HomeMy WebLinkAboutContract 45922-CO1 FORT Wc)RTH City of Fort Worth CITYSECRRETAIRI �
Change Order Request COMCT Nth. _ - -
Project Name: Sanitary Sewer Rehabititation, Contract 86, Unit 2 City Sec No.: I 4$86J " Z TS
Project No.(s): P253 607170196483&P258-703170196483 I DOE No. 7253 CityProj.No.:l 01964
Project Description: Water and Sanitary Sewer Main Replacement on Ohio Garden Road,Haskell Street, Eastwood Avenue and Whitmore
Street
Contractor: P.C.Contractors, LLC Change Order# L� Date: 2/4/2015
City Project Mgr. Soon Wong City Inspector: John Crowley
Phone Number: 817-392-8369 Phone Number:J 817-944-0975
Dept. Water 91 SewerTotals Contract Time
(Calender days)
Original Contract Amount $274,667.90 $904,736.01 $1,179,403.91 150
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $274,667.90 $904,736.01 $1,179,403.91 150
Amount of Proposed Change Order $148,147.00 $148,147.00 045
Revised Contract Amount $422,814.90 $904,736.01 $1,327,550.91 195
Original Funds Available for Change Orders $13,800.10 $27,700.99 $41,501.09
Remaining Funds Available for this CO $13,800.10 $27,700.99 $41,501.09
Additional Funding(if necessary) $134,346.90 $134,346.90
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 12.56%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,474,254.89
JUSTIFICATION(REASONS)FOR CHANGE ORDER
hange order No. 1 will allow for the replacement of the old and deteriorated water main on the Whitmore
Street from Carroll Street to Wimberley Street, prior to pavement replacement by the Transportation and
Public Works Department.
Staff recommends the approval of 45 additional calendar days for this change order.
i v,
OFFICIAL RECORD bY� t� $ �
CITY SECRETARY
FT.WORTH, TX Xonld P. Gonzales, ity
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
a:
�&ny Name Contractor Name r Signature
P.C.Contractors,LLC Chase Pattterson
cit
M Date
UJ -
LU W _ ate, Q6RsUu.Qbo u rvisor TPW Det Da
> Z /g z D t5
W
U m Date Mana
LU 212S-IIS-
Council
2S /SCouncil Action If R aired -
M&C Number C-27172 M&C Date Approved 213711�
Fo p,-u Wo Rrr H City of Fort worth
Change Order Additions
Project Name Sanitary Sewer Rehabititation, Contract 86, Unit 2 City Sec No.: 46005
Project No.(s): P253 607170196483&P258-703170196483 DOE No. 7253 City Proj. No.. 01964
Project Water and Sanitary Sewer Main Replacement on Ohio Garden Road, Haskell Street, Eastwood Avenue and Whitmore
Description Street
Contractor P.C.Contractors, LLC Change Order:L= Date: 1 2/4/2015
City Project Mgr. Soon Wong City Inspector John Crowley
ADDITIONS
ITEM DESCRIPTIZ5N DEPT Qty Unit Unit Cost Total
1 8"PVC Water Pipe Water 1158.00 LF $26.31 $30,466.98
2 9"PVC Water Pipe Water 30.00 LF $24.21 $726.30
3 8'Gate Valve Water 2.00 EA $1,506.72 $3,013.44
4 6'Gate Valve Water 3.00 EA $1,018.16 $3,054.48
5 Ductile Iron Water Fittings Water 0.50 TN $6,188.84 $3,094.42
6 Salvage Fire hydrant Water 3.00 EA $623.23 $1,869.69
7 Fire Hydrent Water 3.00 EA $3,641.40 $10,924.20
8 1"Water Service, Meter Relocation Water 16.00 EA $47.82 $765.12
9 1"Water Service Water 30.00 EA $462.54 $13,876.20
10 Connection to Existing 4"-12"Water Main Water 2.00 EA $1,411.37 $2,822.74
11 Temporary Water Services Water 0.10 LS $12,654.60 $1,265.46
12 Remove and Replace 6"Conc Curb and Gutter Water 180.00 LF $14.41 $2,593.80
13 Asphalt Pvmt Repair, Residential Water 550.00 LF $36.49 $20,069.50
15 6"Concrete Driveway Water 575.02 SF $4.24 $2,438.08
17 Block Sod Placement Water 74.94 SY $4.37 $327.49
19 Imported Embedment/Backfill, CSS Water 9.00 CY $65.00 $585.00
20 8"Waterline Lowering Water 3.00 EA $4,250.00 $12,750.00
21 Temporay Asphalt Paving Repair Water 1875.00 LF $13.50 $25,312.50
22 1" Private Water Service Water 3.00 LF $956.00 $2,868.00
23 8" DI Water Water 10.00 EA $62.10 $621.00
24 1 V2"Water Service Meter Relocafion Water 1.00 EA $265.00 $265.00
25 1 1/2 Water Service Water 1.00 EA $1,185.00 $1,185.00
26 2"Water Service Meter Relocation Water 1.00 EA $340.00 $340.00
27 2"Water Service Water 1.00 EA $1,986.00 $1,986.00
18 Traffic Control Water 0.50 $9,853.20 $4,926.60
Water $148,147.00
Sewer
Page 2 of 4 lAdditions Sub Total 1 $148,147.00
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Sanitary Sewer Rehabilitation, Contract 86, Unit 2 City Sec No.: 46005
Project No.(s): P253-607170196483&P258-703170196483 DOE No, 1 7253 City Proj. No.: 01964
Project Description Water and Sanitary Sewer Main Replacement on Ohio Garden Road, Haskell Street, Eastwood Avenue and
Whitmore Street
Contractor P.C. Contractors, LLC Change Order: [i] Date 2/4/2015
City Project Mgr. Soon Wong City Inspector: F John Crowley
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Water
Sewer
Page 3 of 4 Deletions Sub Total
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 4 of 4
M&C Review Page I of 2
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FoR��I
COUNCIL ACTION: Approved on 2/3/2015 -Ordinance No. 21625-02-2015
DATE: 2/3/2015 REFERENCE NO.: **C-27172 LOG NAME: 60SS86U2CO1-
PCCONST
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Change Order No. 1 to City Secretary Contract No. 46005 with P.
C. Contractors, LLC, in the Amount of$148,147.00 for a Revised Total Contract in the
Amount of$1,327,550.91 for Sanitary Sewer Rehabilitation, Contract 86, Unit 2 on
Whitmore Street and Adopt Appropriation Ordinance (COUNCIL DISTRICT 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize a transfer in the amount of $148,147.00 from the Water and Sewer Operating
Fund to the Water Capital Projects Fund;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations
in the Water Capital Projects Fund in the amount of $148,147.00; and
3. Authorize the execution of Change Order No. 1 to City Secretary Contract No.46005 with P.
C. Contractors, LLC, in the amount of $148,147.00 for a revised total contract in the amount
of $1,327,550.91 for Sanitary Sewer Rehabilitation, Contract 86, Unit 2.
DISCUSSION:
On August 5, 2014, (M&C C-26910) the City Council authorized execution of a contract with P. C.
Contractors, LLC, in the amount of$1,179,403.91 for Sanitary Sewer Rehabilitation, Contract 86, Unit
2.
Change order No. 1 will allow for the replacement of the old and deteriorated water main on
Whitmore Street from Carroll Street to Wimberley Street, prior to pavement replacement by the
Transportation and Public Works Department. Sanitary sewer improvements may also include the
replacement of deteriorated water mains on the same street to provide project efficiencies, as is the
case with this project.
M/WBE Office - P.C. Contractors, LLC, is in compliance with the City's BDE Ordinance by committing
to an additional nine percent MBE participation on this Change Order No. 1. The City's goal on this
change order is eight percent.
The project is located in COUNCIL DISTRICT 9, Mapsco 62 K.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above
recommendations and adoption of the attached appropriation ordinance, funds will be available in the
current capital budget, as appropriated, of the Water Capital Projects Fund, The Fiscal Year 2015
operating budget includes appropriations of$51,724,257.00 for the purpose of providing pay-as-you-
go funding for capital projects. The amount transferred year to date is $24,142,191.00 in the
operating budget.
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=20677&councildate=2/3/2015 2/4/2015
M&C Review Page 2 of 2
TO Fund/Account/Centers FROM Fund/Account/Centers
2) P253 541200 607170196483 $148,147.00 1) PE45 538040 0609020 $148.147.00
1&21 $148,1 47.00 3) P253 541200 607170196483 $148,147.00
P253 476045 6071701964ZZ
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Andy Cronberg (5020)
Additional Information Contact: Soon Wong (8369)
ATTACHMENTS
60SS86U2C01 PCCONST Map.pdf
60SS86U2C01-PCCONST P253 A015.docx
http://apps.cf\vnet.org/council_packet/mc_review.asp?ID=20677&councildate=2/3/2015 2/4/2015