Change Order Request
Project Name:1 Water and Sanitary Sewer Replacement Contract 2014-WSM-C City Sec No.: 46253
Project No.(s): P253-609170238483 I DOE No. 1 7310 City Proj.No.: 02348
Project Description: Water Main Replacement Hammond St,Donna St,W.Spurgeon St,May St
Contractorl Tejas Commercial Construction Change Order# 0 Date: 81412015
City Project Mgr.1 Robert Sauceda City Inspector. I Luisa Allbright
Phone Number.1 817-392-2387 Phone Number. 817-223-2259
Dept. Water Sewer Totals Contract Time
(Calender days)
Original Contract Amount $611,335.00 $611,335.00 120
Extras to Date $65,706.00 $65,706.00 080
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $677,041.00 $677,041.00 200
Amount of Proposed Change Order $39,541.15 $39,541.15 010
Revised Contract Amount $716,582.15 $716,582.15 210
Original Funds Available for Change Orders $25,000.00 $25,000.00
Remaining Funds Available for this CO
Additional Funding(if necessary) $39,541.15 J $39,541.15
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1 17.22%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) 1$764,168.75
JUSTIFICATION (REASONS)FOR CHANGE ORDER
The change order will provide for the following pay items need to complete the project:
• Temporary asphalt and concrete pavement repair.
• 8 inch water line, 1 inch water service lines and 8 inch gate valves.
• Concrete driveway removal and replacement.
• Traffic control.
Staff concurs with the contractor's request for 1 dar days on the change order.
ecretary %a g � vOFFICIAL RECORD'
I CITY SECRETARY
It is understood and agreed that the acceptance of this Change Order by the con ractor constitutes an accod arort fi mese is payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Teas Commercial Construction
MDo MEW [late
M _
r s, oc
a __
''
o
M&C Number N(A M&C Date Approved
FQ T WO KF 14 City of Fort Worth
aw Change Order Additions
Project Name I Water and Ta-nitary Sewer Replacement Contract 2014-WSM-C City Sec No.: 46253
Project No.(s): I P253-609170238483 DOE No. 7310 City Proj.No.: 02348
Project Water Main Replacement Hammond St,Donna St,W.Spurgeon St,May St
Description
Contractor Teas Commercial Construction Change Order:® Date: 8/4/2015
City Project Mgr. Robert Sauceda City Inspector Luisa Albright
ADDITIONS
DEPT Oty Un
1 8"PVC Water Pipe Water 52.00 LF $33.00 $1,716.00
3 8"Gate Valve Water 4.00 EA $1,200.00 $4,800.00
4 6"Gate Valve Water 1.00 EA $1,000.00 $1,000.00
7 Fire Hydrant Water 1.00 EA $3,000.00 $3,000.00
8 1"Water Service Meter Relocation Water 12.00 EA $250.00 $3,000.00
9 1"Water Service Water 10.00 EA $925.00 $9,250.00
10 1"Private Service Water 116.00 LF $30.00 $3,480.00
18 Temporary Asphalt repair Water 4,279.13 LF $9.00 $38,512.17
20 7"Concrete pavement repair Water 20.54 SY J$85.00 $1,745.90
25 Exploratory Excavation of Utilities Water 8.00 EA 1$1,200.00 $9,600.00
29 6"DR 14 PVC Pipe Water 39.00 LF $30.00 $1,170.00
34 Remove Driveway Water 116.00 SF $2.35 $272.60
37 6"Concrete Driveway Water 96.00 SF $6.00 $576.00
16 Salvage 3/4 Water Meter Water 9.00 EA $75.00 $675.00
26 Traffic Control Water 2.00 LS $1,500.00 $31000.00
OFFIC AL R CORD
FTWORTIJIT
Water $81,797.67
Sewer
Page 2 of 4 Additions Sub Total 1$81,797.67
FBR-r WO RT H City of Fort Worth
Change Order Deletions
Project Name Water and Sanitary Sewer Replacement Contract 2014-WSM-C City Sec No.: 46253
Project No.(s): P253-609170238483 DOE No. 7310 City Proj.No.: 02348
Project Description Water Main Replacement Hammond St,Donna St,W.Spurgeon St,May St
Contractor Tejas Commercial Construction Change Order: Date 8/4/2015
City Project Mgr. Robert Sauceda City Inspector: Luisa Allbright
DELETIONS
ITEM DESCR MON CIEP'71' til► Uink cost TOW
5 Concrete Collar Water 16.00 EA $150.00 $2,400.00
6 Ductile Iron Fittings Water 0.85 TN $4,800.00 $4,080.00
15 Connecting to Existing 6'8'water main Water 1.00 EA $950.00 $950.00
21 ITemporary Asphalt sidewalk Water 150.00 SF $7.00 $1,050.00
22 Asphalt curb and gutter Water 57.80 LF $7.00 $404.60
23 Temporary Asphalt Driveway Water 1,125.00 CY $5.00 $5,625.00
27 Asphalt permanent Repair Water 339.22 LF $49.00 $16,621.78
31 Flowable fill Water 89.00 CY $97.00 $8,633.00
32 Haul Off Water 89.00 CY $5.50 $489.50
33 Excavation Water 89.00 CY $6.00 $534.00
35 Remove 4'Concrete Sidewalk Water 51.20 SF $2.20 $112.64
36 Replace 4'Concrete Sidewalk Water 51.20 ISF $5.00 $256.00
38 Concrete Driveway Exposed aggregate Water 100.00 ISF $11.00 $1,100.00
I CITY
SE RETARY
Water $42,256.52
Sewer
Page 3 of 4 IDeletions Sub Total 1$42,256.52
d7'iGPW JhO io vii-,j
Ah
' ��"�"/��I.l�[..��' ��i CW�'�S�M �J lyA'�A.�a.IIJ�4����+za91A r• '��'"�I !'i'�
tA
.�.,��G 9 ��6�. y! ^---- a `ani ia-=i 'S�"I�{•� --`
60%F1Y ]aw.
l i
76 4G,LAI
i
M
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00