HomeMy WebLinkAboutContract 45922-CO2 Pria- ' WORTH City of Fort worth City Secretary Copy
Change Order Request
Project Name:1 Sanitary Sewer Rehabilitation,Contract 86,Unit 2 City Sec No.: 1 45922
Project No.(s): P253.607170196483&P258-703170196483 DOE No. 7253 CityProj.No.:1 01964
Project Description: Water and Sanitary Sewer Main Replacement on Ohio Garden Road,Haskell Street,Eastwood Avenue and Whitmore
Street
Contractor. P.C.Contractors,LLC Change Order# 0 Date: 3/5/2015
City Project Mgr. Soon Wong City Inspector. I John Crowley
Phone Number. 817-392-8369 Phone Number. 817-944-0975
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $274,667.90 $904,736.01 $1,179,403.91 150
Extras to Date $148,147.00 $148,147.00 045
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $422,814.90 $904,736.01 $1,327,550.91 195
Amount of Proposed Change Order 1.50 $1.50
Revised Contract Amount $422,816.40 $904,736.01 $1,327,552.41 195
Original Funds Available for Change Orders $13,800.10 $27,700.99 $41,501.09
Remaining Funds Available for this CO $27,700.99 $27,700.99
Additional Funding(f necessary) $1.50 $1.50
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 12.56%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,474,254.89
-
hange order No. 2 will provide the correct unit prices for pay item No's 6 and 10 which were inadvertently
isted on the change order No. 1, different than listed in the executed contract documents
ORr
O A
�+ t �
o �
aer, Ci Secretary �o00000�°°
o TAX A5
W
7W
W
LJ
W
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
P.C.Contractors, LLC Chase Pattterson —I —
j. r
_Zp .�
M&C Number WA M&C Date Approved
o T WORT City of Fort Worth
I�r Change Order Additions
Project Name I Sanitary Sewer Rehabititation,Contract 86,Unit 2 City Sec No.: 45922
Project No.(s): P253-607170196483&P258-703170196483 DOE No. 7253 City Proj.No.: 01964
Project Water and Sanitary Sewer Main Replacement on Ohio Garden Road,Haskell Street,Eastwood Avenue and Whitmore
Description Street
Contractor P.C.Contractors,LLC Change Order= Date: 3I5I2015
City Project Mgr. Soon Wong City Inspector John Crowle
ADDITIONS
6A Salvagte Fire Hydrant Water 3.00 EA $623.33 $1,869.99
10A Connection to Existing 4"-12"Water Main Water 2.00 EA $1,411.97 $2,823.94
ly
Water $4,693.93
Sewer
Page 2 of 4 Additions Sub Total $4,693.93
City of Fort Worth
��"!• Change Order Deletions
Project Name Sanitary Sewer Rehabilitation,Contract 86,Unit 2 City Sec No.: 45922
Project No.(s): P253-607170196483&P258-703170196483 DOE No. 7253 City Proj.No.: 01964
Project Description Water and Sanitary Sewer Main Replacement on Ohio Garden Road,Haskell Street,Eastwood Avenue and
Whitmore Street
Contractor P.C.Contractors,LLC Change Order: [� Date 3/5/2015
City Project Mgr. Soon Wong City Inspector: John Crowley
DELETIONS
ITEM DESCMPTON DEPT Q1Y Unk UftCoSt TOW
6 Savage Fire hydrant Water 3.00 EA $623.23 $1,869.69
10 Connection to Existing 4'-12'Water Main Water 2.00 EA $1,411.37 $2,822.74
® V% So,a ONO9
Water $4,692.43
Sewer
Page 3 of 4 Deletions Sub Total $4,692.43
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
Page 4 of 4