HomeMy WebLinkAboutContract 45075-CO1 CITY SECRETARY 'er—CC3 FORT WORTH. City of Fort Worth CONTRACT NO. O Change Order Request Project Name I Mercado Channel Improvements City Sec# 1 45075 Client Project#(s)l DOE#56821 City Project#00779 Project Channel improvements consisting of construction of pre-cast concrete block retaining walls to increase channel Description conveyance and reduce streambank_erosion. Contractorl CD Builders, Inc Change Order# Date 4/21/2015 City Project Mgr.I Raul Lopez City Inspector Quincy Jones Dept. TPW-Storm Contract Time Water Totals D Original Contract Amount $1,047,221.50 $1,047,221.50 270 Extras to Date Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1047,221,50 $1,047,221.50 270 Amount of Proposed Change Order $0.00 15 Revised Contract Amount $1,047,221.50 $1,047,221.50 285 Original Funds Available for Change Orders $29,000.00 $29,000.00 Remaining Funds Available for this CO $29,000.00 $29,000.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00% MAX ALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,309,026.88 Changes to the contract prompted by: 1)Unanticipated utility conflict-An existing waterline across creek had to be lowered because it was in conflict with proposed grading on the creek banks.The water line was shown in the construction plans in plan view however a profile of it was not shown and SUE level A did not find it within 12 feet of depth where probed; 2)To protect against erosion,a 4"concrete flume was constructed along edge of north retaining wall at downstream end of project-The June 24,2014 heavy rains caused severe erosion and damage along the top edge of the recently installed concrete block wall.A concrete flume was recommended to channel offsite runoff away from the wall. 3)One row of sheet piles was not required because one of the 3 proposed drop structures was eliminated due t ion change at the outfall being 2 feet less than that shown in the plans. 4)A significant amount of the proposed Articulat cqR M the bottom of the channel was not used because it was found during construction that the existing concrete rip-rap in t s C-1) approximately 12-18"thick. It was decided to keep the bottom concrete rip rap. C A �a o rn ° n VIMS& intyMOAR 00 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfactioNan �' � ent F-4 in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. CD Buikjers, Inc r { ' I r l - i` z!3 , Man - M&C NumberSECgETAgy M&C Date Approved FT.WORTH,TX cu - - if) ° Nr � ® ' 2 % co o & G cqccE O Z- 8 a $ ca A - » £ ) — k ° » / M # J / CD O C4 k = � / $ E ® ® O = E k ® r O a9 a- 0 k § 0 0 ,0 .8 f 2 = « LLCL / � 0 . 0 O m U § 2 / t 2 U 0 ECD 2 2 2 a G � � E2 co2 ECL ° cn 0 C / :2k W) \ = o ¥ w E m 2 . I R k k E = o 2 @ e # Et § # & @ $ 0 o f ( 0) ° 0 2 v to co 0 N Goc) 609, a� c is o_ E o cu C o a � N 4- 0 N GJ t10 m a c O v O v on c m L U cu - � ° Ll� k k k f Q 8 e $ k k § _ 4) § » DO \ # � k / E o ® k / \ & $ y e / Ue c O f Qj_ ■ k E E c -0 Q w 6 2 k z § o z kp ° LU LL � / -a / O CD / \ U § # / U 8 \ a 2 E \ E 2 # ° § U § • ) 8f - _ CL D $ _ E a_ff (1) -1 \ 4-- 2 a m Z \ ca ( ? k $ S 2 E K ± r4 E ® E ° a a o 8 7 S m _ 5 RqL 11 11 1 11 § 5 / 0 : E -U0 N 04 c 7 f ? k mm & b : co m& C.0 CD rn v 0 N O N C � O N O � � O H O N O N O1 OA m d C O .w N N 0 O1 a 0 N OA C m t V M/WBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO N/A(C/O<50K) Total $0.00 Previous Change Orders Co# DATE AMOUNT None Total $0.00