HomeMy WebLinkAboutContract 45999-CO1 CFW Change Order Approval CO-05-PaD Page 2 of 3
CITY SECRE AW
CONTPACT N0.
FORTWORTH.., City of Fort Worth
Change Order Request Approval
lroo� (Change Order Breakdown Available in Links)
For Change Order Submittal No.: 1
Change Order No.: CO-05-PaD Date Started: 2015-06-01
City Sec. No.: 45999 Date Due: 2015-06-04
Project Name: Wayfinding Sign Installations
DOE Numbers:
Project Numbers:
Project Change in reflectivity material due to duribility concerns
Description: with specified product. Ten (10) working days will be added to
order and apply the new product. Details are available in
change order breakdown.
Project Manager: Randy Hutcheson City Inspector: Randy Hutcheson
Contractor: Bunting Graphics, Inc.
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date:
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
Planning & Development $ 30,287.14 GR76-541200-022-302825-800 10
Total Cost: $ 30,287.14 Total Requested Days: 10
Approval Status:
M
M
M
0
Z
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH,TX
https:Hprojectpoint.buzzsaw.com/ bz web/Forms/FonnPrint.aspx?Siteld=51500&Proces... 06/02/2015
CFW Change Order Approval CO-05-PaD Page 3 of 3
Approved: Yes
Comments:
User: Randle Harwood
Date: 2015-06-01 8:54 PM
Approved: Yes
Comments:
User: Melinda Ramos
Date: 2015-06-02 3:20 PM
Approved: Yes
Comments:
User: Fernando Costa
Date: 2015-06-02 3:34 PM
Action Required: Please review, approve, and submit
Vol?T���
0
%0
%
a
Allison Tidwell,Assistant to the City SWf6tUy �*
TEXA000,S
A
.RECORD
CRRFARY
RTN,TX
https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Site1d=51500&Proces... 06/02/2015
FORT WORTH City of Fort Worth
Change Order Request Breakdown
Project Namel Wayfinding Signage Installation City Sec# 1 45999
Client Project#(s)l City Project Number 302825 CSJ 0902-48-802 TxDOT Project Number STP 2003(528)MM
Contracto Bunting Graphics,Inc. PMI Randy Hutcheson Inspectorl Randy Hutcheson
Change Order Submittal# Date 05/29/2015
Dept. P&D Contract Time
Totals (CD)
Original Contract Amount $498,560.16 $498,560.16 171
Extras to Date $0.00
Credits to Date $0.00
Pending Change Orders(in M&C Process) $0.00
Contract Cost to Date $498,560.16 $498,560.16 171
Amount of Proposed Change Order $30,287.14 $30,287.14 10
Revised Contract Amount $528,847.30 $528,847.30 181
Original Funds Available for Change Orders $49,856.16 $49,856.16
Remaining Funds Available for this CO $49,856.16 $49,856.16
Additional Funding(if necessary)
CHANGE ORDERS to DA TE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 6.07%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $623,200.20
The product specified for messaging(names of locations and arrows)on each sign is Oracal 5800 Reflective and 8300 Transparent. During
fabrication,Bunting Graphics,Inc.discovered that the 8300 Transparent pulled apart easily from the base 5800 Reflective material.They
notified me of their concerns with the Oracal material.In response,I requested an investigation of the material to determine if the problem was
associated with one for the following;1.Wrong specification 2.Defective material 3.Improper application. In response,a Oracal product
representative visited the fabrication facility at Bunting to observe the application process. No problems were observed. The remaining
material was shipped to the Oracal facility in Georgia. The manufacturer replicated the condition experienced at the fabrication plant. They
also verified that the product was correctly specified for the application. They stated that they would write a special warranty for the use of
their product in Fort Worth. The Oracal product has a 5 year warranty. During the investigation of the specified product,Bunting sought
alternative materials. After review of a product from 3M,Bunting and our design consultant,Corbin Design,Inc.,I approved the substitution
material(3M 4090 DG3 Diamond Grade Reflective Material). The new material carries a 12 year warranty. Due to separation concerns with
the Oracal 8300 Transparent material,length of warranty,and the need for a special warranty,I am recommending a change in material. I
have consulted with primary community partners at Downtown Fort Worth,Inc.and they feel a change in product is acceptable.
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
Fo r_g Wogs City of Fort Worth
T Change Order Additions
Project Name I Wayfinding S'n e Installation City Sec# 45999
Client Project# I City Proect Number 302825 CSJ 0902.48.802 TxDOT Project Number STP 2003 528 MM
Bunting Grephks,Inc. PM Randy Hutcheson Inspector Randy Hutcheson
Charge Order Submittal# 0 Date 05/29/2015
AUDI I TUNS
ITEM DESGRFT= DEPT Qty Unit ni os Total
Diamond urade Refiecg7e
P&D $30,287.14
u Total Additions 7.
Change Order Additions Page 1 of 2
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
Dallas Digital Signs Installation $0.00
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00