HomeMy WebLinkAboutContract 44408-CO3 CITY 5ECRETAW
FORT WORTIN City of Fort Worth CONTRACT NO. -44409-e-Q3
Change Order Request
Trinity River Vision Phase 1-Bridge and Channel Relocations-Main Street
Water&Sewer Units 1A and 1 B(Part 3):Grand Ave.Storm Drain Unit 2(Part City Sec No. 44408
Project Name 1)
P265-6091760096987(Unit 1A),P275-
Project No.(s)709170096987(Unit 1B)and FE72451970- DOE No. 6940 City Pro.No. 0969
006231701000(Unit 2)
Project Description Water and Sanitary Sewer Utility Relocations for the Tdity River Vision Central City and Trinity Uptown Projects
Contractorl S.J.Louis Construction of Texas,Ltd. Change Order# Date: 7/22/2015
City Project Mgr. Liam Conlon CityInspector I Paul Gieger
Phone Number 817-392-6824 Phone Number: 817-223-2258
Dept. Water(Unit 1A) Sewer(Unit 113) Storm(Unit 2) Totals Contract
Time
Original Contract Amount $5,584,285.24 $178,027.00 $167,431.95 $5,929,744.19 360
Extras to Date $90,684.75 $761,917.32 $852,602.07 81
Credits to Date -$395,551.66 -$395,551.66
Pending Change Orders(in M&C Process)
Contract Cost to Date $5,279,418.33 $939,944.32 $167,431.95 $6,386,794.60 441
Amount of Proposed Change Order $482,508.05 $75,732.00 $558,240.05 09
Revised Contract Amount $5,761,926.38 $1,015,676.32 $167,431.95 $6,945,034.65 450
Original Funds Available for Change Orders $168,000.001 $18,000.001 1 $18,000.00
Remaining Funds Available for this CO
Additional Funding(if necessary) $482,508.051 $75,732.001 $558,240.05
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 17.12%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $7,412,180.24
FIC TiW+I.01MAWNSIFOR CHANGE ORDS
Change Order No.3 will provide compensation for additional pavement repair and replacement sub and/or sanitary
sewer installation at the following locations due to the poor condition of the existing pavement c ssitated
additional improvements beyond the trench width:
° ®
•Adolf Street
•White Settlement Roado
•Rupert Street va �\ �7 0
•Greenleaf Street lel ,;., �o?
•North Commerce Street `° �o°
•North Main Street 0
•NE 11th Street glary J. Ser, lty Se �!!s
•6th Street _.
This change order contains both FWCC(reimbursable by TRVA)and Non-FWCC(city costs)components.
The FWCC cost of the change order cost is: $147,834.00(water:$72,102.00,sewer:$75,732.00)
The Non-FWCC cost of the change order cost is: $410,406.05(water)
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Name Contractor Name
S.J.Louis Construction of Texas,Ltd. Pete Stahl 17•V•/
i owl 15
T 5 .
Rp
rt jRY l
M&C Number C 27388 M&C Date Approved 7 1/2
_�I
23 �
t
� S
Q `s'
cai'
rL-c� TO
a o CP
FORT WORTH City of Fort Worth
W owl Change Order Additions
Trinity River Vision Phase 1-Bridge and Channel Relocations-Main Street Water&Sewer Units 1A 44408
Project Name and 1 B(Part 3):Grand Ave.Storm Drain Unit 2(Part 1) City Sec No.
Project No.(s) P265-6091760096987(Unit 1A),P275-709170096987(Unit 1B)and FE72 DOE No. 00969
6940
451970-006231701000(Unit 2) City Pro.No.
Project Water and Sanitary Sewer Utility Relocations for the Tdity River Vision Central City and Trinity Uptown Projects
Description
Contractor S.J.Louis Construction of Texas,Ltd. Change Order# 0 Date: 7/22/2015
City Project Mgr. Liam Conlon City Inspector Paul Gieger
ADDITIONS
ITEM DESCRIPTION DEPT Unit tlnitCost TMAA
10 6"DIP water(Non-FWCC) Water(Unit 1A) 20.00 LF $47.00 $940.00
32 6'Wide Asphalt Pvmt Repair(Non-FWCC) Water(Unit 1A) 405.00 LF $44.00 $17,820.00
34 Asphalt Pvmt Repair Beyond(Non-FWCC) Water(Unit 1A) 5097.00 SY $66.00 $336,402.00
35 11"Concrete Pvmt Repair(FWCC) Water(Unit 1A) 1182.00 SY $61.00 $72,102.00
36 4"Conc Sidewalk(Non-FWCC) Water(Unit 1A) 749.00 SF $4.00 $2,996.00
37 6"Concrete Driveway(Non-FWCC) Water(Unit 1A) 2238.00 SF $6.00 $13,428.00
38 6"Conc Curb and Gutter(Non-FWCC) Water(Unit 1A) 497.00 LF $17.00 $8,449.00
50 Trench Safety(Non-FWCC) Water(Unit 1A) 20.00 LF $0.01 $0.20
52 Ductile Iron Fittings(6-inch through 16-inch)(Non-FWCC) Water(Unit 1A) 0.25 TN $1.00 $0.25
69 6"Gate Valve(Non-FWCC) Water(Unit 1A) 1.00 EA $900.00 $900.00
80 8"x6"tapping sleeve(Non-FWCC) Water(Unit 1A) 1.00 EA $780.28 $780.28
81 6"Tap(Non-FWCC) Water(Unit 1A) 1.00 EA $1,437.50 $1,437.50
82 Install Temp.Water line and Service for QT and 11 houses.(Non-FWCC) Water(Unit 1A) 1.00 LS $17,372.26 $17,372.26
83 Additional Job Site Cleanup and Haul off for Franchise Utilities(Non-FWCC) Water(Unit 1A) 1.00 LS $9,880.56 $9,880.56
9 Asphalt Pvmt Repair Beyond(FWCC) Sewer(Unit 1 B) 55.00 SY $66.00 $3,630.00
10 11"Concrete Pvmt Repair(FWCC) Sewer(Unit 1B) 1182.00 SY $61.00 $72,102.00
5ALRECORD
Water(Unit 1A) $482,508.05
Sewer(Unit 1 B) $75,732.00
Storm(Unit 2)
Additions Sub Total 1$558,240.05
FFQP,-' WO a x m City of Fort worth
Change Order Deletions
Trinity River Vision Phase 1-Bridge and Channel Relocations-Main Street Water&
Project Name Sewer Units 1A and 1B(Part 3):Grand Ave.Storm Drain Unit 2(Part 1) City Sec No. 44408
Project No.(s) P265-6091760096987(Unit 1A), P275-709170096987(Unit 1B) DOE No.
and FE72-451970-006231701000(Unit 2) 6940 City Pro.No. 00969
Project Description Water and Sanitary Sewer Utility Relocations for the Tdity River Vision Central City and Trinity Uptown Projects
Contractor S.J. Louis Construction of Texas,Ltd. Change Order#E3 Date 712212015
City Project Mgr. Liam Conlon City Inspector FPaul Gieger
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
Water(Unit 1A)
Sewer(Unit 1B)
Storm(Unit 2)
Deletions Sub Total
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
M&C Review Page 1 of 4
Official site of the City of Fort Worth,Texas
CITY COUNCIL AGENDA FORT WORTH
COUNCIL ACTION: Approved on 7/21/2015 - Resolution Pending 7/28/2015
DATE: 7/21/2015 REFERENCE C-27388 LOG NAME: 60TRVP3MAINC03-
NO.: SJLOUIS
CODE: C TYPE: NON- PUBLIC CONSENT HEARING: NO
SUBJECT: Authorize Execution of Change Order No. 3 to City Secretary Contract No. 44408 with S.J.
Louis Construction of Texas, Ltd., in the Amount of$558,240.05 for Trinity River Vision,
Central City Project and the Trinity Uptown Service Area Phase 1 and Bridge and Channel
Relocations Part 3, for a Revised Total Contract in the Amount of$6,945,034.65,
Consistent with the City's Limit of$26.6 Million on Expenditures for the Trinity River Vision
and Adopt Reimbursement Resolution (COUNCIL DISTRICTS 2 and 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of Change Order No. 3 to City Secretary Contract No. 44408 with S.J.
Louis Construction of Texas, Ltd., in the amount of$558,240.05 for Trinity River Vision Central City
Project and the Trinity Uptown Service Area Phase 1 and Bridge and Channel Relocations Part 3, for
a revised contract total amount of$6,945,034.65, consistent with the City's limit of$26.6 million on
expenditures for the Trinity River Vision; and
2. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds of
future debt for Change Order No. 3 to City Secretary No.44408 for Trinity River Vision Central City
Project and the Trinity Uptown Service Area Phase 1 and Bridge and Channel Relocations Part 3.
DISCUSSION:
On March 26, 2013, (M&C C-26178) the City of Fort Worth (City) Council authorized a contract with
S.J. Louis Construction of Texas, Ltd., in the amount of$5,929,744.19 for Trinity Uptown Service Area
Phase 1 and Bridge and Channel Relocations Part 3. The contract was subsequently revised by two
change orders with a net total amount of$457,050.41.
Change Order No. 3 will provide compensation for additional pavement repair and replacement
subsequent to water and/or sanitary sewer installation at the following locations (as shown the attached
location maps) due to the poor condition of the existing pavement and sub-grade which necessitated
additional improvements beyond the trench width, Adolf Street, White Settlement Road, Rupert Street,
Greenleaf Street, North Commerce Street, North Main Street, NE 11th Street and 6th Street.
Subject to approval of this M&C, appropriations for Change Order No. 3 will consist of the following:
Water Sewer StormDrain1E Totals Authorization
Original
Contract $5,584,285.24 $178,027.00 $167,431.95 $5,929,744.19 C-26178
Amount
Change
Order $395,551.66 $753,914.32 $ -0- $ 358,362.66 C-26297
No. 1
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=21167&councildate=7/21/2015 7/24/2015
M&C Review Page 2 of 4
Change
Order $90,684.75 $8,003.00 $ -0- $ 98,687.75 Administrative
No. 2
Amount
of
Proposed $482,508.05 $75,732.00 $ -0- $558,240.05 This M&C
Change
Order
No. 3
Revised
Contract $5,761,926.38 $1,015,676.32 $167,431.95 $6,945,034.65
Amount
Water and sanitary sewer program costs associated with the TRV Project include both costs
necessitated by the TRV Project and costs related to betterments and operational considerations.
Upon approval of this M&C, the total of these water and sewer program costs will consist of the
following:
Engineering Agreements $ 7,745,913.00
Construction Contracts $15,218,186.20
Construction Staking, Project
Management, Inspection,
Material Testing and
Contingencies $ 2,007,561.63
Project Appropriations------1 $24,971,660.83
FUND Existing Additional Revised Encumbrances Remaining
Appropriations Appropriations Appropriations and Balance
Expenditures
Water $14,026,209.66 $0.00 $14,026,209.66 $13,378,952.17 $647,257.49
Capital
Projects
Fund
P265
Sewer $7,180,938.12 $0.00 $7,180,938.12 $6,966,558.75 $214,379.37
Capital
Projects
Fund
P275
2017 Water $3,206,273.00 $558,240.05 $3,764,513.05 $2,922,723.00 $841,790.05
and Sewer
Revenue
Bonds
Capital
Project
Fund
P266
Project $24,413,420.78 $558,240.05 $24,971,660.83 $23,268,233.92 $1,703,426.91
Total
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer
Fund. Available cash within the Water and Sewer portfolio and the City' s portfolio along with the
appropriation authority authorized under the Direct Purchase Note program will be used to provide
http://apps.cfwnet.org/council_packet/mc review.asp?ID=21167&councildate=7/21/2015 7/24/2015
M&C Review Page 3 of 4
interim financing for this project until debt is issued. To the extent resources other than the Water
and Sewer portfolio are used to provide interim financing, the Water and Sewer Fund will be charged
interest that is equivalent to the overall rate of return being earned by the City portfolio (currently
approximately one percent annually). Should the City' s portfolio not support the liquidity needed to
provide an interim short-term financing source, another funding source will be required, which could
mean issuance of securities under the Direct Purchase Note program or earlier issuance of Water
and Sewer revenue bonds than is currently planned. Once debt associated with this project is sold,
bond proceeds will be used to reimburse the Water and Sewer portfolio and the City' s portfolio in
accordance with the attached Reimbursement Resolution.
In accordance with the provisions of the Financial Management Policy Statements, Staff anticipates
presenting revenue-supported debt issuances to the City Council for consideration within the next
three years. The Financial Management Services Department is currently working with all
departments to ensure that multi-year capital improvements plans are in place. Newly developed and
already existing plans, such as the Water Department's current multi-year capital improvement plan,
will be presented to City Council for review and adoption. If the City Council-adopted plan does not
include issuance of debt for this specific project, the project will be funded from other financing
sources. If the Council-adopted plan calls for debt issuance, that debt must be issued within
approximately three years to provide reimbursement for these expenses. If that does not occur, the
costs will no longer be reimbursable by issuing tax-exempt debt and the funding source will have to
be made whole through other budgetary methods. Adoption of this resolution does not obligate the
City to sell bonds, but preserves the ability to reimburse the City from tax-exempt bond proceeds.
Of the $558,240.05 cost of this change order, the amount of$147,834.00 is necessitated by theTrinity
River Vision (TRV) Project while the remaining amount of$410,406.05 is non-TRV related. Upon
execution of this change order, the City will have met its $26.6 Million commitment to the TRV
Project. TRV related expenditures above the $26.6 Million commitment will be reimbursed by the Tax
Increment Financing District and the Tarrant Regional Water District. Of the $147,834.00 considered
TRV related, the amount of$7,092.02 is in excess of the City's $26.6 Million commitment, and will be
reimbursed upon project completion.
M/WBE OFFICE - S.J. Louis Construction of Texas, Ltd., agrees to maintain its initial MBE
commitment of 14 percent that it made on the original contract and extend and maintain that same
M/WBE commitment of 14 percent to all priors up to and inclusive to this change order No
3. Therefore, S.J. Louis Construction of Texas, Ltd., remains in compliance with the City's M/WBE
Ordinance and attests to its commitment by its signature on the Acceptance of Previous MBE
Commitment form executed by an authorized representative of its company.
This project is located in COUNCIL DISTRICTS 2 and 9, Mapsco 62R, 62U, 62V, 62W, 62X and 62Y.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the 2017 Water and
Sewer Revenue Bonds Capital Project Fund for this contract. Currently available revenue in the 2017
Water and Sewer revenue Bonds Capital Project Fund is $55,654,275.06. Upon approval of the
recommendation, Revenue will be appropriated for use in the project, as follows:
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=21167&councildate=7/21/2015 7/24/2015
M&C Review Page 4 of 4
Available Projected
Fund Appropriation Expenditures Balance
Amount
2017 Water and
Sewer
Revenue Bonds $55,654,275.06 $558,241.00 $55,096,034.06
Capital
Project Fund
After appropriation of the amount of$558,241.00 to the project, the amount of$55,096,034.06 in
available revenue will remain in the 2017 Water and Sewer Revenue Bonds Capital Project Fund.
TO Fund/Account/Centers FROM Fund/Account/Centers
P266 541200 609170096987 $482,508.05
P266 541200 709170096987 $75,732.00
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: John Carman (8246)
Additional Information Contact: Liam Conlon (6824)
ATTACHMENTS
60TRVP3MAINC03-SJL Maps.pdf
http://apps.cfwnet.org/council packet/mc review.asp?ID=21167&councildate=7/21/2015 7/24/2015