Rigid Steel.
Conduits 16111-3
FTW99425
3.00 EXECUTION
3.01 INSTALLATION
A. Size conduits as required by the NEC for the number and sizes of wires to be drawn into
the conduit. Conduits less than 3/4" shall not be used unless specified otherwise.
B. Install the conduit at elevations which maintain headroom and at locations which avoid
interference with other work requiring grading of pipe, the structure, finished ceiling,
walls, etc. Avoid crossing other work. Do not place the conduits in close proximity to
equipment, systems and service lines, such as the hot water supply and return lines or
steam pipes which could be detrimental to the conduit and its contents. Maintain a
minimum of 3" separation, except in crossing,which shall be a minimum of V.
C. Prevent displacement by securely supporting the conduit which is to be concealed and
installed in advance of other work. Carefully layout all conduit installed within the
structure, such as in floors,beams and walls to avoid densities excessive for the
F0 construction.
D. Cut the conduit square with a saw. Ream, deburr and swab the inside of the conduit
before installing the conductors. Make bends and offsets in 1" and smaller conduit with
approved bending devices. Use a hydraulic, one-shot conduit bender or factory elbows
for bends in conduit larger than V. Use conduit bodies to make sharp changes in
direction around ground beams. Install no more than four(4) 90 degree bends between
boxes.
E. Where space conditions prohibit the use of standard elbows, use cast ferrous alloy
fittings to match the conduit construction. "Condulet" type fittings shall not be used on
conduit containing#4 or larger wire.
F. Make conduit joints mechanically tight and electrically continuous. Pitch the conduit in
areas where moisture may be present to avoid creating moisture traps. Where indicated
or necessary to prevent accumulation of water in the conduit,provide a junction box with
a drain fitting at the conduit system's low point.
G. Group the conduit in parallel runs where practical and use a conduit rack constructed of
steel channels with conduit straps or clamps. Prove space for an additional 25%conduit.
Route conduit inside building extents parallel to building lines.
H. Route and suspend conduit crossing expansion or Seismic joints to permit expansion,
contraction, and deflection utilizing approved fittings to prevent damage to the structure,
conduit, and supporting devices. Combination expansion/deflection fittings shall be
installed on conduits which are concealed when they cross expansion joints. Route
conduit through roof openings for piping and ductwork where possible; otherwise,route
through the roof with pitch pocket. Do not allow conduit to penetrate duct work. Do not
install conduit exposed on the roof without prior permission from the Engineer.
Conduits 16111-4
FTW99425
I. Connect motors, equipment containing motors, equipment mounted on isolated
foundations, light fixtures and other equipment and devices which are subject to
vibration and which require adjustment with a liquid-tight, flexible metallic conduit from
the device to the conduit serving it. The maximum length of the flexible conduit shall be
3011, unless specifically instructed otherwise by the Engineer in writing.
J. Install escutcheons on exposed conduits passing through interior floors,walls and
ceiling. Install fire seals on conduit passing through fire-rated partitions, floors and
ceilings. Install through-wall seals on conduit passing through exterior walls, or use
standard,galvanized steel pipe sleeves with diameters 1/2" greater than the outside
diameter of the sleeved conduit. Fill the annular space with oakum and the ends of the
sleeve with fire-resistant compound.
K. Install a sleeve for the conduit passing through the interior floors and insulated throat
grounding bushings on conduit which is stubbed through slabs and foundations into
electrical enclosures.
L. Provide grounding for conduit, fittings and accessories.
M. Use PVC coated, rigid steel,factory elbows for bends in PVC conduit runs which are
longer than 100', or in PVC runs which have more that two bends, regardless of their
length.
N. Use double locknut construction on conduit which terminates at electrical enclosures,
pull boxes,motor terminal enclosures, etc.,with an approved bushing over the conduit.
Increase the length of the conduit threads at outlets and junction boxes wherever
necessary to accommodate double locknuts and bushings. Seat all bushings fully against
the end of the conduit.
O. Generally, conduit runs shall not be installed in concrete slabs, but shall be installed in
cushion sand below slabs. Where specifically indicated to be cast into concrete, conduits
shall be rigid steel and shall be located in the middle between top and bottom
reinforcing. Maintain a minimum of 1-1/2" concrete cover at all locations. The
maximum size of conduit permitted to be embedded in slabs is 1". Do not route conduit
in a manner to cross each other. Conduit shall have a minimum spacing of 1-1/2" apart.
Unless specifically indicated, conduits shall not be placed in slabs on grade.
P. Use PVC coated, rigid metal conduit for all conduits penetrating slabs. Where PVC
coated, rigid steel or aluminum conduit joins a dissimilar conduit, the fittings shall also
be PVC coated. PVC conduit in slabs shall be protected from mechanical damage by
extending PVC coated rigid metal conduit a minimum of 12" into the concrete at the
transition.
Q. Use suitable conduit caps to protect installed conduit against entry of dirt and moisture.
Conduits 16111-5
FTW99425
R. Install empty conduits in or below-slabs so that a threaded fitting with PVC plug is
placed on each conduit and is flush with the concrete or finished floor surface.
3.02 UNDERGROUND DUCT BANK INSTALLATION
A. Install top of duct bank minimum of 18"below finished grade.
B. Install conduit with minimum grade of 4"per 100'.
C. Terminate conduit in end bell at manhole entries.
D. Stagger conduit joints in concrete encasement a minimum of 6" vertically.
E. Use suitable separators and chairs installed not greater than 4' on centers. Band conduit
together with suitable banding devices. Securely anchor conduit to prevent movement
during concrete placement.
F. Provide a minimum of 3" concrete cover at bottom,top, and sides of duct bank.
G. Provide two No. 4 steel reinforcing bars in top of bank under paved areas.
H. Color of concrete encasement shall be red.
I. Duct bank trench shall be backfilled with material free from large rocks, paving material,
or large angular substance.
END OF SECTION
Conduits 16111-6
PM FTW99425
TABLE OF CONTENTS
1. Part A - Notice to Bidders
- Comprehensive Notice to Bidders
2. Special Instructions to Bidders
3. Minority and Women Business Enterprise Specifications
4. Part B - Proposal
5. Part C - General Conditions (City of Fort Worth)
6. Part D - Special Conditions
7. Part E - Material and Construction Specifications
8. City of Fort Worth Standard Certificate of Insurance
9. Contractor Compliance With Worker's Compensation Law .
10. Part F - Bonds (City of Fort Worth):
a. Performance Bond
b. Payment Bond
C. Maintenance Bond
11. Part G - Contract (City of Fort Worth)
Appendix A - Easements
(See Special Conditions)
Appendix B - Storm Water Pollution Prevention Plan
PART A
NOTICE TO BIDDERS
PART A- NOTICE TO BIDDERS
Sealed proposals for the following:
FOR: NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
WATER DEPARTMENT PROJECT NUMBER PW77-060770140490
DEPARTMENT OF ENGINEERING PROJECT NUMBER 2923
Addressed to Mr. Bob Terrell, City Manager of the City of Fort Worth, Texas will be
received at the Purchasing Office until 1:30 p.m., Thursday, DECEMBER 16, 1999 and
then publicly opened and read aloud at 2:00 p.m. in the Council Chambers. Plans and
Specifications for this project may be obtained at the office of the Department of
Engineering, Municipal Office Building, 1000 Throckmorton Street, Fort Worth, Texas.
One set of plans and documents will be provided for a deposit of fifty dollars ($50.00).
This deposit is refundable if the documents are returned in good condition within ten
(10) days after the bids are opened. Additional sets may be purchased on a
nonrefundable basis for fifty dollars ($50.00) per set.
A majority of the work consists of the following:
New Pump Station, Yard Piping, Electrical and SCADA
Approximately 1,500 LF 24" Waterline and Appurtenances
Included in the above will be all other items of construction as outlined in the Plans and
Specifications.
In accordance with City of Fort Worth Ordinance No. 13471 as amended by Ordinance
No. 13781, the City of Fort Worth has goals for the participation of minority business
enterprises and women business enterprises in City contracts. A copy of the ordinance
can be obtained from the Office of the City Secretary. In order for a bid to be
considered responsive, the AFFIDAVIT STATEMENT included within these bid
documents must be completed and submitted with the bid. Failure to submit the
completed AFFIDAVIT STATEMENT shall render a bid non-responsive. In addition,
the M/WBE UTILIZATION FORM, M/WBE GOALS WAIVER FORM, AND GOOD
FAITH EFFORT FORM, as applicable, must be submitted within five (5) City business
days after the bid opening. Failure to comply shall render a bid non-responsive.
For additional information concerning this project, please contact Anthony Wilkins,
Project Manager, at (817) 871-8047 or J.R. Baddaker, P.E. or Mike Brownlee, E.I.T.,
Freese and Nichols, Inc. at (817) 735-7300.
Advertising Dates:
November 18. 1999 November 24, 1999
FTW99425 A-1
COMPREHENSIVE NOTICE TO BIDDERS
Sealed proposals for the following:
FOR: NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
WATER DEPARTMENT PROJECT NUMBER PW77-060770140490
DEPARTMENT OF ENGINEERING PROJECT NUMBER 2923
Addressed to Mr. Bob Terrell, City Manager of the City of Fort Worth, Texas will be
received at the Purchasing Office until 1:30 p.m., DECEMBER 16, 1999 and then
publicly opened and read aloud at 2:00 p.m. in the Council Chambers. . Plans and
Specifications for this project may be obtained at the office of the Department of
Engineering, Municipal Office Building, 1000 Throckmorton Street, Fort Worth, Texas.
One set of plans and documents will be provided for a deposit of fifty dollars ($50.00).
This deposit is refundable if the documents are returned in good condition within ten
(10) days after the bids are opened. Additional sets may be purchased on a
nonrefundable basis for fifty dollars ($50.00) per set.
A majority of the work consists of the following:
New Pump Station, Yard Piping, Electrical and SCADA
Approximately 1,500 LF 24" Waterline and Appurtenances
Included in the above will be all other items of construction as outlined in the Plans and
Specifications.
The City reserves the right to reject any and/or all bids and waive any and/or all
formalities.
Award of Contract: No bid may be withdrawn until the expiration of ninety (90) days
from the date bids are opened. The award of contract, if made, will be within ninety
(90) days after the opening of bids, but in no case will the award be made until all the
necessary investigations are made as to the responsibility of the bidder to whom it is
proposed to award the contract.
Bidders are responsible for obtaining all addenda to the contract documents and
acknowledging receipt of the addenda by initialing the appropriate spaces on the
Proposal form. Bids that do not acknowledge receipt of all addenda may be rejected as
being non-responsive. Information regarding the status of addenda may be obtained
by contacting Department of Engineering at (817) 871-7910.
FTW99425 A-2
In accordance with City of Fort Worth Ordinance No. 13471 as amended by Ordinance
No. 13781, the City of Fort Worth has goals for the participation of minority business
enterprises and women business enterprises in City contracts. A copy of the ordinance
can be obtained from the Office of the City Secretary. In order for a bid to be
considered responsive, the AFFIDAVIT STATEMENT included within these bid
documents must be completed and submitted with the bid. Failure to submit the
completed AFFIDAVIT STATEMENT shall render a bid non-responsive. In addition,
the M/WBE UTILIZATION FORM, M/WBE GOALS WAIVER FORM, AND GOOD
FAITH EFFORT FORM, as applicable, must be submitted within five (5) City business
days after the bid opening. Failure to comply shall render a bid non-responsive.
For additional information concerning this project, please contact Anthony Wilkins,
Project Manager, at (817) 871-8047 or J.R. Baddaker, P.E. or Mike Brownlee E.I.T.,
Freese and Nichols, Inc. at (817) 735-7300.
BOB TERRELL GLORIA PEARSON
CITY MANAGER CITY SECRETARY
Department of Engineering
A. Douglas R maker, P.E.
Director
Advertising B Dates: :
Y
Rick Trice, P.E.
November 18. 1999 Manager, Consultant Services
November 24, 1999
FTW99425 A-3
SPECIAL INSTRUCTIONS TO BIDDERS
1. PREQUALIFICATION REQUIREMENTS: A current financial statement, an
acceptable experience record and an acceptable equipment schedule must be
filed with the director of the Water Department at least one week prior to the hour
for opening bids. The financial statement required shall have been prepared by an
independent certified public accountant or an independent public accountant
holding a valid permit issued by an appropriate state licensing agency, and shall
have been so prepared as to reflect the current financial status. This statement
must be current and not more than one (1) year old. In the case that a bidding
date falls within the time a new statement is being prepared, the previous
statement shall be updated by proper verification. Proposals submitted by the
prospective bidder who has not fulfilled the above requirements shall remain
unopened.
Prospective bidders whose qualifications are not deemed to be appropriate to the
nature and/or magnitude of the project on which bids are to be received will be
notified before the date of bid opening, and any proposals submitted by them shall
be returned unopened. Liquid assets in the amount of ten (10%) percent of the
estimated project cost will be required.
For an experience record to be considered acceptable for a given project, it must
reflect the experience of the firm seeking the qualification in work of both the
same nature and magnitude as that of the project for which bids are to be
received, and such experience must have been on projects completed not more
than five (5) years prior to the date on which bids are to be received. The
Director of the Water Department shall be the sole judge as to the acceptability of
experience for qualification to bid on any Fort Worth Water Department project.
The prospective bidder shall schedule the equipment he has available for the
project and state that he will rent such additional equipment as may be required to
complete the project on which he submits a bid.
2. BID SECURITY: A cashier's check, or an acceptable bidder's bond, payable to
the City of Fort Worth, in an amount of not less than five (5%) percent of the
largest possible total of the bid submitted must accompany the bid, and is subject
to forfeiture in the event the successful bidder fails to execute the Contract
Documents within ten (10) days after the contract has been awarded. To be an
acceptable surety on the bond, (1) the name of the surety shall be included on the
current U.S. Treasury list of acceptable sureties, or (2) the surety must have
capital and surplus equal to ten times the limit of the bond. The surety must be
licensed to do business in the State of Texas. The amount of the bond shall not
exceed the amount shown on the treasury list or one-tenth (1/10) the total capital
FTW99425 SI-1
and surplus.
3. BONDS: A performance bond, a payment bond, and a maintenance bond, each
for one hundred (100%) percent of the contract price, will be required. Refer to
Part C - General Conditions, Item C3-3.7, as well as Part D - Special Conditions.
4. WAGE RATES: Not less than the prevailing wage rates established by the City of
Fort Worth, Texas, and as set forth in the Contract Documents must be paid on
this project.
5. AMBIGUITY: In the case of ambiguity or lack of clearness in stating prices in the --
Proposal, the City reserves the right to adopt the most advantageous construction
thereof to the City or to reject the Proposal.
6. BIDDER LICENSE: Bidder must be a licensed Contractor in the State of Texas.
7. NONRESIDENT BIDDER: Pursuant to Article 6018, Tex. Rev. Civ. Stat., the City
of Fort Worth will not award this contract to a nonresident bidder unless the
nonresident's bid is lower that the lowest bid submitted by a responsible Texas
resident bidder by the same amount that a Texas resident bidder would be
required to underbid a nonresident bidder to obtain a comparable contract in the
state in which the nonresident's principal place of business is located.
"Nonresident bidder" means a bidder whose principal place of business is
not in this state, but excludes a contractor whose ultimate parent company
or majority owner has its principal place of business in this state.
"Texas resident bidder" means a bidder whose principal place of business -
is in this state, and includes a contractor whose ultimate parent company or
majority owner has its principal place of business in this state.
This provision does not apply if this contract involves federal funds.
The appropriate blanks in the Proposal must be filled out by all nonresident
bidders in order for the bid to meet specifications. The failure of a nonresident
contractor to do so will automatically disqualify that bidder.
8. PAYMENT: If the bid amount is less than $25,000.00, the contract amount shall 4
be paid in one lump sum upon completion and acceptance by the City of Fort
Worth Water Department.
9. AGE: In accordance with the policy ("Policy') of the Executive Branch of the
Federal Government, Contractor covenants that neither it nor any of its officers,
members, agents, employees, program participants or subcontractors, while
FTW99425 SI-2
engaged in performing this contract, shall, in connection with the employment,
advancement or discharge of employees or in connection with the terms,
conditions or privileges of their employment, discriminate against persons because
of their age except on the basis of a bona fide occupational qualification,
retirement plan or statutory requirements.
Contractor further covenants that neither it nor its officers, members, agents,
employees, subcontractors, program participants, or persons acting on their
behalf, shall specify, in solicitations or advertisements for employees to work on
this contract, a maximum age limit for such employment unless the specified
maximum age limit is based upon a bona fide occupational qualification, retirement
plan or statutory requirement.
Contractor warrants it will fully comply with the policy and will defend, indemnify
and hold City harmless against any claims or allegations asserted by third parties
or subcontractors against City arising out of Contractor's and/or its
• subcontractors' alleged failure to comply with the above-referenced Policy
concerning age discrimination in the performance of this agreement.
10. DISABILITY: In accordance with the provisions of the Americans with Disabilities
Act of 1990 ("ADA"), Contractor warrants that it and any and all of its
subcontractors will not unlawfully discriminate on the basis of disability in the
provision of services to the general public, nor in the availability, terms and/or
conditions of employment for applicants for employment with, or employees of
Contractor or any of its subcontractors. Contractor warrants it will fully comply
with ADA's provisions and any other applicable federal, state, and local laws
concerning disability and will defend, indemnify and hold City harmless against any
claims or allegations asserted by third parties or subcontractors against City
arising out of Contractor's and/or its subcontractors' alleged failure to comply with
the above referenced laws concerning disability discrimination in the performance
of this agreement.
11. MINORITY AND WOMEN BUSINESS ENTERPRISES: In accordance with City of
Fort Worth Ordinance No. 11923, the City of Fort Worth has goals for the
participation of minority business enterprises and women business enterprises in
City contracts. A copy of the Ordinance can be obtained from the Office of the
City Secretary. In order for a bid to be considered responsive, the AFFIDAVIT
STATEMENT included with these bid documents must be completed and
submitted with the bid. Failure to submit the completed AFFIDAVIT STATEMENT
shall render a bid non-responsive. In addition, the bidder shall submit the
MBE/WBE UTILIZATION FORM, PRIME CONTRACTOR WAIVER FORM
AND/OR THE GOOD FAITH EFFORT FORM (Documentation), as appropriate.
The documentation must be received no later than 5:00 p.m., five (5) City
FTW99425 SI-3
business days after bid opening. The bidder shall obtain a receipt from the
appropriate employee of the managing department to whom the delivery was
made. Such receipt shall be evidence that the documentation was received by the
City. Failure to comply shall render a bid non-responsive.
Upon request, Contractor agrees to provide the Owner complete and accurate
information regarding actual work performed by a Minority Business Enterprise
(MBE) and/or a Woman Business Enterprise (WBE) on the contract and payment
therefore. Contractor further agrees to permit an audit and/or examination of any
books, records, or files in its possession that will substantiate the actual work
performed by an MBE and/or WBE. The misrepresentation of facts (other than a
negligent misrepresentation) and/or the commission of fraud by the Contractor will
be grounds for termination of the contract and/or initiating action under the
appropriate federal, state or local laws or ordinances relating to the false
statements. Further, any such misrepresentation (other than a negligent
misrepresentation) and/or commission of fraud will result in the Contractor being
determined to be irresponsible and barred from participating in City work for a "-
period of time of not less than three (3) years.
The City will consider the Contractor's performance regarding its M/WBE program
in the evaluation of bids. Failure to comply with the City's M/WBE Ordinance, or
to demonstrate "good faith effort", shall result in a bid being rendered non= -
responsive to specifications.
Contractor shall provide copies of subcontracts or co-signed letters of intent with
approved M/WBE subcontractors prior to issuance of the Notice to Proceed.
Contractor shall also provide monthly reports on utilization of the subcontractors to
the City's M/WBE office.
The Contractor may count first and second tier subcontractors and/or suppliers
toward meeting its goals. The Contractor may count toward its goal a portion of
the total dollar amount of the contract with a joint venture equal to the percentage
of the M/WBE participation in the joint venture for a clearly defined portion of the
work to be performed. All M/WBE contractors used in meeting the goals must be :.
certified prior to the award of the Contract. The M/WBE contractor(s) must be
certified by either the North Central Texas Regional Certification Agency
(NCTRCA) or Texas Department of Transportation (TXDOT), Highway Division
and must be located in the nine (9) county marketplace or currently doing business
in the marketplace at the time of bid. The Contractor shall contact all such
M/WBE subcontractors or suppliers prior to listing them on the M/WBE utilization
or good faith forms as applicable. Failure to contact the listed M/WBE
subcontractor or supplier prior to bid opening may result in the rejection of bid as
non-responsive.
FTW99425 SI-4
Whenever a change order affects the work of an M/WBE subcontractor or
supplier, the M/WBE shall be given an opportunity to perform the work.
Whenever a change order exceeds ten (10%) percent of the original contract, the
M/WBE coordinator shall determine the goals applicable to the work to be
performed under the change order.
During the term of the contract the contractor shall:
Make no unjustified changes or deletions in its M/WBE participation
commitments submitted with or subsequent to the bid, and,
If substantial subcontracting and/or substantial supplier opportunities arise
during the term of the contract which the contractor had represented he
would perform with his forces, the contractor shall notify the City before
subcontracts or purchase orders are let, and shall be required to comply
with modifications to goals as determined by the City, and,
Submit a REQUEST FOR APPROVAL OF CHANGE FORM, if the
contractor desires to change or delete any of the M/WBE subcontractors
or suppliers. Justification for change may be granted for the following:
Failure of Subcontractor to provide evidence of coverage by
Worker's Compensation Insurance.
Failure of Subcontractor to provide required general liability of other
insurance.
Failure of Subcontractor to execute a standard subcontract form in
the amount of the proposed used by the Contractor in preparing his
M/WBE Participation plan.
Default b the M/WBE subcontractor or supplier in the performance
Y PP
of the subcontractor.
Within ten (10) days after final payment from the City, the Contractor shall
provide the M/WBE Office with documentation to reflect participation of
each subcontractor and supplier used on the project, inclusive of M/WBEs.
FTW99425 SI-5
2x-14-2000 4:22PM FROM CONTROL SPECIALIST 817 638 2629 P.2
ATTACHMENT 'iA
City of Fort Worth gage 102 of2
Minority and Women Business Enterprise Specifications
�_ �� ��_ 1 MBENVBE UTILIZATION
�r
�rTPou 5rEC.I At_.I ST t FJ G 12.12�I9
PRIME COMPANY NAM£ eIu DATE�---•—
las�-►Jmc BC-a�C�t STw �tau rAF1 SrA. f gaL*t 2'T L3
PROJECT NAME 4tW l wpm"ArN )NST4%A Arr WJ– tJtTS PROJECT MULL ER
Carrs My U rROJacc GQ4L: IAVWBE ptJUMN:Ac&wcu&vf&;
Failure to complete this form, in its ="etty with supporting documentation, and received by the.Managing
Department on or before 5:00 p.m. fire (5) City business days after bid owing,exclusive of bid opening data,will
result in the bid being considered non-responsive to bid specifications.
The undersigned bidder agrees to enter into a formal agreement with the MBE and/or INBE firms for work listed in tAis
schedule, conditioned upon execution of a contract with the City of Fort Worth..:The intentional and/or knowing
misrepresentation of facts is grounds for consideration of disqualification and will.r in The bid being considered
non-responsive to speciticatma.
Com pony Name,Contact Name, Ca tltled Specify$lLC0T**Mn9 Speck�'Items to be Dollar Amount
Address,and Telephone Na Scope of tAlork Supplied('). £
,( ecwRF fN 'ice 2Z 1,278
Mr*Ws minit to tooted Into tl(i** 4aft bivatnmse Intl*atidcatplape at the ume of W.
In SPar ►aM.trMsfi whicirMWBE'sn bu Li uiglf�.d endla items to be sp�pllad:
A o1l ww.lo tie !r 1n.adM ► h+ti:c[+�1Rtaiwis+d tpe MINI
1'I Mwft aaclr Thr iw#sk . TMf.Mises itis lsvei4f aubeosRaallpp bNow ilia pdrat! ... l.af a dihet.psllnrnt
f t>trprin+roonl or W�i•ahaoiNradortr+oA.lau+ra;t�`fir:=p+T t b5r i#uhoo for 1�
al: IirtY"ti.,.
THIS FORM MUST BE RECEIVED BY THE MANAGING DEPARTMENT BY 5:00 p.m.,FIVE(5)CITY BUSINESS DAYS AFTER BID
OPENING,EXCLUSIVE OF THE BID OPENING DATE
Rev.erilli
b
2-14-2000 4.23PM FROM CONTROL SPECIALIST 817 638 2629 P.3
ATTACHMENT 1A
Page 2 of 2
Cly of Fort Worth
Minority and Women Business Enterprise Specifications
MBEIWBE UTILIZATION
Canpeey Neme,Comeau k a". c0tlllsa SpecifjtAll CW*44ing city At wags babe Douu Amount
Address,and Teloplwpe No. Scope of Wak
9A
The bidder further agrees to provide, directly to the City upon request, complete and accurate information regarding
actual work performed by all subcontractors, including MSE(s) and/or WBE(s) arrangements submitted with this bid.
The bidder also agrees to allow an audit and/or examination of any books, records and files held by their company
that will substantiate the actual work performed by the MBE(s) and/or WBE(s) on this contract, by an authorized
officer or employee of the City. Any intentional and/or knowing misrepresentation of facts will be grounds for
terminating the contract or debarment from City work for a period of not less than three (3) years and for initiating
action under Federal,State or Local laws concerning false statements. Any failure to comply with this ordinance and
creates a material breach of contract may resuH In a determination of an irresponsible offeror and bared from
participating in City work for a period of time not less than one(1)year.
ALL BEs and WBEs MUST BE CERTIFIED BY THE CITY BEFORE CONTRACT AWARD
. :ri'w►es W, 100tS
ARorized Signature Printed Signature
0.)6ea" "A►'JAGEaz
Title Contact Name and Title(if different)
&*nWoL- 5feCtAWT gli- i.s8- ZGZ,7
C;W p—Name Telephone Number(s)
Fo .max j.4i gI?- 4s- 25
Z�o7i AZ
uatim
�� T O
ChylSa t 0p Code ate
THIS FORM MUST BE RECEIVED BY THE MANAGING DEPARTMENT BY 5..00 p.m.,FIVE(5)CITY BUSINESS DAYS AFTER BID
OPENING,EXCLUSIVE OF THE BID OPENING DATE
Rev.6f2J'i8
' City of Fort Worth
Minority and Women Business Enterprises Specifications
4 Affidavit Statement
" Project Name K6�H fyff,,N Scmaf--r 85111*?LWtP0 Project No. fV4T7- 060770140410
�Jl 7DT..
» L:tRi* Q4Si38M€:, # iCt) �TE
as�Y•�?TC� v�JC :.. WiY-.,.. C,�nv:�tvna� Ga ~'Ai, W. moi. ( 'Hy q- 1�TtC—
'�t� yka.�c^wx�!s �t}��i':�x.
X ;wF D:a it°T Nf �.,f7i�x;Bt[ �u=.aP NIN 01M,
Y.RES€ ' �„ iAI TF�1Sw::>: i f 3i"1NG
'.v•�f..f��a.:w.,�<?}«:Cs*:sausn(ou�ras -N.-s a�aUE- K„fic'N."IT�
r,a,
................TD:ER.�. . ONESPC
a
.. .: ... ........ ...:....................... .....................:..........•.............,....................:.. a............ -.'r;;:,ca..:o,::tAcm wYc:«<,,.c.
The undersigned bidder hereby certifies that they will comply with the City's
'M/WBE Ordinance and the specifications of this bid in the following manner.
[check the most appropriate nranber(s]]
t. Y THE M/WBE PARTICIPATION WILL MEET OR EXCEED THE STATED
GOAL, WILL COMPLETE THE MMBE UTILIZATION FORM.
" 5 2 THE MJWBE PARTICIPATION WILL BE LESS THAN THE STATED
GOAL,WILL COMPLETE"GOOD FAITH EFFORT FORM".
3. NO M/WBE PARTICIPATION,WILL COMPLETE"GOOD FAITH
EFFORT".
4. NO SUBCONTRACT OR SUPPLIER OPPORTUNITIES AVAILABLE,
WILL COMPLETE WAIVER FORM.
Vo-
utho ed 1gnatu Printed Signature
tTJE=M-T
Tale Contact Name and Title(if different)
C.o"moo, SFGCIAL-I STS I N C 517- (3S - Z6 z9
Company Name Contact Telephone Number(s)
`tom" 0. T�,e 14l S l� ir,38 Z -
�. Address Fax Number
1`0AP40KZ(oZ
City/StateMp Code Date
Rev 316!96
PART B - PROPOSAL
(This Proposal must not be removed from this book of Contract Documents)
TO: Mr. Bob Terrell
City Manager
City of Fort Worth, Texas
FOR: NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
WATER DEPARTMENT PROJECT NUMBER PW77-060770140490
DEPARTMENT OF ENGINEERING PROJECT NUMBER 2923
Includes the furnishing of all materials (except as specified to be furnished by the City),
equipment and labor for the installation of all improvements and appurtenant work shown
in the plans and specification, all necessary appurtenances and incidental work to provide
a complete and serviceable project.
Pursuant to the foregoing "Notice to Bidders", the undersigned bidder, having thoroughly
examined the contract documents, including plans, special contract documents, and the
General Contract Documents and General Specifications for Water Department Projects,
the site of the project and understanding the amount of work to be done, and the
prevailing conditions, hereby proposes to do all the work, furnish all labor, equipment and
material except as specified to be furnished by the City, which is necessary to fully
complete the inspection and approval of the Director of the City Water Department of the
City of Fort Worth, Texas; and binds himself upon acceptance of this proposal to execute
a contract and furnish an approved Performance Bond, Payment Bond, and Maintenance
Bond, and such other bonds, if any, as may be required by the Contract Documents for
the performing and completing of the said work.
Contractor proposes to do the work within the time stated and for the following sums:
(Furnish and install, including all appurtenant work, complete in place, the following
items):
FTW99425 B-1
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
UNIT ONE - YARD PIPING, 36-INCH WATERLINE, WATERLINE CONNECTIONS
1. 1 LS Yard Piping for Pump Station
Including Piping, Fittings and
Appurtenances for Pump Station Site
ONE NuNnkcp TiiRef-7rA tsmJ Dollars
�p and
Cents
per LS $ /04,000 $ /03,OOa-2. 1 EA 16" Gate Valve and Valve Vault
Including Appurtenant Piping and
Equipment
` S1,tfcm Thousand Dollars
and
nlb Cents U-0 09
per EA $ /41000 $ 14"ASU
1 1 EA Remotely Operated Motor Operated
16" Butterfly Valve and Operator
Stand Installed with NS II / ES II
Transfer Meter Vault Including
! Appurtenant Piping and Equipment
!en Thvu6&nd Dollars
and
A10 Cents ud 00
per EA $ /0,000 $ 10, 000
4. 2 EA Meter Vaults Including 8" Bypass
Piping, 2 - 16" Isolation Gate Valves
and Vaults, Fire Hydrant Assembly,
Appurtenant Piping and Equipment
fwu Thousa4Dollars
and
� rid d Cents `v o0
per EA $ 82, o00 $ 16110,00
FTW 99425 B-2
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
5. 1 LS For Chlorine Analyzer, Water
Sample Station, Ph/Temperature
Meter and Pressure Transmitter and
Appurtenances to be Installed in the
New NS III Meter Vault on Discharge
Side of Pump Station
Fi-teen Yh o usa nd Dollars
and
A10 Cents 0 0
- per LS $ l 5,Uoo $ l
6. 1 LS Tie-In to Existing 24" Waterline and
Existing 16" Discharge Piping with
New 16" x 16" Tee and New 16" x
24" Reducer (Sheet 3A)
C14k, T oases d Dollars
and ov vv
do Cents
per LS
7. 1 LS For Connection to Existing 30"
Suction Header at Line "A" Sta 2+48
(Sheet 3A)
SIx4-gcn 7-housclAd Dollars
and
. n/a Cents p o
per LS $ /4J0000-0$ 16,000
8. 1 LS For Connection to Existing 24"
Waterline at Line "B" Sta 0+00
(Sheet 3A)
Seven TAou.suhcl Dollars
and
/Vo Cents o 0 00
per LS $ 7, 000 $ 000
FTW 99425 B-3
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
9. 1 LS For Modifications to the 21"
Waterline (Sheet 9A) Including All
Piping, 12" Gate Valve, Fire Hydrant
Assembly, Fittings and
Appurtenances
Tweniy Thoa.6dmd Dollars
- and
No Cents 09 00
per LS $ 20, 000 $ 201 UoU r
10. 1,403 LF 36" Waterline Including Piping,
Fittings, Closure Pieces, Joint
Restraint, and Appurtenance
014Lc
L dundad Six �je On
and
0 Cents 100
per LF $ l ro l —
1. LS Work Performed by H.S.Q. to
Complete Stage One - Piping Plan
as Specified and Shown on the
Drawings
Niter-! ~THvvSA�n Dollars
and
oto Cents
per LS $ 301600 00 $ 30,1000
12. 1 LS For Electrical Work Required to
Complete the Stage One - Piping
Plan as Specified and Shown on the
Drawings Including All Provisions for
Temporary Power
TN�RT�t E►�t-rr�I��bDollars
and
"o Cents 00
per LS $ 38,oco— $ 38,�QO
c
13. 1,738 LF Trench Safety System
Or.►E Dollars
and
�r F-I r--r%4 Cents 7
I� per LF $ � � $ 2,
FTW 99425 B-4
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
14. 1 LS Install and Maintain Erosion and
Sediment Control During Entire
Construction Period
C` mr -t4oUSANo, owe NvNyeEoDollars
and
1.to Cents
per LS $ 1,10000 $ 11100°0
15. 1 LS Post Construction Hydro-Mulch
Seeding For All Areas Disturbed
During Construction Activities
(544- iV4xjsAt w ,-rw0 Nvr►arzGvDollars
and
No Cents _
0
per LS $ l,Zoo00 $ it Z,00 p
16. 1 LS AQ,Q1<DEDUCT> For All Additional
Work Required to Complete Stage
One Piping Plan as Specified and
Shown on the Drawings but Not
Included in Other Items
Sixieen 'Thousand Dollars
anc+
A/O Cents v_o QP
per LS $ 14,000 S l6, DOO
r
F
rFTW99425 B-5
r
NORTH BEACH STREET N.S. III PUMP STATION EXPANSION
PAY APPROXIMATE DESCRIPTION OF ITEMS WITH UNIT AMOUNT
ITEM QUANTITY BID PRICES WRITTEN IN WORDS PRICE BID
21. 1 LS ADD/<DEDUCT> For All Additional
Work Required to Complete Stage
Two Pump Station Plan as Specified
and Shown on the Drawings but Not
Included in Other Items
Sire,„ Z'hvusand Dollars
and
Md Cents ®® 8m
per LS $ 14,1000 $ l6,Dao
ALTERNATE BID ITEM
22. 1 EA 30" Butterfly Valve and Valve Vault
Including Appurtenant Piping and
Equipment
Forty Thousand Dollars
and
A10 Cents oa o0
per EA $ ¢U,000 $ 4 0,000'
BID SUMMARY FOR NORTH BEACH N.S. III PUMP STATION EXPANSION
4W TOTAL FOR UNIT ONE (Bid Items 1 through 16) $ (o -73, 7 to
00
TOTAL FOR UNIT TWO (Bid Items 17 through 21) $ 383, 000—
ALTERNATE
383, 000`ALTERNATE BID ITEMS (Bid Item 22) $ '10,006
BASE BID TOTAL (Bid Items 1 though 21) $ (j USG, y4
ao
ALTERNATE BID TOTAL (Bid Items 1 through 22) $ 1, 076, y0
36" waterline pipe shall be in accordance with City of Fort Worth Water Department
specification E 1-4 or E 1-6.
An Bidder/Contractor shall check the pipe material to be used for 36" diameter waterline pipe and
yard piping.
[✓] E1-4 Concrete Pressure Pipe and Fittings
E1-6 Ductile Iron Pipe
FTW 99425 B-7
PART B - PROPOSAL (continued)
Within ten (10) days after acceptance of this Proposal, the undersigned will execute the formal
contract and will deliver an approved Surety Bond and such other bonds as required by the
Contract Documents, for the faithful performance of the Contract. The attached bid security in
the amount of five (5%) percent is to become the property of the City of Fort Worth, Texas, in
the event the contract or bonds are not executed and delivered within the time above set forth,
as liquidated damages for delay and additional work caused thereby.
The undersigned bidder certifies that he has been furnished at least one set of the General
Contract Documents and General Specifications for Water Department Projects dated
January 1, 1978, and that he has read and thoroughly understands all the requirements and
conditions of those General Documents and these specific Contract Documents and
appurtenant plans.
The undersigned bidder certifies that he agrees the OWNER reserves the right to award
either Unit 1 or Unit 2, or both Unit 1 and Unit 2, or neither Unit 1 or Unit 2, and that individual
line items may be deleted from the Proposal from either Unit 1 or Unit 2 to arrive at the most
advantageous bid total for the OWNER. Alternate bid items may be added to or deleted from
the contract-by the Owner. The work includes furnishing all materials, tools, equipment,
transportation, services and all labor and superintendence for the construction as indicated in
the Contract Documents.
The undersigned assures that its employees and applicants for employment and those of anv
labor organization, subcontractors or employment agency in either furnishing or referring
employee applicants to the undersigned are not discriminated against as prohibited by the
terms of City Ordinance No. 7278 as amended by City Ordinance No. 7400.
The Bidder agrees to begin work on the Contract and to complete all work on the Contract
within the time set forth in Part D - Special Conditions, "Completion Time".
(Complete A or B below, as applicable:)
[ ] A. The principal place of business of our company is in the State of
[ ] Nonresident bidders in the State of , our principal place of
business, are required to be percent lower than resident bidders
by state law. A copy of the statute is attached.
[ ] Nonresident bidders in the State of , our principal place of
business, are not required to underbid resident bidders.
[VI B. The principal place of business of our company or our parent company or
majority owner is in the State of Texas.
FTW99425 B-8
Receipt is acknowled ed of the following addenda:
Addendum No. 1 v �o
Addendum No. 2
Addendum No. 3
Respectfully submitted,
Co►-4T L, SPECIAL -LST INC .
(SEAL) By:
If Bidder is Corporation Title: aESL0Ew-r
Address: -7.o . 1 oA 141,
I�A►�oL�E, T?C. 7GZ�Z
FTW99425 B-9
PART C
GENERAL CONDITIONS
?ART C - GENERAL 'CONDITIONS
TABLE OF CONTENTS'
NOVEMBER, 1, 1987
TABLE OF CONTENTS
C1-1 DEFINITIONS
C1-1.1 Definition of Terms C1-1 (1)
C1-1.2• Contract Documents C1-1 (1)
C1-1.3 Notice to Bidders C1-1 ( 2)
C1-1.4 Proposal C1-1 (2)
C1-1.5 Bidder C1-1 (2)
C1-1. 6 General Conditions Cl-1 (2)
C1-1.7 Special Conditions Cl-1. (2)
C1-1. 8 Specifications C1-1 (2)
C1-1. 9 Bond C1-1 (2)
C1-1.10 Contract C1-1 (3 )
C1-1.11 Plans Cl-1 (3 )
C1-1.12 City C1-1 (3 )
C1-1.13 City Council C1-1 (3)
C1-1.14 Mayor C1-1 (3)
C1-1.15 City Manager C1-1 (3)
C1-1.16 City Attorney C1-1 (3)
C1-1.17 Director of Public Works Cl-1 (4)
C1-1.18 Director, City Water Depart-ment C1-1 (4)
C1-1.19 Engineer -1 (4)
C1-1.20 Contractor C1-1 ( 4 )
C1-1. 21 Sureties C1-1 (4 )
C1-1.22 The Work or Project C1-1 (4)
C1-1.23 Working Day C1-1 (4 )
C1-1.24 Calendar Day C1-1 ( 4)
C1-1. 25 Legal Holiday C1-1 (4)
C1-1.26 Abbreviations C1-1 (5)
C1-1.27 Change Order C1-1 (6 )
C1-1.28 Paved Streets and Alleys C1-1 ( 6 )
C1-1.29 ' Unpaved Streets and Alleys - C1-1 ( 6 )
C1-1.30 City Streets C1-1 ( 6)
C1-1.31 Roadway C1-1 ( 6)
C1-1.32 Gravel Street C1-1 ( 6)
- C2-2 INTERPRETATION AND PREPARATION
OF PROPOSAL. '
C2-2.1 Proposal Form C2-2 (1)
C2-2.2 . Interpretation of Quantities C2-2 (1)
C2-2.3 Examination of Contract Documents
and Site C2-2' (2)
C2-2. 4 Submitting of Proposal C2-2 (3 )
C2-2.5 Rejection of Proposals C2-2 (3 )
C2-2. 6 Bid Security C2-2. (3 )
t
C2-2. 8r Withdrawing Proposals C2-2 (4 )
C2-2. 9 Telegraphic Modification of ?roposals C2-2 ( 4 )
-r C2-2 .10 Public Opening of Proposal C2-2 ( 4)
C2-2 .11 Irregular Proposals C2-2 ( 4 )
C2-2 .12 Disqualification of Bidders C2-2 (5 )
C3-3' AWARD AND EXECUTION OF DOCUM2\TS
C3-3 .1 Consideration of Proposals C3-3 (1)
C3-3 . 2 Minority Business Enterpise
Women-Owned Business Enterprise
compliance C3-3 (1)
C3-3 . 3 Equal Employment Provisions C3-3 (1)
C3-3 . 4 Withdrawal of Proposals C3-3 (2)
C3-3 .5 Award of Contract C3-3 ( 2)
C3-3 . 6 Return of Proposal Securities C3-3 (21
C3-3 .7 Bonds C3-3 (2)
C3-3 . 8 Execution of Contract C3-3 (4 )
C3-3 . 9 Failure to execute Contract C3-3 ( 4)
C3-3 .10 Beginning Work C3-3 (4 )
C3-3 .11 Insurance C3-3 (4)
C3-3 .12 Contractor's Obligations C3-3 (7)
C3-3 .13 Weekly Payroll C3-3 (7)
C3-3 .14 Contractor's Contract Administration C3-3 (7)
C3-3 .15 Venue C3-3 ( 8 )
C4-4 SCOPE OF WORK
C4-4.1 Intent of Contract Documents C4-4 (1)
C4-4. 2 Special Provisions C4-4 (1)
C4-4. 3 Increased or Decreased Quantities C4-4 (1)
C4-4 .4 Alteration of Contract Documents C4-4 (2)
C4-4.5 Extra Work C4-4 (2)
C4-4. 6 Schedule of Operations C4-4 (3 )
C4-4.7 Progress Schedules for Water and
Sewer Plant Facilities C4-4 (4 )
C5-5 CONTROL OF WORK AND MATERIALS
C5-5.1 Authority of Engineer C5-5 (1)
CS-5. 2 Conformity with Plans Ct,-5 (1)
C5-5. 3 Coordination of Contract Documents C5-5 (2)
C5-5. 4 Cooperation of Contractor C5-5 (2)
C5-5.5 Emergency and/or Rectification Work CS-5 (3 )
CS-5 . 6 Field Office -05-5 (3 )
CS-5.7 Construction Stakes C5-5 (3 )
CS-5 . 8 Authority and Duties of Irsp_ctors , C5-5 (4 )
C5-5. 9 Inspection CS-5 (5 )
CS-5.10 Removal of Defective and Unauthorized Work C5-3 (5 )
CS-5.11 Substitute Materials or Equipment C5-5 (5 )
CS-5 .12 Samples and Tests of Materials CS-5 ( 6 )
CS-5 .13 Storage of Materials C5-5 ( 6)
CS-5 . 14 Existing Structures and Utilities C5-5 (7)
C5-5 . 15 Interruption of :Service & CS-3 (7)
C5-5 . 16 Mutual Responsibility 'of Contractors CS-5 (8 )
C5-5 . 17 Cleanup
CS-S ( 8 )
C5-5 .18 Final Inspection CS-5 (9 )
(2)
C6-6 L:G=.L RELATIONS PND ?UBLIC R=SPONSIBILITY.
C6=6.1 Laws to be Observed C6-6 (1)
C6-6 .2 Permits and Licenses C6-6 (1)
C6-6 .3 Patented Devices , Materials and Processes C01-6 (1)
C6-6 . 4 Sanitary Provisions C6-6 (2)
C6-6.5 Public Safety and Convenience Co'-6 (2)
Co"-6. 0' Privileges of Contractor in Streets,
Alleys, and Right-of-Way C6-6 (3)
C6-6.7 Railway 'Crossings C6-6 (4)
C6-6. 8 Barricades, Warnings and Watchmen C6-6 (4)
C6-6. 9 Use of Zxplcsives, Drop Weight, etc. C6-6 (5)
C6-6.10 Work Within Easements C6-6 ( 6)
C6-6.11 lnd=Pend=nt Contractor Co'-6 (8)
CS-6.12 Contractor ' s Responsibility for
Damage Claims ' C6-6 (8 )
Co"-6 .13 Contr_ctdr• ' s Claim for Damages C6-6• (10)
C'o-6.14 Adjesht of Relocatioa of Public
IItilities, etc. C5-6 (10)
Co'-6.15 Te-Moorary Sewer Drain Connections COO-6 (10)
Co'-6 .16 Arrancement and Charges of Water
Furnished by City C5-6 (11)
C6-6.17 Use of a Section of Portion of the Work Co'-6 (11)
C6-6.18 Contractor' s Responsibility for Work C6-6 (11)
C6-6 .19 No Waiver of Legal Rights C6-6 (12)
Co'-6. 20 Personal Liability of Public Officials Co"-6 (12)
C6-6. 21 State Sales Tax C6-6 (12)
C7-7 PROSECUTION AND PROGRESS
C7-7.1 Subletting C7-7 (1)
C7-7.2 Assignment of Contract C7-7 (1)
C7-7. 3 Prosecution of the Work C7-7 (1)
C7-7. 4 Limitations of Operations C7-7 (2)
C7-7.5 Character of Workman and Eauipment C7-7 (2)
C7-7.6 Work Schedule C7-7 (3)
C7-7. 7 Time of Commencement and Comm=_tion C7-7 (4 )
C7-7. 8 Extension of time of Completion C7-7 (4)
C7-7.9 Delays C7-7 (4)
C7-7.10 Time of Completion C7-7 (5)
C7-7.11 Suspension by Court Order C7-7 (6)
C7-7.12 Temporary Suspension C7-7 (6)
C7-7.13 Termination of Contract due to
National Emergency C7-7 (7)
C7-7.14 Suspension of Abandonment of the
Work and Annulment of Contract C7-7 (7)
C7-7.15 Fulfillment of Contract C7-7 (9)
C7-7.16 Termination for Convenience of the Onwer C7-7 (10)
C7-7.17 Sa__ty Methods and Practices C7-7 (13)
C8-8 M.=.ASUR:CM=NT AND PANT
CS-8 .1 Measurement of Quantities CS-8 (1)
C8-8 . 2 Unit Prices C8-8 (1)
(3 )
CS-8 . 4 Scop_ of Payment c�-8 ►�,
C8-8.5Partial estimates and Retainage C3-8 (2)
C8-8 . 6 Withholding Payment C3-8 (3)
CS-8 .7 Final Accept-ance _ C8-8 (3 )
C8-8 . 8 Final Payment' C3-8 (3)
CB-8 .9 Adcuacy of Design C3-8 ( 4)
CB-8 .10 General Guaranty CS-B (4)
CS-8 .11 Subsidiary Work C3-8 (5)
C8-8.12 Miscellaneous Placement of Material C3-8 (5 )
CS-8.13 Record Documents C3-8 (5)
4
I
3
(4)
f ,
PART C - GENERAL CONDITIONS
. Cl-1 DEFINITIONS
SECTION C1-1 DEFINITIONS
C1-1 . 1 DEFINITIONS OF TERMS : Whenever in these Contract
Documents the following terms or. pronouns in place of them are
used , the intent and meaning shall , be understood and
interpreted as follows:
C1-1. 2 CONTRACT DOCUMENTS: The Contract Documents are all of
the written and drawn documents , such as specifications ,
bonds , addenda , plans , etc . , which govern the terms and
performance of the contract . These *are contained in the
General Contract Documents and the Special Contract Documents.
a. GENERAL CONTRACT DOCUMENTS :* The General Cont-, act-
Documents
Documents govein all Water Department Projects and
include the following items:
PART A - NOTICE TO BIDDERS (Sample) White
PART B - PROPOSAL (Sample) White
PART C - GENERAL CONDITIONS (CITY) Canary Yellow
(Devel(3per) Brown
PART D - SPECIAL CONDITIONS Green
PART E - SPECIFICATIONS El-White
E2-Golden Rod
E2A-White
PERMITS/EASEMENTS Blue
PART F - BONDS (Sample) White
• PART G - CONTRACT (Sample) White =
b. SPECIAL CONTRACT DOCUMENTS : The Soecial Contract
Documents are prepared for each specific project as
a suoolement to the General Contract Documents and
include the following items:
PART A - NOTICE TO BIDDERS (Advertisement) Same as
• above
PART B - PROPOSAL (Bid)
PART C - GENERAL CONDITIONS
PART D - SPECIAL CONDITIONS
PART E - SPECIFICATIONS
PERKITS/EASEMENTS
PART F - BONDS
PART G CONTRACT
PART H -' PLANS (Usually bound separately)
Cl-1 (1)
C1-1 . 3 NOTICE TO BIDDER'S : All of the legal publications
either actually published. in public advertising mediums or
furnished direct to interested parties pertaining to the work
contemplated under the Contract Documents constitutas the
notice to bidders.
C1-1 . 4 P.tO?OSAL: The completed written and signed offer or
tender of' a bidder to perform the work which. the Owner desires
to have done, together with the bid security, constitutes the
Proposal, which becomes binding upon the Bidder when it is
officially received by the Owner, has been publicly opened and
read and not rejected by the Owner.
i
C1-l . S BIDDBE : Any-. person, persons , firm , partnership,
company, association, corporation; acting 'directly or through
a duly authorized representative, submitting a proposal for
performing the work contemplated under the Contract Documents ,
constitutes a bidder.
C1-1 . 6 G.NE3AL CONDITIONS : ' The General Conditions are the
usual construction and contract requirements which govern the
performance of the work so that it will be carried on in
accordance with the customary procedure , the local statistes ,
and -requirements of the City of Fort Worth ' s charter and
g+, promulgated ordinances.
_. Wherever there may be a conflict between the General
Conditions and Special Conditions , the latter shall take
Precedence and shall govern.
C1-1 . 7 S?ZCIAL CONDITIONS : Spacial conditions are the
specific requirements which are necessary for the particular -
project covered by the Contract Documents and not specifically
covered in the General Conditions . When considered with the
General Conditions and other elements of the Contract
Documents they provide the information which the Contractor
and Owner should have in order to gain a thorough knowledge of
the project.
C1-1 . 8 S?TCIFICATIONS : The Specifications is that section or
part of the Contract Documents which sets f orth in detail the
requirements which must be met by all materials, construction,
workmanship, equipment and services in order to render a
completed and useful project. Whenever reference is made to
standard specif ications, regulations, requirements .. statutes ,,
etc . , such referred• to documents shall become a part of the
Contract Documents just as though they were embodied therein.
C1-1 . 9 BOND: The bond or bonds, are the written guarantee or
security furnished by the Contractor for the prompt and
i
Cl-1 (2)
faithful performance of the contract and include the
X
ollowing: .
a. Performance Bond (see paragraph C3-3 .7 )
b. ?aym=nt Bond (see paragraph C3-3 .7)
C. maintenance Bond (see paragraph C3-3 .7 )
d. ?roposal or Bid Security (se_ Special Instructions
to Bidders, Part A and C2-2. 6)
C1-1 . 10 CONTRACT: The- Contract is the formal signed 'agr=em=nt
between the Owner and the Contractor covering the mutual
understanding of the two contracting parties about the project
i to be completed under the Contract Documents.
� 1 •
C1-1 . 11 PLANS : The clans are the drawings or reproductions
therefrom m_de by the Owner ' s representative showing in detail
the location, dimension and position of the various elements
of the project , including such' profiles , typical
cross-sections, layout diagrams, working drawings, preliminary
drawings and such supplemental drawings as the Owner may issue
- to clarify other drawings or for the purpose of showing
changes in the work hereinafter authorized by the Owner . The
plans are usually bound separately from other parts of the
-€ Contract Documents , but they are a part oaf the Contract
Documents just as though they were bound therein.
C1-1 . 12 CITY: The City of Fort Worth , Texas , a municipal
corporation, authorized° and chartered under the Texas State
i
Statutes , acting by and through its governing body or its City
Manger, each of which is required by charter to perform
--'• specific duties . Responsibility for final enforcement of
Contracts involving the City of Fort North is by Charter
vested in the City Manager. The terms City and Owner are
synonymous.
C1-1 . 13 CITY COUNCIL : The duly elected and qualified
q.
' governing body of the City of Fort Worth, Texas.
C1-1 . 14 MAYOR: The officially elected Mayor, or in his
absence, the Mayor Pro tem of the City of Fort Worth, Texas.
C1-1.15 CITY MANAGER: The officially appointed and authorized
City Manager of the City of Fort Worth , Texas , or his duly
authorized representative.
C1-1.16 CITY ATTORNEY: The officially appointed City Attorney
of the City of Fort Worth, Texas , or his duly authorized
representative. .
C1-1 (3)
C1-1 . 17 DIR CT03 OF PUBLIC. WORKS: The duly appointed official
of the City of Fort north , referred to in the Charter as the
City Engi::eer, or his* duly authorized representative.
C1-1 . 18 DIRECTOR, CITY WATER DEPARTMENT: The duly appointed
Director of the City Water Department of the City of Fort
Worth , Texas , or his duly authorized represeentative ,
assistant, or agents.
C1-1 . 19 ENGINEER: The Director of Public Works, the Director
of the Fort north City dater Department , or their duly
authorized assistants , agents , engineers , inspectors , or
superintendents, acting within the scope o.6 the particular
duties entrusted to them. ,
C1-1 . 20 CONTRACTOR: The person , persons , partnership ,
company, firm, association, or corporation, entering into a
contract with the Owner for the execution of the work, acting _
directly or through a duly authorized representative . A
sub-contractor is a person, firm, corporation, or others under
contract with the principal contractor , supplying labor and
materials or only labor, for work at the site of the project. -
C1-1. 21 SURETIES: The Corporate bodies which are bound by
such bonds are required with and for the Contractor . The
-_:::::,. sureties engaged are to be fully responsible for the entire
and satisfactory fulfillment of the Contract and for any and
all requirements as set forth in the Contract Documents and
approved changes therein.
C1-1. 22 TBE WORK OR PROJECT: The completed work contemplated
in and covered by the Contract Documents , including but not
limited to the furnishing of all labor , materials , tools ,
equipment, and incidentals necessary to prod"uce a completed
and Serviceable project.
C1-1. 23 WORKING DAY: A . working day is defined as a calendar
day, not including Saturdays, Sundays , and legal holidays , in
which the weather or other conditions not under the control of
the Contractor .permit the perfortiance of the principal unit of
work for a period of not less than seven (7 ) hours between
7: 00 a.m. and 6 : 00 p.m. , with exceptions as permitted in
paragraph C7-7.6.
Cl-1 . 24 CALENDAR DAYS : : A calendar day is any day of the week
or month , -no days being excepted.
C1-1. 25 LEGAL HOLIDAYS: Legal holidays shall be observed as
prescribed by the City Council of the City of Fort- Worth for
observance by City employees as follows:
Cl-1 (4)
1. New Year's Day January 1
2. M. L. Ring,' Jr . Birthday Third Monday in January
3. Memorial Day Last Monday in May
4. Indenend_nce Day July 4
5. Labor Day First Monday in September
6. Thanksgiving Day Fourth Thursday in November
7. Thanksgiving Friday Fourth Friday in November
8. Christmas Day December 25
9. Such other days in lieu of
holidays as the City Council
} ray determine
When one of the -above named holidays or a special holiday is
declared by the City Council, falls on Saturday, the holiday
shall b: observed on the orec=_ding Friday or if it falls on
Sunday, it- shall be observed on the following Monday, by those
employees working on working day operations . Employees
working calendar day operations will consider the calandar
holiday as the holiday.
C1-1. 26 ABBREVIATIONS : Wherever the abbreviations defined
herein appear in Contract Documents , the intent and meaning
shall be as follows :
nASHTO - American Association of MGD Million Gallons Per
"Day Highway Transportation
Officials
' ASCE - American Society of Civil CF S - Cubic' Foot per
Engineers Second
LAW - In Accordance With
ASTM - American Society of Min. - Minimum
Testing Materials Mono.- Monolithic
AWWA - American Water Works 3 - Percentum-
�• AssociationR - Radius
ASA - American Standards Association I.D. - Inside Diameter
HI - Hydraulic Institute O. D . - Outside
Diameter
FitAsoh. _ AsphaltE1 ev.- Elevation
Ave Avenue F - Fahrenheit
Blvd. - Boulevard C - Centigrade
P, CI - Cast Iron In. - Inch
CL, - Center Line ?t. - Foot
OI - Galvanized Iron St. - Street
` Lin. - Linear or Lineal CY - Cubic Yard
lb. - Pound Yd. - Yard
MH - Manhole SY - Square Yard
Max. - Maximum L.P. - Linear Foot
D.I. -.Ductile Iron
Cl-1 (5)
C1-1 27 C3ANGE ORDER A " Chang_ Order " is a written
supplemental agreement between the Owner and the Contractor
covering some added or deducted item or feature which may be
found necessary and which was not specifically included in tae
scope of the project on which bids were submitted. Increase
in unit auanti=ies stated in the proposal are not the subject
matter of a Change, Order unless the increase or de=raase is
more than 25% of the amount of the particular item or items in
the originil proposal.
All " Change Orders " shall be prepared by the City from
information as necessary furnished by the Contractor.
C1-1 . 28 PAVED STREETS AND ALLEYS : A paved street or alley
shall be defined as a street or alley having on: of the
following types of wearing surfaces applied over the natural
unimproved surface:
1. Any type of asphaltic concrete with or without
sezarate bass material.
2. Any type of asphalt surface treatment , not
including an oiled surface , with or without
seoarate base material.
3 . Brick, with or without separate base material.
4. Concrete, with or without separate bas= material.
S . Any combination of the above.
C1-1 . 29 UNPAVED STREETS OR P.LLEYS: An unpaved street-, alley,
roadway or other surface is any area except those defined
above for "Paved Streets and Xlleys. 0
C1-1 . 30 CITY STREETS : A city street is defined as ;.:gat area
between the right--of-way lines as the st_eet .is dedicated.
C1-1 . 31 ROADWAY: The roadway is defined as the area between .�
parallel lines two ( 2 ' ) feet back of the curb lines or four
( 4 ' ) f eat back of the average edge or pavement where no curb
exists.
C1-1 . 32 GRAVEL STREET: A gravel street is any unpaved street
to which has been added one or more applications of g=avel or
similar material other than the natural material found on the
street surface before any improvement was made.
Cl-1 (5)
SECTION C - GMNEIIRI� CONDITIONS
C2-2 INTERPRETATI0N PWD
PREPARATION 0= PROPOSAL
SECTION C2-2 INTv-RPRETATION AND PREPARATION OF PROPOSA-1.
C2-2.1 PROPOSAL FORM: The Owner will furnish bidders with
proposal form, which will contain an itemized list of the
items of work to be done or materials to be furnished and upon
which bid prices are requested. The Proposal form will state
the Bidder ' s general understanding of the project to be
completed, provide a space for furnishing the amount of bid
security, and state the basis for entering into a'- formal
contract. The Owner will` furnish forms for the Bidder ' s
"Experience Record, " "equipment Schedule , " and "Financial
Statement," all of which must be properly executed and filed
with the Director of the City water Department one week prior
to the hour for omeninq o= bids.
The financial statement required shall have been prepared by
an independent certified public accountant or an independent
public accountant holding a valid permit issued by an
appropriate state licensing agency, and shall have been so
Dr as to reflect the current financial status . This
statement must be current and not more than one (1) year old.
=' In the case that a bidding date falls within the time a 'new
statement is being prepared, the previous statement shall be
updated by proper verification. Liquid assets in the amount
of ten (10% ) percent of the estimated project cost will be
required.
For an . experience record to be considered to be accent_ble for
a given project, it must reflect the experience o= the firm
seeking qualification in work of both the same nature and
magnitude as that of the project for which bids are to be
received , and such experience must have been on projects
completed not more than five (5 ) years prior to the date on
which are to be received . The Director of the Water
department shall be -sole judge as to the acceptability of
experience for qualification to bid on any Fort north Water
Department project.
The prospective bidder shall schedule the equipment he has
available for the project and state that he will rent such
additional equipment as may be required t'o complete the
project on which he submits a bid.
C2-2 . 2 INTERPRETATION OF QUANTITIES: The quantities of work
and materials to be furnished as may Be listed in the proposal
C2-2(1)
Mp
forms or other parts of the Contract Documents will be
considered as approximate only and will be used for the
purpose of comparing bids on a uniform basis. Payment will be
made to tele Contractor for only the actual quantities of work,
performed or materials furnished in strict accordance with the
Contract Documents and Plans . The quant=ities of work to �e
performed and materials to b: furnished may be increased or
decreased as hereinafter provided, without • in any way
invalidating the unit prices bid or any other requirements of
the Contract Documents.
C2-2 . 3 EXAMINATION Or CONTRACT DOCUMENTS AND SITE Or PROJECT:
Bidders are advised that the Contract Documents on file -with
the Owner -shall, constitute 'all 'of the information which' - -the
Owner will furnish. All additional information and data which
the owner will supply after promulgation of the formal
contract documents shall be issued in the form of written
addenda and shall become part of the Contract Documents jus,;;'_'
as though such addenda were actually written into the original
Contract Documents. '
Bidders are required, prior to the filing of proposal, to read
and become familiar with the Contract Documents , to vis�t the
site of the project and examine carefully all local
conditions , to inform themselves by their own independent
research and investigations, tests, boring, and by such other
means as may be necessary- to gain a complete knowledge of. the
conditions which will be encountered during the construction
of the project . They must judge for themselves a the
difficulties of the work and all attending circumstances
affecting the cost of doing the work or the time required for
its completion, and obtain all information required to make an
intelligent proposal. No information given by the Owner or
any representative of the Owner other than that contained- in
the Contract Documents and officially promulgated addenda
thereto, shall be binding upon the Owner. Bidders shall rely
exclusively and solely upon their own estimates ,
investigation, research , tests, explorations, and other data
which are necessary for `full and complete information upon
which the proposal is to be based. It is mutually agreed that
the submission of a proposal is prima-facie evidence that the
bidder has made the investigations, examinations and tests
herein required. Claims for additional compensation due to
variations between conditions actually encountered in
construction and as indicated in the Contract Documents will
not be allowed.
The logs of Soil Borings, if any, showing on the plans are for
general information only and may not be correct. Neither the
C2-2(2)
Owner nor the Engineer guarantee that the data shown is
representative of conditions which actually exist.
C2-2. 4 SUBMITTING Or PROPOSAL: The Bidder shall submit his
_Proposal on t:^.e form furnished by the Owner. All blank spaces
applicable to the project contained in the form shall be
correctly filled in and the Bidder shall state the prices ,
written in ink in both words and numerals , for which he
proposes to do the work contemplated or furnishe the materials
required. All such .prices shall be written legibly. In case
of discrepancy between the price written in words and the
price written in numerals, the price most advantageous to the
City shall govern.
If a proposal is submitted by an individual, his or her :.ame
must be signed by him (h=r) or his (her) duly authorized agent.
If a proposal is submitted by a firm, association , or
partnership, the name and address of. each member must be
given , and the proposal must be signed by a member of the
firm, association , or partnership,. or by a parson duly
authorized. If a proposal is submitted by a company or
corporation, the company or corporate name and business
address must be given, and the proposal signed by an official
or duly authorized agent. The corporate seal must be affixed.
Power of Attorney authorizing agents or others to sign
proposal must be properly certified and must be in writing and
submitted with the proposal.
�� C2-2 . 5 REJECTION OF PROPOSALS : Proposals may be rejected if
they show any alteration of words or figures , additions not
called for , conditional or uncalled for alternate bids ,
incomplete bids, erasures , or irregularities of any kind, or
contain unbalance value of any items . Proposal tendered or
delivered after the official time designated for receipt of
or000sal shall be returned to the Bidder unopened.
C2-2 . 6 BID SECURITY: No DroDosal will be considered unless it
is accompanie3 by a "Proposal Security" of the character and
in the amount indicated in the "Notice to- Bidders " and the
"Proposal. " The Bid Security is required by the owner as
evidence of good faith on the part of the Bidder, and by way
of a guaranty that if awarded the contract, the Bidder will
within the required time execute a formal contract and furnish
the required performance and other bonds. The bid security of
the three lowest bidders will be ret=fined until the contract
is awarded or other disposition is made thereof . The bid
security of all other bidders may be returned promptly after
the canvass of bids.
C2-2(3 )
C2-?.7 DELIVR?v 0= 2ROPOSAL: No Proposal will be considered
unless it is delivered, accompanied by its pro-a=r Bid
security, t0 the City Manager or his reor=sentative in the
official place of business as set forth in the "Notice to
Bidders . " It is the Bidder ' s sols responsibility to'd_liver
the proposal at tae proper time to the proper place. The mere
fact that a pr000sal was dispatched will *not be considered.
The Bidder must have the proposal actually delivered. ZEach
oro_oosal shall be in a sealed envelops plainly marked with the
word "PROPOSXL, " and the name or description of th_ project as
designated in the "Notice to Bidders. The envelope shall be
addressed to the City Manager, City 3a11, Fort Worth, Texas .
C2-2. 8 WITEDRAWTNG PROPOSALS: Proposals actually filed w=,th
the City Manacer cannot be withdrawn prior to the time set for
opening proposals . A request for non-consideration of a
pr000sal must be made in writing , addressed to the City
Manager , and filed with him prior to the time set for the
opening of proposals. After x.11 proposals not requested for
non-consideration are opened and publicly read aloud, the
proposals for which non-consideration requests have been
properly filed may, at the option of the Owner , be recur_ned -
unoDened.
C2-2. 9 TELEGRAPHIC MODIFICATION OF PROPOSALS: any bidder may
; modify his proposal by telegraphic communication at any time
prior to the time set- for opening proposals , provided such
telegraphic communication is received by the City Manager
prior to the said proposal opening time, and provided further,
that the City Manager is satisfied that a written and duly
authenticated confirmation of such telegraphic communication
over the signature of the bidder was mailed prior to the
pr000sal opening time. If such confirmation is not received
within forty-eight (48) hours after the proposal opening time,
no further consideration will b: given to the proposal.
C2-2. 10 PUBLIC OPENING Or PROPOSAL: Proposals which have been
properly tiled and for which no "Non-consideration Request"
has been received will be publicly opened and read aloud by
the City Manager or his authorized representative at the time
and place indicated in the "Notice to Bidders. " All proposals
which have been•opened and read will remain on file with the
Owner until the contract has been awarded. Bidders or their
authorized representatives are invited to be present for the
opening of bids.
C2-2. 11 IRREGULAR PROPOSALS: Proposals shall be considered as
Bing "Irregular" if they show any omissions , alterations of
form, additions, or.. conditions not called for , unauthorized
alternate bids, or irregularities of any kind. However , the
C2-2(4)