Change Order Request
Project Name:1 Water and Sanitary Sewer Main Relocations for SH121T, Part 25. City Sec No.: 45893
Project No.(s): P275-706170089987 and C221-303210000580 I DOE No. 7183 City Proj.No.: 00899
Project Description: Water and Sanitary Sewer Main Relocations for SH121, Part 25 from Dirks Road to FM 1187
Contractor: Jackson Construction,Ltd. Change Order# Date: 1 4/15/2015
City Project Mgr.1 Liam Conlon City Inspector: Luisa Allbright
Phone Number:1 817-392-6824 Phone Number: 817-223-2259
Dept. Water Sewer Screen Wall Totals Contract Time
(Calender days)
Original Contract Amount $1,545,302.50 $367,013.00 $1,912,315.50 180
Extras to Date
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,545,302.50 $367,013.00 $1,912,315.50 180
Amount of Proposed Change Order $62,615.00 $62,615.00 075
Revised Contract Amount $1,607,917.50 $367,013.00 $1,974,930.50 255
Original Funds Available for Change Orders $47,000.00 $18,400.00 $65,400.00
Remaining Funds Available for this CO $47,000.00 $18,400.00 $65,400.00
Additional Funding(if necessary) $15,615.00 $15,615.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.27%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,390,394.38
he change order will provide for the following:
• Repair of sun damage Hobas pipe (stored in the open from previous project) by th u ur in
Houston including delivery and return.
0000°°°
• The lowering of the proposed 8-inch sewer main to accommodate the existing sewer � al�
were encountered at a deeper elevation than anticipated during construction. ,
V
• Additional depth of 4-ft diameter manholes to accommodate the deeper 8-inch sewer main. u
• Lowering of 4-inch sewer mains.
C-) Staff concurs with the contractor's request for 75 additional calendar days on the change order.
M
C7
0
3 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
n< in full(both time and money)for all costs arising out of,or incidental to,the above Change Or .
Contractor's Name Contractor Name _
'N Jackson Construction, Ltd. Steve Harberstoh
1.J
0
WOda. Amftu-
AQQW
61 iS
M&C Number NtA FT. WORTH, YJC Cate Approved irA
r
FORT W0a-FH City of Fort Worth
1W 000- Change Order Additions
Project Name SH121T Part 25 Relocations City Sec No.: 45893
Project No.(s): P265-606170089987-P275-706170089987 DOE No. 7183 City Proj.No.: 899
Project SH 121 Southwest Parkway Water and Sewer Main Relocations part 25 from Dirks Road to FM 1187
Description
Contractor Jackson Construction Change Order:= Date: 4/15/2015
City Project Mgr. Liam Conlon City Inspector Luisa Allbri ht
ADDITIONS
UEM
omfuPTION f?EPT ft IM Unit Cast
13 Additional cost to lower 8"Sanitary Sewer Line lower flowline 4' Sewer 808.00 LF $16.00 $12,928.00
15 Additional cost lower main 4" Services INSTALL ONLY MATERIAL Sewer 14.00 EA $418.00 $5,852.00
56 Additional Cost lower main 4"Sewer services Sewer 1.00 EA $432.00 $432.00
57 4'Manhole Sewer 1.00 EA $3,200.00 $3,200.00
58 4'Extra Depth Manhole Sewer 21.60 VF $300.00 $6,480.00
59 Connect to City provided Manhole at different flow line Sewer 2.00 EA $1,850.00 $3,700.00
60 Hobas pipe delivery to Houston and repair Sewer 1.00 LS $34,523.00 $34,523.00
OFFICIAL RECORD water
Sewer $67,115.00
CITY SECRETARY Screen Wall
�� �•� Additions Sub Total $67,115.00
w
FORT ZORTH City of Fort worth
Change Order Deletions
Project Name Water and Sanitary Sewer Main Relocations for SH121T,Part 25. City Sec No.: 1 45893
Project No.(s): P275-706170089987 and C221-303210000580 DOE No. 7183 City Proj. No.: 00899
Project Description Water and Sanitary Sewer Main Relocations for SH 121, Part 25 from Dirks Road to FM 1187
Contractor Jackson Construction,Ltd. Change Order: D] Date 4/15/2015
City Project Mgr. Liam Conlon City Inspector: Luisa Allbright
DELETIONS
ITEM SCIPWR DEPT Qty Unit Unit Cost
14 4'Drop Manhole Sewer 1.00 EA $4,500.00 r$4,500.00
OFFICIAL RECORD Water
CITY SECRETARY Sewer $4,500.00
y�
Screen Wall
FTS RPMO TX Deletions Sub Total $4,500.00
MMBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
N
RECORDRETARYTH, TX