HomeMy WebLinkAboutContract 44812-A1 CITY SECRETA q4vl'�-
AMENDMENT No.1 CWRACT RO
TO CITY SECRETARY CONTRACT
WHEREAS, the City of Fort Worth (CITY) and CH2M HILL
Engineers, Inc. , (ENGINEER) made and entered into City Secretary
Contract No. 44812 , (the CONTRACT) which was authorized by M&C
C-26412 on the 20th day of August, 2013 in the amount of
$303,870.00; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
Water Main and Sanitary Sewer Relocation on East Rosedale
Street from Miller Avenue to IH 820
WHEREAS, it has become necessary to execute Amendment No.
1 to the CONTRACT to include an increased scope of work and
revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated February 19,
2015, a copy of which is attached hereto and incorporated
herein. The cost to City for the additional design services to
be performed by Engineer totals $13, 907 .00 .
2 .
M
M
_m Article II of the CONTRACT is amended to provide for an increase
m
in the fee to be paid to Engineer for all work and services
C3 performed under the Contract, as amended, so that the total fee
paid by the City for all work and services shall be an amount of
o $318,777 . 00.
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
OFFICIAL RECORD
Page -1- CITY SECRETARY
FT.WORTH,TX
EXECUTED and EFFECTIVE as of the date last written by a
signatory, below.
APPROVED: ENGINEER
City of Fort Worth CH2M HILL Engineers, Inc.
r� Sj,.-(,c- pt Fernando Costa Ken C. Hall, P.E.
Assistant City Manager Vice President
DATE: DATE:
APPROVAL RECOMMENDED:
Andrew T Cronberg re E.
Interim Director, er Department
APPROVED AS TO FORM AND LEGALITY: M&C: N/A
Date: N/A
Douglas W. Black
Assistant City Attorney
ATT ST: ®RT �j
°° ®0
°
8 0°
Mary J. yse
City Sec etary �°°�°�°�°A°��
'TW
00FICIAL RECORD
CITY SECRETARY
14 WORTH,TX
Page -2-
0 CH2MHILL
February 19,2015
John Kasavich
Project Manager
City of Fort Worth
1000 Throckmorton Ave
Fort Worth,TX 76102
Subject: AMENDMENT No.1-Water And Sewer Replacements East Rosedale From Miller
To IH-820
Dear Mr. Kasavich,
Attached is CH2M HILL Engineers,Inc.'s (CH2M HILL) Amendment proposal for the Services
During Construction support,Attachment A& B,for the Water And Sewer Replacements East
Rosedale From Miller To IH-820 as we have recently discussed. In accordance with our
discussions, the services compliment Task 6 of the existing contract and adds subtasks
currently not included.
Our fee for the proposed Scope of Services,is as shown below and as we discussed in the
amount of$13,907 The water portion of this total will be$9,390 and the sewer portion of this
total will be$4,517. The terms and conditions of the contract do not change.
Contract/Amendment Amount
Original contract $303,870
Amendment No. 1 $ 13,907
TOTAL $318,777
We look forward to starting work upon notice to proceed. If you have any additional
comments or concerns, please contact J. Felipe Pulido at 817.988.0172.
Sincerely,
CH2M HILL Engineers, Inc.
J. Felipe Pulido,P.E. Edward Motley,P.E.
Project Manager Vice President
Enclosures:
Attachment A-Proposed Scope of Work
Attachment B-Compensation,Level of Effort and Fees
Attachment D-Construction Schedule
EXHIBIT B-2
Level of Effort Spreadsheet
TASKMOUR BREAKDOWN
Design Services for
Water and Sanitary Sewer Replacement Contract
City Project No.01894 DOE No.01895
Labor hours I Ex ense
Task No. Task DescriptionProject OA10C Proiec[ Talal Labor Total Expense
Principal Mana a n in En Ineer ER CADD Administrative Cosl SS.—n-Ran[ Travel Reproduction Cost Task Sub Taal
Rate 5261 S13d E $195 $116 $91VO .
$ MME Non-MME
6.0 Constructton Phase Services 0 20 0 84 0 $12,407 $600 S 1,000 $ 1,500 $ 13,907
6.1 CansWcOon Su ort
6.1.3 Field Observations 8 36 $5.241
6.1 6 Pay Application Processing 12 48 $7,166
Tatals 0 20 0 84 0 512,407 O S S 500.00 S 1,000 $ 1,500 $ 13,907
Wale, $ 9,390
Sewer $ 4,517
City of Fort W,M,Texas
Attachment B-level of EffoM1 Supplement
Typical Water and Sewer Replacement
FN^NTR Official Release Data 02.19.2015 AMENDMENT No.1