WHEREAS, the City of Fort Worth (City) and Dunaway Associate
Inc. , (Engineer) made and entered into City Secretary Contract No.
24313, (the Contract) which was authorized by the City Council by
M&C C-17014 on the 29th day of September, 1998; and
WHEREAS, the Contract involves engineering services for the
following project:
Engineering contract for the design of Mains 207 and 207A,
Drainage Area Sanitary Sewer System Rehabilitation and
Improvements (Group 3, Contract 4) Part 4.
WHEREAS, it has become necessary to execute Amencbnent No. 1 to
said Contract to include an increased scope of work and revised
maximum fee;
NOW THEREFORE, City and Engineer, acting herein by and through
their duly authorized representatives, enter into the following
agreement which amends the Contract:
1.
Article I, of the Contract is amended to include the addition-
al engineering services specified in M&C C-18014, adopted by the
City Council on 23rd day of May, 2000, and further amplified in a
proposal letter dated March 14, 2000, copies of which are both
attached hereto and incorporated herein. The cost to City for the
additional services to be performed by Engineer total $24,080.06.
2 .
Article II, of the Contract is amended to provide for an
increase in the maximum fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall not
exceed the sum of $92 ,225.06.
00- V COAL j'EC"0G�D
F'IV
FR VE�Y
o
All other provisions of the Contract which are not expressly
amended herein shall remain in full force and effect.
EXECUTED on this the d/ day of 2000, in
Fort Worth, Tarrant County, Texas.
ATT: � �' �0
a Contract Authorization
Gloria Pearso , City Secretary
City Secretary 15"61- Date
APPROVAL RECOb24ENDED: R VED:
A. Douglas Rademaker, P.E. Mike Groomer
Director, Department of Assistant City Manager
Engineering
DUNAWAY ASSOCIATES, INC.
Engin
By:
Name;James DeOtte P.E. R.P.L.S.
ce-P esident
150 Merrimac Circle, Suite 100
Fort Worth, TX 76107
APPROVED AS TO FORM AND LEGALITY:
Tjo
?e_-�:�-
Gary Steinberger
Assistant City Attorney
24313-2
City of Fort Worth, Texas
4Vravoir AndC ounciCommunicniflonl
DATE REFERENCE NUMBER LOG NAME PAGE
5/23/00 **C-18014 30M207 1 of 2
SUBJECT AMENDMENT NO. 1 TO ENGINEERING AGREEMENT WITH DUNAWAY
ASSOCIATES, INC. FOR MAINS 207 AND 207A DRAINAGE AREA SANITARY
SEWER SYSTEM REHABILITATION AND IMPROVEMENTS (GROUP 3, CONTRACT
4) PART 4
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute Amendment No. 1 to
City Secretary Contract (No. 24313) with Dunaway Associates, Inc. in the amount of $24,080.06 to
provide for additional design and survey services, thereby increasing the contract amount to
$92,225.06.
DISCUSSION:
On September 29, 1998 (M&C C-17014), the City Council authorized the City Manager to execute an
engineering agreement with Dunaway Associates, Inc. in the amount of $68,145.00 for the preparations
of plans and specifications for Mains 207 and 207A Drainage Area Sanitary Sewer System
Rehabilitation and Improvements (Group 3, Contract 4) Part 4.
It has been determined that an additional 1,500 linear feet of severely deteriorated sewer lines located
within the project area must be replaced in order to alleviate sewer backup problems to customers.
Due to the close proximity of the identified sewer lines to this project, staff recommends that Dunaway
Associates, Inc.'s contract be amended to provide the necessary design services.
The change order will also allow for the preparation of additional permanent and temporary construction
easements and temporary right-of-entry agreements needed for the additional sewer lines.
Staff considers Dunaway Associates, Inc.'s proposed fee to be fair and reasonable for the additional
services to be provided.
Dunaway Associates, Inc. is in compliance with,the City's M/WBE Ordinance by committing to an
additional 18% M/WBE participation on this amendment No. 1.
F
a
City of Fort Worth, Texas
4vayor and coun"K Communication
DATE REFERENCE NUMBER LOG NAME PAGE
5/23/00 **C-18014 1 30M207 2 of 2
SUBJECT AMENDMENT NO. 1 TO ENGINEERING AGREEMENT WITH DUNAWAY
ASSOCIATES, INC. FOR MAINS 207 AND 207A DRAINAGE AREA SANITARY
SEWER SYSTEM REHABILITATION AND IMPROVEMENTS (GROUP 3, CONTRACT
4) PART 4
FISCAL INFORMATION/CERTIFICATION:
E'
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of
the Commercial Paper-Sewer Fund.
MG:k
I
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to) '
Mike Groomer 6140 � ARROVED
COriginating Department Head: COUNCIL.
A.Douglas Rademaker 6157 (from) MAY 9!>! 2000
PS46 531200 070460410120 $24,080.06
Additional Information Contact: �W`
City Sear m"of th,o
A. Douglas Rademaker 6157 City of Fort Worth.Tmms
DUNAWAY ASSOCIATES, INC.
ENGINEERS • PLANNERS • SURVEYORS
DAI No. 9814000
March 14, 2000
Mr. Tony Sholola, P.E.
City of Fort Worth
Department of Engineering
1000 Throckmorton
Fort Worth, Texas 76102
Reference: Amendment No. 1
Mains 207 and 207A
Drainage Area Sanitary Sewer System Rehabilitation and Improvements
(Group 3, Contract 4), Part 4
Sewer Project No. PS 46-070460410110
D.O.E. Project No. 2089
Dear Mr. Sholola:
Dunaway Associates Inc. (DAI) is pleased to present this Amendment No. 1 for the following
additional services that are beyond our original scope of services.
• 77 LF of additional survey and design for L-6757. (This is a new line replacement
resulting from the re-routing of L-5524 at the City's request.)
• 380 LF of additional survey and design for L-6242. (This line was re-routed at the City's
request.)
• 669 LF of additional survey and design for M-242. (This line is a new line replacement
resulting from the re-routing of L-6751.)
• 284 LF of additional survey and design for L-6751. (This line was re-routed at the City's
request.)
• 87 LF of additional survey and design for L-7581. (This is a new line replacement that
was a re-route at the request of the City.)
• Preparation of 5 new Permanent Sanitary Sewer Easements (one created for the re-route
of L-6242 and four created for the re-route of L-6751.)
• Preparation of 8 new Temporary Right-of-Entries. (Created for replacements of L-5524,
L-5525, and L-6242.)
• Meetings with the property owners (requested by City regarding easement acquisition).
• Meetings with Geotechnical Engineer and Contractors on-site ad
owner's concerns. QMCN� d I RIE ou P1,@
CNN MCINEW"ef
1501 MERRIMAC CIRCLE • SUITE 100 • FORT WORTH,TEXAS 76107-6572 • 817 335-1121 • METRO8 K!''`u N.fy, 33J-7437
• Amendment No. 1
March 14, 2000
Page 2
A summary of the proposed budget for this revised amendment is as follows:
Basic Fee
Design of 1,497 LF of sewer($10.00/LF) $14,970.00
Survey(1,497 LF x $2.86 x 1.1) $4,709.56
Easement Preparation
Permanent Sanitary Sewer Easement ($300 / ea) $ 1,500.00
Temporary Right-of-Entry ($50/ea) $ 400.00
Meetings (5 additional) $2,000.00
Geotechnical Services $500.50
TOTAL PROPOSED AMENDMENT $24,080.06
A summary of the total project fees is as follows:
Contract Description Fee
Original Contract 5,049 LF of sewer $ 68,145.00
Amendment No. 1 Additional 1,497 LF of sewer and related survey, $ 24,080.06
easement preparation, Geotechnical Services and
meetings.
TOTAL PROJECT $ 92,225.06
Please review the enclosed information and do not hesitate to call me if you have any
questions or require additional information regarding this revised proposal.
Sincerely,
DUNAWAY ASSOCIATES, INC.
w
Brian S. Darby, P.E.
BSD/jme
9814000_TSho1o1a_8SD_Amend 1.doc
Enclosure
Cc: Mr. Peter Fu,P.E.—City of Fort Worth,Water Department
Mr. Rakesh Chaubey, P.E.—City of Fort Worth,Wet Weather Program
Amendment No. 1
Mains 207 and 207A
Drainage Area Sanitary Sewer System Rehabilitation and Improvements
(Group 3, Contract 4), Part 4
Sewer Project No. PS 46-070460410110
D.O.E. Project No. 2089
Design Services: Sewer Main Construction
Previous
Estimated Increased
DESCRIPTION Expense Expense Total Expense
Construction Estimate $632,690.00 $278,005.19 $910,695.19
Curve "A" 8.3% in original Contract (7.7% in for this $52,513.27 $17,610.26 $70,123.53
Addendum)
Less 15% for City Administration $44,635.00 $14,970.00 $59,605.00
Survey $15,910.00 $4,709.56 $20,619.56
Easements $0.00 $1,900.00 $1,900.00
Meetings $800.00 $2,000.00 $2,800.00
Geotechnical Engineer $0.00 $500.50 $500.50
Progress/ Design, Monthly Meetings $2,000.00 $0.00 $2,000.00
Deliver Documents, Bidding Assistance, Pre-Bid Conf. $1,000.00 $0.00 $1,000.00
Final Inspection $400.00 $0.00 $400.00
Final Report $800.00 $0.00 $800.00
Printings $2,600.00 $0.00 $2,600.00
TOTAL FEE $68,145.00 $24,080.06 $92,225.06