HomeMy WebLinkAboutIR 7547 INFORMAL REPORT TO CITY C%,JNCIL MEMBERS No. 7547
�•""^fa Septc=nber 3, 1991
� To the Mayor and Members of the City Council
�EfORT�o
4
'rexay=
Subject: CENTRAL LIBRARY EXPANSION PROJECT
1073
In the 1986 Capital Improvement Program bond election, $5,600,000 was
Included for the expansion of the Central Library. After the bonds were approved
by the voters, it was determined that if the Library was expanded by the amount
of the approved bonds the size of the expanded Library would be outgrown within
ten to fifteen years. The design of the limited expansion would have prohibited
additional expansion.
Additionally, other -needs which could be designed into the expansion were
identified. These needs included a Heritage Center, a cable television studio and
a parking garage. Major water infiltration problems in the current building were
also identified. The City Council concurred to proceed with the design of the
expansion project including the new elements. The sources of funds identified to
underwrite the cost of these new elements included cable funds, revenue bonds,
capital reserves account, and private funds. (Original plan in the attachment)
The design of the expanded structure included a parking garage, ground level
housing of the cable television studio, the Business and Technology Center floor,
the Heritage Center floor and the capacity to add two.floors for future needs. A
citizens committee was appointed by the Mayor to raise$3,000,000 from private
donations for the Heritage Center to complete the funding for the project. After
a lengthy effort, the committee was unable to raise the necessary funds. The lack
of funds from private donations prohibited the project from being constructed.
Although the expansion of the Library can be delayed, the water infiltration
problem continues to deteriorate the building. The further postponement of
solving this problem will increase damage to the existing building and corrrective
costs. The estimated cost to correct this water infiltration problem alone is
$1,500,000. This does not include$500,000 needed to repair the streets around
the Library to ensure that water infiltration does not occur from the streets.
(Optional plan of the attachment) If only the water infiltration is addressed, this
work would have to be penetrated and the work redone when the expansion work
is initiated. The inclusion of only the correction of the water infiltration problem
in a construction project would prohibit the use of funds from the sale of capital
Improvement bonds. Therefore, a new source of funds would have to be identified
to correct the water infiltration.
City staff reviewed the expansion project with the City Council at the May 7,
1991, Pre-Council session. Staff presented a recommended program of work for
a revised Phase I that would primarily address construction work to the ground
floor level required for the future expansion as well as the water infiltration
problem. (Current plan of the attachment) The implementation of this plan 1; L RFS -
C1'1 Y
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS ----�
INFORMAL REPORT TO CITY C-JNCIL MEMBERS No. 7547
yam,,f R? ember 3, 1991
O'R�TTo the Mayor'and Members of the City Council
u s
irEXAy Subject: CENTRAL LIBRARY EXPANSION PROJECT
allow the use of bond funds for the cost of Phase I. The City Council informally
agreed with the staff to proceed toward construction of $3,550,000 of
improvements to the existing facility and preparatory work for future expansion.
Before any renovation or construction work can occur, it will be necessary to
conduct an environmental assessment. A written report will be prepared that will
Identify potential problem areas, establish priorities,recommend remedial actions,
and develop specifications for work that may be necessary at this time. This work
was not a part of the original contract, and the architect has proposed to provide
the additional services for a fee of$10,000. This amendment would increase the
architectural contract to $840,500.
Bond funds in the amount of $3,590,000 would be used for Phase I. The
remaining bond funds approved in 1986 would remain unsold until a subsequent
bond election provides additional funds for the remaining phases of the expansion
project.
Further Council action will be required in the months ahead to close Lamar Street
and to award contracts for street work and construction.
If the City Council concurs with this recommendation, staff will place on next
week's City Council agenda the appropriate M&C authorizing the City Manager
to amend the current contract with the architect of the project. The sale of the
necessary bonds would occur in November or December of this year.
Should the Council require further information, please let me know.
David Ivory
City Manager
till V,
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
FORT WORTH PUBLIC LIBRARY
CENTRAL EXPANSION
ORIGINAL PLAN
Cable Studio $1,000,000 Cable Contract
Parking Garage 2,199,748 Revenue Bonds
To contain approximately 221 parking spaces
Library 10,076,177 CIP G.O. Bonds &
Capital Reserve
Correct water infiltration, reconstruct streets, construct two
library floors and finish one out--Heritage Center finish
out not included. Each floor averages 76,000 square feet.
TOTAL $13,278,925
CURRENT PLAN
Phase I $ 3,590,000 CIP G.O. Bonds
Correct water infiltration and all underground work for Library
expansion, including street reconstruction.
Phase II $ 9,510,000 CIP G X. Bonds
Construction of structure, completion of Business & Technology
and Heritage Center floors, & the parking garage.
Cable Studio will not be included.
Phase III $ 7,423,000 CIP G.O. Bonds
Completion of Humanities and Social Sciences floors.
TOTAL $20,523,000
OPTIONAL PLAN
Correct water Infiltration $1,500,000 Undetermined
Replace membrane, reroof existing Plaza building, and replace
damaged ceiling. This does not include any street work which
would add $500,000 to the budget. CIP G.O. Bond funds cannot
be used for this work.
FUNDING
1. Source of Funds
a. CIP G.O. Bond money $5,600,000 T
b. Tandy money 375,000 OFFICIAL. .RECORD
c. Street funds 275,000
$6,250,000 RR RY
2. Expenditures to date 875,000 CITY SES,, i ,
J. Balance of funds currently availabe $5,375,000 " jin•
4. Balance of funds available after Phase I $1,785,000 -"
5. Additional funds needed for Phase II $7,725,000
6. Additional funds needed for Phases II & III $15,148,000