HomeMy WebLinkAboutContract 45837-CO1 Y5 914'1 -Cb l
FORT WcowrH City of Fort Worth City Secretary opy
Change Order Request
Project Name:1 Sanitary Sewer Rehabititation,Contract 83 City Sec No.: 1 45837
Project No.(s): P258-703170150283 DOE No. 6614 Ci1yProj.No.:J 01502
Project Description: Sanitary Sewer Replacement on Aberdeen Drive,Roanoke Street,Penrose Avenue,Wilis Avenue,Ewing Street and
Davenport Avenue
Contractor. PM Contraction and Rehab,LLC Change Order# L Date: 3/19/2015
CityPmjectMgr.1 RakeshCha City Inspector. I Richard Salazar
Phone Number. 817-392-6051 Phone Number. 817-223-2261
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $1,445,511.90 $1,445,511.90 270
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,445,511.90 $1,445,511.90 270
Amount of Proposed Change Order 15-00 15,00 020
Revised Contract Amount $1,445,526.90 $1,445,526.90 290
Original Funds Available for Change Orders $43,500.10 $43,500.10
Remaining Funds Available for this CO $43,500.101 $43,500.10
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,806,889.88
JUSTIFICAT l N(kWO FOR MWE ORM
Change order No. 1 will provide for the following:
• The replacement of existing sewer pipe by pipe enlargement method in lieu of open cut installation,
due to limited space for trenching operations.
• The rehabilitation of sewer pipe by pipe enlargement method for additional footage of deteriorated
laterals that were encountered during construction.
• The rehabilitation of additional footage of sewer pipe by cured-in-place pipe method in lieu of open
cut installation, due to access limitations.
• The deletion of pay item quantities that are n n er needed on the project.
rM Staff concurS with the c ctor's reques il ndar days for the change order.
a
M
rrn
C1
A-p °
X7 �oO000aoo00
+� It is understood and agreed that the acceptance of this Change Orderctor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. _
s Company Name-
PM Contruction and Rehab, LLC Bac On
YI
ow
20 /7
�.
T5330 � erg
v
Cowtpl AOag I(Reqwpa
M&C Number N/A M&C Date Approved WA ']
F R�' VVoxT'H City of Fort Worth
Change Order Additions
Project Name Sanitary Sewer Rehabilitation,Contract 83 City Sec No.: 1 45837
Project No.(s): P258-703170150283 DOE No. 6614 City Proj.No.: 1 01502
Project Sanitary Sewer Replacement on Aberdeen Drive,Roanoke Street,Penrose Avenue,Wilis Avenue,Ewing Street and
Description Davenport Avenue
Contractor PM Contivction and Rehab,LLC Change Order:= Date: 3/19/2015
City Project Mgr. Rakesh Chaubey City Inspector Richard Salazar
ADDITIONS
QtY W*
1 8"Pipe Enlargement Sewer 1300.00 LF $46.00 $59,800.00
4 8"DIP Sewer Pipe-Bore Sewer 8.00 LF $90.00 $720.00
6 6"Cup Sewer 47.00 LF $125.00 $5,875.00
7 Pre CCN Inspection Sewer 600.00 LF $3.15 $1,890.00
8 Post CCTV Inspection Sewer 600.00 LF $1,75 $1,050.00
Water
Sewer $69,335.00
Page 2 of 4 Additions Sub Total $69,335.00
FORT wb]axH City of Fort Worth
Change Order Deletions
Project Name Sanitary Sewer Rehabilitation,Contract 83 City Sec No.: 45837
Project No.(s): P258-703170150283 DOE No. EiE City Proj.No.: 01502
Project Description Sanitary Sewer Replacement on Aberdeen Drive,Roanoke Street,Penrose Avenue,Wilis Avenue,Ewing Street
and Davenport Avenue
Contractor PM Contruction and Rehab,LLC Change Order: = Date 3/19/2015
City Project Mgr. Rakesh Chaubey City Inspector: Richard Salazar
DELETIONS
ITEM tMV'Tttlll+t DEPT Unft Unk Cost Tow
2 8"Sewer Pipe Sewer 330.00 LF $85.00 $28,050.00
12 4"Manhole Sewer 2.00 EA $4,850.00 $9,700.00
13 4"Drop Manhole Sewer 1.00 EA $5,000.00 $5,000.00
14 4"Extre Depth Manhole Sewer 21.50 VF $200.00 $4,300.00
19 6"Bored Sewer Service Sewer 2.00 EA $815.00 $1,630.00
20 6"2-Way Clean Out Sewer 2.00 EA $350.00 $700.00
23 4"Private Sewer Service Sewer 150.00 LF $23.00 $3,450.00
24 6"Private Sewer Service Sewer 50.00 LF $30.00 $1,500.00
29 6"-12"Tree Removal Sewer 6.00 EA $165.00 $990.00
30 12"-18"Tree Removal Sewer 4.00 EA $350.00 $1,400.00
31 18"-24"Tree Removal Sewer 2.00 EA $1,500.00 $3,000.00
38 6"Chain Link Sewer 400.00 LF $12.00 $4,800.00
39 6"Wood Fence Sewer 400.00 LF $12.00 $4,800.00
Water
Sewer $69,320.00
Page 3 of 4 Deletions Sub Total $69,320.00
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
Page 4 of 4