TRANSPORTATION AND PUBLIC WORKS
NOTICE OF PROJECT COMPLETION
D.O.E. Ns: 6565
WSM-A
Regarding contract 44406 for WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2009-w^as
required by the WATER DEPARTMENT as approved by City Council on 03/05/2013 through M&C C-26142 the
director of the WATER DEPARTMENT upon the recommendation of the Assistant Director of the Transportation&
Public Works Department has accepted the project as complete.
Original Contract Prices: �� 1EE 1 $1,638,475.30
Amount of Approved Change Orders: AP ���� �� $68,033.65 Ns 1,2
i
Revised Contract Amount: 1� $1,706,508.95
Total Cost Work Completed: $1,666,415.70
Less Deductions:
Liquidated Damages: Days @$210.00/Day
Pavement Deficiencies:
Total Deduction Amount: $0.00
Total Cost Work Completed: $1,666,415.70
Less Previous Payments: $1,644,156.96
Final Payment Due $22,258.74
Recommended for Acceptance Date
Asst. Director, TPW - Infrastructure Design and Construction
Accepted Date
erector, WATER DEPARTMENT
City Manager Date
m Comments: FUND P253-608170144483 /P258-708170144483
M
M
M OFFICIAL RECORD
0
M CITY SECRETARY
FT.WORTH, TX
{{
APR 3 0 2015 / C S 14�4 44 No
City Project Numbers 01444 !?: DOE Number 6565
Contract Name WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2009 Estimate Number 23
Contract Limits Payment Number 23
Project Type WATER&SEWER For Period Ending 228/2015
Project Funding
Project Manager Ch-bey City Secretary Contract Number 44406
Inspectors RODGERS / SAI AZAR Contract Date 3/5/2013
Contractor JACKSON CONSTRUCTION LTD Contract Time 200 CD
5112 SUN VALLEY DRIVE Days Charged to Date 299 CD
FORT WORTH, TX 76119 Contract is 000000 Complete
CITY OF FORT WORTH i\�}y!O i�
- >>
SUMMARY OF CHARGES - "
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $1,666,415.70
_ Less %Retained $0.00
Ep,DEr<.RI'Y!EAiT Net Earned $1,666,415.70
E IGINEERiNG k ND FISCAL SER` !CES
��rcr n o_ 8429Earned This Period $22,258.74
Coria B�* ena i_os- ;t:..
De pF o-_l Si naLu—for' Retainage This Period $0.00
Less Liquidated Damages
DEPARTMENT CHECK PICK-l YES ❑ 0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $1,644,156.96
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $22,258.74
Friday,Much 06,2015 Page 6 of 6
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name WATER AND SAMTARY SEWER REPLACEMENT CONTRACT 2009 WS M—A
Contract Limits
Project Type WATER&SEWER
City Project Numbers 01444
DOE Number 6565
Estimate Number 23 Payment Number 23 For Period Ending 2/28/2015
CD
City Secretary Contract Number 44406 Contract Time 20CD 79 9 C D4ee
WJE
Contract Date 3/5/2013 Days Charged to Date 299
Project Manager Chaubey Contract is 98.000 Complete
Contractor JACKSON CONSTRUCTION LTD
5112 SUN VALLEY DRIVE
FORT WORTH, TX 76119
Inspectors RODGERS / SALAZAR
Friday,March 06,2015 Page 1 of 6
City Project Numbers 01444 DOE Number 6565
Contract Name WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2009 Estimate Number 23
Contract Limits Payment Number 23
Project Type WATER&SEWER For Period Ending 2/28/2015
Project Funding
WATER IMPROVEMENTS
ItemEstimated Estimated Completed Completed
Description of Items Unit Unit Cost
No. Quanity Total Quanity Total
1 24"PVC C905 WATER PIPE(CO#2) 2013 LF $108.00 $217,404.00 2013 $217,404.00
2 12"WATER PIPE(CO 92) 1115 LF $46.00 $51,290.00 1115 $51,290.00
3 8"WATER PIPE(CO#2) 8634.4 LF $27.00 6233,128.80 8634.4 $233,128.80
4 6"PVC WATER PIPE(CO#2) 85 LF $27-00 $2,295.00 85 $2,295.00
5 24"GATE VALVE W/VAULT 3 EA $28,000.00 $84,000.00 2 $56,000.00
6 12"GATE VALVE 5 EA $2,000.00 $10,000.00 5 $10,000.00
7 8"GATE VALVE(CO#2) 18 EA $1,100-00 $19,800.00 18 $19,800.00
8 6"GATE VALVE 13 EA $775.00 $10,075.00 13 $10,075.00
9 SALVAGE 3/4"WATER METER 264 EA $15.00 $3,960.00 244 $3,660.00
10 SALVAGE FIRE HYDRANT(CO#2) 11 EA $500.00 $5,500.00 11 $5,500.00
11 REMOVE 6"WATER VALVE 13 EA $50.00 $650.00 13 $650.00
12 SALVAGE 24"WATER VALVE 3 EA $175.00 $525.00 2 $350.00
13 4'WIDE ASPHALT PVMT REPAIR,RESD(CO#2) 11872.68 LF $30-00 6356,180.40 11872.68 $356,180-40
14 TEMPORARY ASPHALT PAVING REPAIR 6505 LF $11.50 $74,807.50 6505 $74,807.50
(RYAN AVE)(CO#2)
15 6"CONC PVMT REPAIR(CO 42) 386 SY $87.00 $33,582.00 386 $33,582.00
16 4"CONC SIDEWALK(CO#2) 866.64 SF $8.00 $6,933.12 866.64 $6,933.12
17 4'BARRIER FREE RAMP,TYPE A(CO#2) 6 EA $900.00 $5,400.00 6 $5,400.00
18 7"CONC CURB AND GUTTER1815(CO 42) 635 LF $33.00 $20,955.00 635 $20,955.00
19 7"CONC VALLEY GUTTER(CO 42) 32 SY $89.00 $2,848.00 32 $2,848.00
I
20 TEMPORARY WATER SERVICES I LS $80,000.00 $80,000.00 1 $80,000.00
21 TRENCH SAFETY(CO#2) 3128 LF $0.10 $312.80 3128 $312.80
22 CONCRETE COLLAR(CO#2) 6 EA $415.00 $2,490.00 6 $2,490.00
23 DUCTILE IRON WATER FITTING W/ 4.04 TN $8,800.00 $35,552.00 4.04 $35,552.00
RESTRAINT(CO#2)
24 I"WATER SERVICE(CO#2) 255 EA $530.00 3135,150.00 255 $135,150.00
25 1 1/2"WATER SERVICE 10 EA $13435.00 $14,350.00 10 $14,350.00
26 2"WATER SERVICE(CO#2) 4 EA $1,990.00 $7,960.00 4 $7,960-00
27 1"WATER SERVICE METER RELOCATION(CO 255 EA $230.00 $58,650.00 255 $58,650.00
#2)
28 1 1/2"WATER SERVICE METER RELOCATION 10 EA $275.00 $2,750.00 10 $2,750.00
29 2"WATER SERVICE METER RELOCATION(CO 3 EA $300-00 $900.00 3 $900.00
#2)
Friday,March 06,2015 Page 2 of 6
II
City Project Numbers 01444 DOE Number 6565
Contract Name WATER AND SANI'T'ARY SEWER REPLACEMENT CONTRACP 2009 Estimate Number 23
Contract Limits Payment Number 23
Project Type WATER&SEWER For Period Ending 228/2015
Project Funding
30 CONNECTION TO EXISTING 24"WATER MAIN 2 EA $8,000.00 $16,000.00 2 $16,000.00
31 CONNECTION TO EXISTING 12"WATER MAIN 4 EA $1,000.00 $4,000.00 4 $4,000.00
32 CONNECTION TO EXISTING 8"WATER MAIN 10 EA $1,000.00 $10,000.00 10 $10,000.00
(CO#2)
33 CONNECTION TO EXISTING 6"WATER MAIN 10 EA $1,000.00 $10,000.00 10 $10,000.00
36 FIRE HYDRANT(CO#2) 11 EA $2,400.00 $26,400.00 11 $26,400.00
37 2"WATER AIR RELEASE VALVE VAULT 1 EA $12,000.00 $12,000.00 1 $12,000.00
38 TRAFFIC CONTROL 6 MO $1,250.00 $7,500.00 6 $7,500.00
39 SWPPP>1 ACRE 1 LS $3,200.00 $3,200.00 1 $3,200.00
40 WATER LINE GROUTING(FLOWABLE FILL) 72 CY $140.00 $10,080.00 72 $10,080.00
(CO#2)
41 9"CONCRETE PAVEMENT REPAIR HIGH 226 SY $114.00 $25,764.00 226 $25,764.00
EARLY STRENGTH(CO#1)
42 ADDITIONAL SIGNAGE&BARRICADES FOR 1 LS $13,014.83 $13,014.83 1 $13,014.83
BERRY/RYAN INTERSECTION(CO#1)
Sub-Total of Previous Unit $1,615,407.45 $1,586,932.45
SEWER IMPROVEMENTS
Item Estimated Estimated Completed Completed
Description of Items Unit Unit Cost
No. Quanity Total Quanity Total
1 8"DIP SEWR PIPE 52 LF $200.00 $10,400.00 52 $10,400.00
2 8"SEWER PIPE 645 LF $34.00 $21,930.00 645 $21,930.00
3 REMOVE 4'SEWER MANHOLE 4 EA $400.00 $1,600.00 4 $1,600.00
I
i
4 T WIDE ASPHALT PVMT REPAIR, 760 LF $39.00 $29,640.00 353.25 $13.776.75 j
RESIDENTIAL
5 TEMPORARY ASPHALT PAVING REPAIR 52 LF $14.00 $728.00 39I $5,474.00
6 TRENCH SAFETY 744 LF $1.00 $744.00 697 $697.00
7 PRE-CCTV INSPECTION 697 LF $2.00 $1,394.00
8 POST-CCTV INSPECTION 697 LF $1.50 $1,045.50 697 $1,045.50
9 CLAY DAMS 1 EA $150.00 $150.00 1 $150.00
10 4"SEWER SERVICE,2-WAY CLEANOUT 2 EA $780.00 $1,560.00 2 $1,560.00
11 T MANHOLE 6 EA $2,500.00 $15,000.00 6 $15,000.00
12 MANHOLE VACUUM TESTING 6 EA $150.00 $900.00 4 $600.00
13 CONCRETE COLLAR 4 EA $415.00 $1,660.00
14 T EXTRA DEPTH MANHOLE 7 VF $300.00 $2,100.00
15 BLOCK SOD PLACEMENT 125 SY $8.00 $1,000.00 750 $6,000.00
Friday,March 06,2015 Page 3 of 6
City Project Numbers 01444 DOE Number 6565
Contract Name WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2009 Estimate Number 23
Contract Limits Payment Number 23
Project Type WATER&SEWER For Period Ending 2/28/2015
Project Funding
16 TRAFFIC CONTROL I MO $1,250.00 $1,250.00 1 $1,250.00
17 MANHOLE VACUUM TESTING 6 EA t
Sub-Total of Previous Unit $9I,101.50 $79,483.25
——--- ---------———
i
I
I
i
it
I,
i
ii
i
I
I
I
i
i
Friday,March 06,2015 Page 4 of 6
City Project Numbers 01444 DOE Number 6565
Contract Name WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2009 Estimate Number 23
Contract Limits Payment Number 23
Project Type WATER&SEWER For Period Ending 2/28/2015
Project Funding
Contract Information Summary
Original Contract Amount $1,638,475.30
Change Orders
Change Order Number 1 $36,428.83
Change Order Number 2 $31,604.82
Total Contract Price $1,706,508.95
j� !- l
` +G t li- � �Date Total Cost of Work Completed $1,666,415.70
C Inactor Less %Retained $0.00
lao L Net Earned $1,666,415.70
Date J Earned This Period $22,258.74
Inspection Supervisor
Retainage This Period $0.00
Date 2� Less Liquidated Damages
Pr 'ect M r
1 Days @ /Day $0.00
Date LessPavement Deficiency $0.00
Asst.Director/TPW-Infrastruc a Design and Construction Less Penalty $0.00
Date C" Less Previous Payment $1.644,156.96
/45jo-Director/Contracting Depa e t Plus Material on Hand Less 15% $0.00
Balance Due This Payment $22,258.74
Friday,March 06,2015 Page 5 of 6
FORT woRTH City of Fort Worth CITY Si:C OAW 444,00 2-
. Change Order Request COMMCT NO.
Project Name Water&Sanitary Saw Replacement Contract 2009,WSM-A City Sec No. 44406
Project No.(s)P253-6061701444831 P2%708170144483 DOE No. 6565 City Pro.No. 01444
Water and Sanitary Sewer Main Replacemant on 5th Avenue,6th Avenue,Ryan Avenue,Ryan Place Drive,Stadium Drive,
mon Avondale Avenue,Lowden Street and Frazer Avenue
Convactorl Jackson Construction,Ltd. Change Order# 0 Date: 11113015
City Project Mgr. Rakesh Chaubey City Inspector I Richard Salazar
Phone Number; 817-392-6051 Phone Number: 817-223-2261
Dept. Water Sewer Totals Contrail Time
(Calendar Days)
Original Contract Amount $1,547,373.80 $91,101.50 $1,638,475.30 200
Extras to Date $36,428.83 $36,428.83 15
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $1,583,802.63 $91,101.50 $1,674,904.13 215
Amount of Proposed Change Order 5,354.82 4$3 750.00 31,604.82 084
Revised Contract Amount $1,619,157.45 $87,351.50 $1,706,508.95 299
Original Funds Available for Change Orders $46,421.00 $4,555.00 $50,976.00
Remaining Funds Available for this CO $9,992.17 $4,555.00 $14,547.17
Additional Funding(if necessary) $25,362.65 $25,362.65
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 4.16%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,048,094.13
The change order will provide for the following:
• Increased pay item quantities of temporary asphalt,permanent asphalt and concrete pavement
repair that are necessary on the project.
• Additional 8-inch gate valves that are necessary on the project.
M 0 The deletion of pay item quantities that are no longer needed on the project.
C-)
m_
c Staff concurs with the contractor's request for 84 additional calendar days on the project for the
0 order. e 0 R�
$:r
d t'
00UU�'QO
Mgry J. ser, City S20076rx
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and repres
in full(both time and money)for all costs arising out of,or incidental to,the above Change Ord*
J J-
Jackson Construction,Ltd. Steve Haberstroh
Iiia_
z4 �S
M&C Number Id1A M&C Date Approved NIA
FORT WORTH' City of Fort Worth
—�%"'"V'+' - Change Order Additions
Project Name lWater 8Sewer Reiplaoernent Contract 2009,WSM-A City Sec No.
Project No.(s) P253.MI70144483!P258-708170144483 DOE No.= City Pro.No. 01444
Project Water and Sanitary Sewer Main Replacement on 5th Avenue,6th Avenue,Ryan Avenue,Ryan Place Drive,Stadium Drive,
Description Avondale Avenue,Lowden Street and Frazier Avenue
Contractor I Jadworn Construction,Ltd. Change Order# = Date: 1h312015
City Project Mgr. I Rakesh City Inspector I Richard Salazar
ADDITIONS
ITEM LIMCMM DEPT MYunit Unit G TOW
3 84nch Water Pipe Water 33.40 LF $27.00 $901.80
7 8'Gate Valve Water 10.00 EA $1,100.00 $11,000.00
13 4'Wide Asphalt PVMT Repair Residential Water ;1487.68 LF $30.00 $44,630.40
14 Temporary Asphalt Paving Repair Water 1750.00 LF $11.50 $20,125.00
15 6'Conc PVMT Repair Water 1206.00 SY $87.00 $17,922.00
16 4"Conc Sidewalk Water 846.64 SF $8.00 $6,773.12
17 4"Barrier Free Ramp,Type A Water 4.00 EA $900.00 $3,600.00
19 7"Conc Valley Gutter Water 7.00 Lf $89.00 $623.00
24 1'Water Service Water 1.00 EA $530.00 $530.00
27 1'Water Service Relocation Water 1.00 EA $230.00 $230.00
32 Connection to EAsting 8"Water Main Water 1.00 EA $1,000.00 $1,000.00
i
Water $107,335.32
Sewer
Page 2 of 4 lAddiflons Sub Total 1 $107,335.32 i
Fk> r Wild wr tII City of Fort Worth
-'—`"404�� Change Order Deletions
Project Name lWater 8 Sanitary Sewer Replacement Contract 2009,WSM-A City Sec No.
Project No.(s) P253.608170144483/P258-708170144483 DOE No. 6565 City Pro.No.Project 01444
Description Water and Sanitary Sewer Main Replacement on 5th Avenue,6th Avenue,Ryan Avenue,Ryan Place Drive,Stadium
Drive,Avondale Avenue,Lowden Street and Fraser Avenue
Contractor Jacitson Constriction,Ltd. Change Order#0.2 Date 1113!2015
City Project Mgr. Rakesh Chaubey City Inspector iGa Salazar
DELETIONS
ITEM DESCRIPnON DEPT Qty Unit Unit Cost r
1 24"PVC C95 Water Pipe Water 5.00 LF $108.00 $540.00
2 17 Water Pipe Water 20.00 LF $4600 $920.004 6"PVC Water Pipe Water .45.00 LF $27.00 $1,215.00
10 Salvage Fire Hydrant Water 1.00 EA $500.00 $500.00
18 T Conc Curb 8 Gutter Water -1180.0011-F $33.00 $38,940.00
21 Trench Safety Water 25.00 LF $0.10 $2.50
22 Concrete Collar Water 7.00 EA $415.00 $2,905.00
23 Ductile Iron Water Fitting with Restraint Water '0.21 TN $8,800.00 $1,848.00
26 T Water Service Water ,-1.00 EA $1,990.00 $1,990.00
29 2'Water Service Metier Reloction Water -2.00 EA $300.00 $600.0
34 2"x8°Tapping Sleeve 8 Valve Water 1.00 EA $3,300.00 $3,300.00
36 Fire Hydrant Water /2.00 EA $2,400.00 $4,800.00
40 Water Une Grouting(Flowable Fill) Water !103.00 CY $140.00 $14,420.00
43 Extra Width Asphalt Pavement Repair Sewer 30.00 TN $125.00 $3,750.00
Water $71,980.50
Sewer $3,750.00
Page 3 of 4 IDelefions Sub Total $75,730.50
MfWBE Breakdown for this Change Order
Total
Previous Change Orders
I III WRIN.,MR
M,
Total I I-mm mm",MW
I-.ONSENT OF SURETY OWNER
TO FINAL PAYMENT ��TRCT
cONnT ACTOR
D?Gt7t2ertt G707SURETY1
Bond No. BCD1009407 CFTHF.R
TO OWNFa- ARCI 1 FCT'S PRO,TECI' NO_:
;Warne urrd ad&nm,1
City of Fort Worth, Texas
CONTRACT FOR_ Water& Sewer Replacements
TX
PROTECT: CON'S RACi DA-1"ED:
i:Ntane and ad&vKfl
Contract 2009/WSM-A DOE 6565/Water Sewer Replacements
=ort Worth, TX
in teetweer;the Owner anti the Cantractor as indicated albava,the
(/tuerr name alit(adrfe�3s ct5rrrwyJ
The Hanover insurance Company
440 Lincoln Street
Worcester MA 01653
SUET-TY,
on bond of
tinter name and addrem o{Canrraaar)
Jackson Construction, Ltd.
5112 Sun Valley Drive
Fort Worth TX 76119
CONTRACTOR,
hereby apptrnes of the n^.al payment to the Contractor,and agrees that final payment to the Contractor shall not relieve the Surety or
any of its obligations to
(l,zwrt natneand addren o,f caner)
City of Fort Worth, Texas
TX
OW?ZER,
as set forth in said 5ureys bond
LN WITNESS WHEREOF,the Surety has hereunto set iLs hand ors This date: March 10, 2015
(lnrrl in uv idrg,t&-month folloxtd 4-sire munerk dssr and.swar.)
The Hanover Insurance Company
{Srrrr'ry)
1 CS{gnaturcofw r�iuQrrpresen+atiser)
Attest;
�',;��J� . y Jack M. Crowley Attorney-in-Fact
thime$name and 1111e)
Surety Phone No. 508-853-7200 x-4476
G707--1994
THE HANOVER INSURANCE COMPANY
MASSACHUSETTS BAY INSURANCE COMPANY
CITIZENS INSURANCE COMPANY OF AMERICA
POWERS OF ATTORNEY
CERTIFIED COPY
KNOW ALL MEN BY THESE PRESENTS: That THE HANOVER INSURANCE COMPANY and MASSACHUSET 1 S BAY INSURANCE COMPANY,both;being
corporations organized and existing under the laws of the State of New Hampshire and CITIZENS INSURANCE COMPANY OF AMERICA,a corporation
organized and existing under the laws of the State of Michigan,do hereby constitute and appoint
Steven R.Foster,Jack M.Crowley;Patricia A.Smith and/or Marie Perryman
of Dallas,TX and each is a true and lawful Attorney(s)-in-fact to sign,execute,seal,acknowledge and deliver for,and on its behalf,and as its act and deed
any place within the United States,or,if the following line be filled in only within the area therein designated any and all bonds,recognizances:undertakings,
contracts of indemnity or other writings obligatory in the nature thereof,as follows:
Any such obligations in the United States,not to exceed Thirty Five Million and No/100($35,000,000)in any single instance
and said companies hereby ratify and confirm all and whatsoever said Attomey(sl-in-fact may lawfully do in the premises by virtue of these presents.
These appointments are made under and by authority of the following Resolution passed by the Board of Directors of said Companies which resolutions
are still in effect:
"RESOLVED.That the President or any Vice President,in conjunction with any Vice President.be and they are hereby authorized and empowered to appoint
Attomeys-in-fact of the Company,in its name and as its acts.to execute and acknowledge for and on its behalf as Surety any and all bongs.recognizances,
contracts of indemnity,waivers of citation anc all other writings obligatory in the nature thereof,with power to atach thereto the seal of the Company.Any such
writings so executed by such Attomeys-in-fact shall be as binding upon the Company as if they had been duly executed and acknowledged by the regularly
elected officers of the Company in their own proper persons` (Adopted October 7 1981 -The Hanover Insurance Company,Adopted April 14. 1982-
Massachusetts Bay Insurance Company,Adopted September 7.2001-Citizens Insurance Company of America)
W WITNESS WHEREOF, THE HANOVER INSURANCE COMPANY, MASSACHUSETTS BAY INSURANCE COMPANY and CITIZENS INSURANCE
COMPANY OF AME-RICA have caused these presents to be sealed with their respective corporate seals,duly attested by two Vice Presidents,
this 5th day of December 2011.
THE}iANCFVER INSURANCE COMPANY
MASSACHUSETTS BAY INSURANCE COMPANY
CITIZENSII SURANCE:POMPANY OF AMERICA
4
r /
ftclk.rr Thomas. Vice Prpsitient
THE COMMONWEALTH OF MASSACHUSETTS
COUNTY OF WORCESTER ss. Ire BTenstrorn. Vicc' ?resilient
On this 5th day of December 2011 before me came the above named Vice Presidents of The Hanover Insurance Company,Massachusetts Bay Insurance
Company and Citizens Insurance Company of America,to me personally known to be the individuals and officers described herein;and acknowledged that the
seals affixed to the preceding instrument are the corporate seals of The Hanover Insurance Company,Massachusetts Bay Insurance Company and Citizens
insurance Company of America, respectively, and that the said corporate seats and their signatures as officers were duly affixed and subscribed to said
instrument by the authority and direction of said Corporations.
�5'�wr� oAPB.ARkA,vARt.ti,Y,
� ttdtary Public �� _ y/'/ 1
:�mfr10'7�'E3�t1��1�Li5aL1t115Ch51,./�,t ) pr�f flf_4/
L�Lh�t�>sMnza'�x55eF. -
Barbara A.Garlick, Notary Public
My Commission Expires September 21,2018
I.the undersigned Vice President of The Hanover Insurance Company Massachusetts Bay insurance Company and Citizens Insurance Company of America,
hereby certify that the above and foregoing is a full,true and correct copy of the Original Power of Attorney issued by said Companies,and do hereby further
certify that the said Powers of Attorney are still in force and effect.
This Certificate may be signed by facsimile under and by authority of the following resolution of the Board of Directors of The Hanover Insurance Company,
Massachusetts Bay Insurance Company and Citizens Insurance Company of America.
"RESOLVED,That any and all Powers of Attorney and Certified Copies of such Powers of Attomey and certification in respect thereto,granted and executed
by the President or any Vice President in conjunction with any Vice President of the Company,shall be binding on the Company to the same extent as if all
signatures therein were manually affixed,even though one or more of any such signatures thereon may be facsimile.` (Adapted October 7, 1981-The
Hanover Insurance Company,Adopted April 14,1982-Massachusetts Bay Insurance Company,Adopted September 7,2001-Citizens Insurance Company of
America)
GIVEN under my hand and the seals of said Companies,at Worcester,Massachusetts,this 10th day of March 2015.
THE HANOVER INSURANCE COMPANY
MASSACHUSETTS BAY INSURANCE COMPANY
CITIZENS INSURANCE COMPANY OF AMERICA
(:�teitn Margosian,Vice President
&I JACKS Q50
C=ONSTRUCTION LTD.
51 12 SUN VALLEY DRIVE
FORT WORTH,TX 76119
TEL 817-572-3303
FAX 817-478-0443
Affidavit of All Bills Paid
STATE OF TEXAS
KNOW ALL MEN BY THESE PRESENTS:
COUNTY OF TARRANT
I, Troy L. Jackson, of the undersigned principal hereby certify that all
obligations, claims and debts due laborers, materialmen, subcontractors,
suppliers, and others incurred in or contingent to the performance of the
work on the project known as Water and Sanitary Sewer Replacement Contract
2009 WSM-A in the City of Fort Worth, Texas have been fully paid.
This affidavit is made for the purpose of obtaining payment from the
City of Fort Worth on above construction work.
Subscribed and sworn to before me this Jackson Construction, Ltd.
Principal
10th Day of March, 2015
By.
to Signature Troy L. Jac on,Vice resident
Commission Expires: 04/06/2016
`4pRV yUBCARMEN L. ESTEP
Notory Public,Stote of Texos
e€ My commission Expires
April 06, 2016
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Water and Sanitary Sewer Replacement Contract 2009
PROJECT NUMBER: 1444
DOE NUMBER: 6565
WATER
PIPE LAID SIZE TYPE OF PIPE LF
24" PVC 2013
12" PVC 1115
8" PVC 8634.4
6" PVC 85
FIRE HYDRANTS: I I VALVES(161"OR LARGER) 2
PIPE ABANDONED SIZE TYPE OF PIPE LF
24" PVC 2013
12" PVC 1115
8" PVC 8634
6" PVC 85
DENSITIES: Yes
NEW SERVICES: (255) 1-
(10)
255) 1"(10) 1 1/2"
(5)_2'
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
8" DIP 52
8" PVC 645
PIPE ABANDONED SIZE TYPE OF PIPE LF
8" PVC 697
DENSITIES: Yes
NEW SERVICES: (2)4" PVC
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth•1000 Throckmorton Street•Fort Worth,TX 76012-6311
la
(817)392-7941 •Fax:(817)392-7845
FORTWORTHREV:02/20/07
TRANSPORTATION AND PUBLIC WORKS
PERFORMANCE EVALUATION OF CONTRACTOR
CONTRACTOR&PROJECT DATA
Name of Contractor Project Name
Jackson Construction Water and Sanitary Sewer Replacement Contract 2009
DOE Inspector DOE Number
Richard Salazar 6565
DOE Inspector Project Manager
Q WaterO Waste Water❑ Storm Drainage0 Pavement Rakesh Chaube
Initial Contract Amount Project Difficulty
$1,638,475.30 0 Simple Q Routine 0 Complex
Final Contract Amount s Date
V,ft670 S 3/9/2015
In PERFORMANCE EVALUATION
0-Inadequate 1-Deficient 2-Standard 3-Good 4-Excellent
ELEMENT WEIGHT(x) APPLICABLE(Y/N) RATING(0-4) MAX SCORE SCORE
1 Submission of Documents 2 Y 3 8 6
2 Public Notifications 5 Y 3 20 15
3 Plans on Site 5 Y 4 20 20
4 Field Supervision 15 Y 3 60 45
5 Work Performed 15 Y 4 60 60
6 Finished Product 15 Y 4 60 60
7 Job Site Safety 15 Y 3 60 45
8 Traffic Control Maintenance 15 Y 3 60 45
9 Daily Clean Up 5 Y 3 20 1 15
10 Citizen's Complaint Resolution 5 Y 3 20 15
11 Property Restoration 5 Y 3 20 15
12 After Hours Response 5 Y 3 20 15
13 Project Completion 5 Y 3 20 15
TOTAL ELEMENT SCORE(A) 371
BONUS POIN'T'S(25 Maximum)(B)
TOTAL SCORE(PS) 371
III)CONTRACTOR'S RATING
Maximum Score(MS)=448 or sum of applicable element score maximums which= 448
Rating([TS/NLS]* 100%) 371 / 448 — 83%
Performance Category Excellent
<20%=Inadequate 20%to<40%=Deficient 40%to<60%=Standard 60%to<80%=Good _>80%=Excellent
Inspector's Comments(INCLUDING EXPLANATION OF BONUS POINTS AWARDED)
Signature DOE Inspector Signature Contractor
Signature DOE Inspector's Supervisor
CONTRACTOR'S COMMENTS
TRANSPORTATION AND PUBLIC WORKS
The City of Fort Worth•1000 Throdanorton Street•Fort Worth„TX 76012-6311
(817)392-7941 •Fax:(817)392-7845
FORTWORTHREV:02/22/07
TRANSPORTATION AND PUBLIC WORKS
CONTRACTOR'S EVALUATION OF CITY
PROJECT INFORMATION Date: 3/9/2015
Name of Contractor Project Name
Jackson Construction,LTD Water and Sanitary Sewer Replacement Contract 2009
DOE inspector Project Manager
Richard Salazar Rakesh Chaube
DOE Number Project Difficulty Type of Contract
6565 0 Simple OQ Routine 0 Complex 2 waterRI Waste water Storm Drainage0 Pavement
Initial Contract Amount Final Contract Amount
$ 1,638,475.30 )Ob S—
II)
i
/
II)PERFORMANCE EVALUATION
0-Inadequate 1 -Deficient 2-Standard 3 -Good 4-Excellent
ELEMENT RATING ELEMENT RATING
(0-4) (0-4)
INSPECTION EVALUATION PLANS&SPECIFICATIONS
1 Availability of Inspector 1 Accuracy of Plans to Existing Conditions
2 Knowledge of Inspector 2 Clarity&Sufficiency of Details
3 Accuracy of Measured Quantities 3 Applicability of Specifications
4 Display Of Professionalism 4 Accuracy of Plan Quantities
5 Citizen Complaint Resolution PROJECT MANAGER EVALUATION
6 Performance-Setting up Valve Crews,Labs 1 Knowledge And/Or Problem Resolution
ADMINISTRATION 2 Availability of Project Manager
1 Chane Order Processing Time Y 3 Communication 3
2 Timliness of Contractor Pa ents 1 4 Resolution of Utility Conflicts
3 Bid Opening to Pre-Con Meeting Timeframe
IIT)COMMENTS&SIGNATURES
COMMENTS
Signature Contractor
Signature DOE Inspector
Signature DOE Inspector's Supervisor
INSPECTOR'S COMMENTS
TRANSPORTATION A!-ID PUBLIC WORKS
ID
The City,of Fort Worth-1000 Throckmorton Street-Fort Worth,TX 76012-6311
(817)392-7941 -Fax:(817)392-7845
FORT WORTH,
TRANSPORTATION AND PUBLIC WORKS
STATEMENT OF CONTRACT TIME
STATEMENT#
FINAL STATEMENT# 22 DOE
NAME OF PROJECT: Wator and Sattilary Sowor Pj*boottwdConboft4#06 Contractor • icer:COASL
YEAR:j 2015
PROJECT NO.: FINAL INSPECTION DATE W9W14
WD CD
CONTRACT TIME 200 1 X
PERIOD FROM: TO: 1,2118r1d1KMID - Month j1DEVFL0Pmmf4(Y/N N
WORK ORDER EFFECTIVE: ": BEG /n ARID /n
DAY OF MONTH DAYS REASON FOR DAY OF MONTH DAYS REASON FOR
CHARGED DAYS CREDITED CHARGED DAYS CREDITED
1 16 Mon 0
2 0 WA 17 Tue 0
3 0 ISA 18 Wed 0
4 0 NIA 19 Thu 0
5 0 [ 20 Fri 0 f
6 0 21 Sat 0 $tom ft
7 0 22 Sun 0 Slate kitfl6
8 0 23 Mon 0 Stop tariafl
9 0 24 Tue 0 stop 17cTFB!
10 0 WR 25 Wed 0 stop of
11 0 NfA 26 Thu 0 mwft
12 0 IVIG 27 1 Fri 0 ftR AMR
13 0 28 Sat 0 §Ng lift
14 0 Int 29 0 -ft
15 0 30 0 W
31 0 Btor fits!
�Idol d�
Not Applicable SAT,SUN,and WEATHER UTILITIES OTHERS DAYS TOTAL DAYS
HOLIDAYS RELOCATE CHARGED
THIS PERIOD 0 0 0 0 0 0
PREVIOUS PERIOD ( 2" 299
TOTAL TO DATE 1 0 0 0 0 299 299
REMARKS:
Stop time on 8/0112010
Sigmrtures Signature:
Eft � Yt3 d Richard Salazar