HomeMy WebLinkAboutResolution 4469-06-2015 Resolution
NO. 4469-06-2015
STATEMENT EXPRESSING
OFFICIAL INTENT TO REIMBURSE
EXPENDITURES WITH PROCEEDS OF FUTURE DEBT FOR THE
Water and Sewer Replacement Contract 2011 WSM-F PROJECT
WHEREAS, the City of Fort Worth, Texas (the "City") is a home-
rule municipality and political subdivision of the State of Texas; and
WHEREAS, the City expects to pay expenditures in connection with the
design, planning, acquisition and construction for the Water and Sewer
Replacement Contract 2011 WSM-F project as shown on the attached map (the
"Project") prior to the issuance of obligations by the City in connection with the
financing of the Project from available funds; and
WHEREAS, the City finds, considers, and declares that the
reimbursement of the City for the payment of such expenditures will
be appropriate and consistent with the lawful objectives of the City
and, as such, chooses to declare its intention, in accordance with the
provisions of Section 1.150-2 of the Treasury Regulations, to reimburse
itself for such payments at such time as it issues obligations to finance
the Project;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS:
Section 1. The City reasonably expects debt, as one or more series of
obligations, may be issued or incurred by the City with an aggregate maximum
principal amount not to exceed $3,000,000.00 for the purpose of paying the
aggregate costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto will be capital t
expenditures. No obligations will be issued by the City in furtherance of this
Statement after a date which is later than 18 months after the later of (1) the
date the expenditures are paid or (2) the date on which the property, with
respect to which such expenditures were made, is placed in service.
I
URT ORT
i
Resolution No.4469-06-2015
Section 3. The foregoing notwithstanding, no obligation will be issued
pursuant to this Statement more than three years after the date any
expenditure which is to be reimbursed is paid.
Adopted this 91h day of June, 2015.
0.0000000 o ;
ATTEST: Q® �¢
0
® Q
0 OP
B Y: j— "'."�I —
6 kZ1 ------- 0000
Mary 'Ka X` r, Citecretar
,, Y Y
r
F
ORT ORT
f
o✓
r i 9
9
MAYOR AND COUNCIL COMMUNICATION MAP
OB so-S ST '�i
All d
FORTWORTH
l ��l
,
,
I.
s
i
I
r
i
WAM
i'
i
n
COMMUNICATION MAYOR AND COUNCIL
,t
f
r f i '��j +i ++ MISTrLETOE BLVD r
W MAGNOLIA AVE
W MAGNOLIA AVE
p
m
,o.
i
HARRISON AVE
l
r f�;
HARRISON AVE
W MORPHY ST o
MISTLETOE
EDWIN ST
�s
W �
FORTWORTH
•u• p}i�iiiiiiigiiiiii�il@iii a
WAM
c4 j
0 .
,
�;,; MC LEMORE AVE
r
/ l
r / �irna� % rrr � � m U ✓ 116��/�k
MAYOR AND COUNCIL COMMUNICATION MAP
P
! 1l
PLUMWOOD ST
MARSHALL
/ NOBLE AVE ly
G-LIS ST
FORTWORTH
WAM
y ,�J
ESQ' .v
f
PITTSBURG PL �^' '
I , TERRANCE 5T 1
r
MAYOR AND COUNCIL COMMUNICATION MAP
G� r
Jarr
Cti Dig
�,` SPRINGHILL �
S
CUMBERLAND RD
RTWORTH
II ii
i �rri 1 r
WAHR
COMMUNICATION MAYOR AND COUNCIL
fo
LL
Cif' , G� s� � L �� l L• %r
r s C'1
tVOODSTOCK� RD � 'D �
u
B'RANTS LN�' G�
,
y
s
o
u
� r
r
i
rJ
p
FORTWORTH n
E
0
A
J
f
City , Texas
Mayor and Council Comm unication
, m�orr i,,ur,,;to/ /u;,n.na,.: / ,Darr. r,,,/mir,:/zrJ/ /.ri ai,,,,:.a / m,q.,✓rr„r<r.✓irc.,lz/r ,eur,rzrr ,;,Jn/o%uu:..l,am,n,,;l,e:v,;, /r/r, ,,,:r/ /u, a. ,zr ,. ,.,,�,,:,�,.,, ;Fr,uli2 ra renrn°r;naar,nnmr-gar
COUNCIL ACTION: Approved on 6/9/2015 - Resolution No. 4469-06-2015
/ A 1L,//GC,,:.//I,J//f/.,.l c...,d/J//P/(Ul/,�vJ1 OL/!A�/�/IJa"J/OUI;RJ/Idl%I!/IGLJ Id/f///J/.dll/l,:G'?!'i,IJ;/J/,1N//�//////J f2Y////J/,/JG/!J/JJJJ.I/I//fU(dJ)f/%///J;J/d/lJ///UIOA:'✓l/Jl///////J////L//41f/O////J///IJ;/J/,l/J/UJdYI1pIG)/A/1//%///d%//JZ/X/1!/C+J/ul
DATE: Tuesday, June 09, 2015 REFERENCE NO.: C-27328
LOG NAME: 6011 WSMF-CONATSER
SUBJECT:
Authorize Execution of a Contract with Conatser Construction TX, LP, in the Amount of$2,620,310.00 for
Water and Sanitary Sewer Replacement Contract No. 2011, WSM-F on Clayton Road, Woodstock Road,
Angus Drive, Grace Avenue, Harrison Avenue, W. Morphy Street and True Avenue, Provide for Project
Costs and Contingencies for a Project Total in the Amount of$2,753,310.00 and Adopt Reimbursement
Resolution (COUNCIL DISTRICT 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of a contract with Conatser Construction TX, LP, in the amount of
$2,620,310.00 for Water and Sanitary Sewer Replacement Contract No. 2011, WSM-F; and
2. Adopt the attached resolution expressing its official Intent to Reimburse expenditures with proceeds of
future debt for the Water and Sewer Replacement Contract No. 2011, WSM-F Project.
DISCUSSION:
On September 11, 2012, (M&C C-25815) the City Council authorized an Engineering Agreement with
APM and Associates, Inc., to prepare the plans and specifications for Water and Sanitary Sewer
Replacement Contract No. 2011, WSM-F.
This Mayor and Council Communication (M&C) is to authorize a construction contract for the replacement
of the deteriorated water and/or sanitary sewer mains as indicated on the following streets:
STREET FROM TO SCOPE OF
WORK
Clayton Road Floyd Drive Rowan Drive water/sewer
W.
Woodstock Road Rowan Drvie Dayton Road (water/sewer
Angus Drive Chickering Road IWayton Road (sewer
Marshall
Grace Avenue Avenue Race Street water
Harrison Avenue Jerome Street E. Dead End wa
.. ...ter ;.
W. Morphy Street Jerome Street E. Dead End water
Logname: 6011 WSMF-CONATSER Page 1 of 4
True Avenue NW 16th Street JFlagstone Drive water/sewer
The project was advertised for bid on October 30, 2014 and November 6, 2014 in the Fort Worth Star-
Telegram. On December 18, 2014, the following bids were received:
_..w.. ... . ..... __ _.....__.. ___, __. -
�BiDDEF2 AnnOUNT TIME... __
�Conatser Construction, TX, LP $2,620,310.00� s alendar
Y
A&M Construction and Utilities, Inc $2,956,620.50
William J Schultz, Inc Circle "C"
Construction
$3 104,285.00
Jackson Construction LTD $3,202 494.00
M.E. Burns Construction, Inc. ($3,340,615.00
Ark Contracting Services, LLC $3,366,545.00
Atkins Brothers Equipment Co., Inc. $4,760,900.00
In addition to the contract amount, the amount of$54,000.00 (water: $29,500.00; sewer: $24,500.00) is
required for construction staking, inspection and material testing and $79,000.00 (water: $47,000.00;
sewer: $32,000.00) is provided for project contingencies.
Upon approval of this M&C, appropriations for the Water and Sewer Replacement Contract No. 2011,
WSM-F, will consist of the following:
_ _.. _w.. _..._...__._...___ _
[APM and Associates �$ 220,345.00
�Conatser Construction TX, LP $2,620,310.00
Construction Staking, Project
Management, Inspection, Material $ 160,000.00
Testing and Contingencies
Total $3,000,655.00
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.
Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation
authority authorized under the Direct Purchase Note program will be used to provide interim financing for
this project until debt is issued. To the extent resources other than the Water and Sewer portfolio are
used to provide interim financing, the Water and Sewer Fund will be charged interest that is equivalent to
the overall rate of return being earned by the City portfolio (currently approximately one-percent
annually). Should the City's portfolio not support the liquidity needed to provide an interim short-term
financing source, another funding source will be required, which could mean issuance of securities under
the Direct Purchase Note Program or earlier issuance of Water and Sewer revenue bonds than is
currently planned. Once debt associated with this project is sold, bond proceeds will be used to reimburse
the Water and Sewer portfolio and the City's portfolio, in accordance with the attached Reimbursement
Resolution.
ii
In accordance with the provisions of the Financial Management Policy Statements, Staff anticipates
presenting revenue-supported debt issuances to the City Council for consideration within the next three
years. The Financial Management Services Department is currently working with all departments to
ensure that multi-year Capital Improvements Plans are in place. Newly developed and already existing
Logname: 6011 WSMF-CONATSER Page 2 of 4
plans, such as the Water Department's current multi-year Capital Improvement Plan, will be presented to
City Council for review and adoption. If the City Council adopted plan does not include issuance of debt
for this specific project, the project will be funded utilizing pay-as-you go financing sources. If the City
Council adopted plan calls for debt issuance, that debt must be issued within approximately three years to
provide reimbursement for these expenses. If that does not occur, the costs will no longer be
reimbursable by issuing tax-exempt debt and the funding source will have to be made whole through other
budgetary methods. Adoption of this resolution does not obligate the City to sell bonds, but preserves the
ability to reimburse the City from tax-exempt bond proceeds.
Existing Additional Revised Encumbrances
Fund ,appropriations Appropriations Appropriations and Balance
Expenditures
Water
Capital
Projects $ 135,153.00 $ 0.00 $ 135,153.00 $126,153.00 $ 9,000.00
Fund
P253
Sewer
Capital
Projects $112,192.00 $ 0.00 $ 112,192.00 $103,192.00 $ 9,000.00
Fund
P258
2017
Water
and
Sewer
Revenue $ 0.00 $2,753,310.00 $2,753,310.00 $ 0.00 $2,753,310.00
Bonds
Capital
Project
Fund
(Total Is 247,345.00 $2,753,310.00 $3,000,655.00 $229,345.00 I$_2,,_7_7_1__,_31_
$2,771,310.00
...._ _ - -___.. -.._._.. _._. _ - - --_
Construction is anticipated to commence in July 2015. With a contract time of 150 calendar days, the
construction is estimated to be complete by the end of January 2016.
M/WBE OFFICE - Conatser Construction, TX, LP, is in compliance with the City's BDE Ordinance by
committing to eight percent MBE participation and documenting good faith effort. Conatser Construction
TX, LP, identified several subcontracting and supplier opportunities. However, the MBE's contacted in the
areas identified did not submit the lowest bids. The City's MBE goal on this project is 14 percent. a
The project is located in COUNCIL DISTRICT 9, Mapsco 76S and 76W.
i
FISCAL INFORMATION /CERTIFICATION: t
t,
i
The Financial Management Services Director certifies that appropriations are available as directed by
M&C G-18375 in the 2017 Water and Sewer Revenue Bonds Capital Project Fund for transfer from
Unspecified Funding to the Water and Sanitary Sewer Replacement Contract No. 2011, WSM-F Project
for this contract, as depicted in the table:
:
r
Logname: 6011 WSMF-CONATSER Page 3 of 4
Available Remaining
Fund Appropriation Transfer Available
Amount Appropriation
Amount
2017 Water
and Sewer
Revenue $62,866,782.06 $2,753,310.00 $60,113,472.06
Bonds Capital
Project Fund
FUND CENTERS:
TO Fund/Account/Centers FROM Fund/Account/Centers
P266 485114 601159990100 $2,753,310.00
P266 541200 603170193083 $1,610,710.00
P266 541200 703170193083 $1,088,600.00
P266 511010 603170193080 $4,500.00
P266 531200 603170193084 $8,000.00
P266 531350 603170193084 $2,000.00
P266 531350 603170193085 $15,000.00
P266 511010 703170193080 $3,500.00
P266 531200 703170193084 $8,000.00
P266 531350 703170193084 $1,000.00
P266 531350 703170193085 $12,000.00
CERTIFICATIONS:
Submitted for City Manager's Office by_: Fernando Costa (6122)
Originating Department Head: John Carman (8246)
Additional Information Contact: Roberto Sauceda (2387)
i
i
p
Logname: 6011 WSMF-CONATSER Page 4 of 4
rt