FORT WORTH. City of Fort Worth
Change Order Request
Project Namel 2008 CIP Neighborhood Street Project 3A City Sec# 1 43995
Client Project#(s)l #01275-DOE#6169
Change Order Submittal# Date 8/21/2015
Dept. TPW Water Sewer Totals Contract Time CD
Original Contract Amount $941,936.40 $127,695.00 $219,754.00 $1,289,385.40 270
Extras to Date $164,242.00 $10,700.00 $174,942.00 75
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $941,936.40 $291,937.00 ;$230,454.00 $1,464,327.40 345
Amount of Proposed Change Order $15,560.78 $0.00 10.00 $15,560.78 192
Revised Contract Amount $957,497.18 $291,937.00 $230;454.00 $1,479,888.18 537
Original Funds Available for Change Orders $47,096.82 $6,384.75 $10,987.70 $64,469.27
Remaining Funds Available for this CO $47;096.82 $0.00 $287.70 $47,384.52
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 14.77%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $1,611,731.75
x,. .,,,,, ,gym erS ' I ,' ., „":'':�.8 uo�, Y➢ , s. .� " 9
This change order accounts for overruns to existing pay items and the addition of new pay items necessary to complete the project. The prices
for the new pay items are fair and reasonable. Additionally,contract time has been added to accommodate for delays and remobilizations due
to unforeseen gas and water line conflicts.
,?94�
Oct
p C
0
#ie�etary
CITY SECRE"FAR"V
F KITH, IM
FORTWORTH City of Fort Worth
Change Order Additions
Project Name 2008 CIP Neighborhood Street Project 3A City Sec# 43995
Client Project# #01275-DOE#6169
Change Order Submittal# F-T] Date 8/2112015
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
UNIT II:PAVING IMPROVEMENTS 0.00 0.00
1-INCR 0241.0100 Remove Sidewalk TPW 1,103.00 SF 0.50 55 .5
3-INCR 0241.0401 Remove Concrete Drive TPW 375.00 SF $050------ff8-7-57
5-INCR 0241.1300 Remove Conc Curb&Gutter TPW 167.501 LF $1.00 $167.50
6-INCR 0241.1400 Remove Conc Valley Gutter TPW 68.00 SY $9.00 $612.00
14-INCR 3212.0401 HMAC Transition TPW 31.23 TN 150.00 .5
15-INCR 3213.0102 T'Conc Pvmt TPW 13.50 SY 33.65 5 .
16-INCR 3213.0301 4"Conc Sidewalk TPW 725.00 SF 4.00
18-INCR 3213.0401 6"Concrete Driveway TPW 2,803.00 SF 5.00 , 5.
22-INCR 3216.0102 T'Conc Curb and Gutter TPW 97.50 LF $25.00 $2,437.50
28-INCR 3305.0111 Valve Box Adjustment TPW 5.00 LF 300.00 $1,500.00
33-INCR 9999.0000 Utility Adjustment TPW 0.04 LS $10,000.0 0
34-INCR 9999.0000 Meter Box Adjustment TPW 37.00 EA 35.00 5.
35-NEW 9999.0000 Variable Height Sidewalk Curb TPW 103.00 LF 15.00 5 5.
36-NEW 9999.0000 Adjust Sanitary Sewer Cleanouts TPW 8.00 EA 200.00 6
37-NEW 9999.0000 Extra Depth Driveway Removals by Flatwork Crew TPW 1,090.00 SF 1.50 ,6 5.
TPW $33,964.78
Water $0.00
Sewer $0.00
Sub Total Additions $33,964.781
Change Order Additions Page 1 of 1
Foa_ _H City of Fort Worth
Change Order Deletions
Project Name 2008 CIP Neighborhood Street Project 3A City Sec# 43995
Client Project# #01275-DOE#6169
Change Order Submittal# 0 Date 8/21/2015
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
UNIT II:PAVING IMPROVEMENTS
2-DECR 0241.0200 Remove Step TPW 60.00 SF $5.00 3 .
4-DECR 0241.0600 Remove Wall<4' TPW 25.00 LF 5.00 57
8-DECR 0241.4001 Remove 10'Curb Inlet TPW 4.00 EA 750.00 3,
12-DECR 3211.0400 Lime TPW 2.72 TN T150.00
13-DECR 3211.0502 8"Lime Treatment TPW 122.001 SY $2.00 $244.00
17-DECR 9999.0000 6"Concrete Step TPW 110.00 SF 10.00
23-DECR 3232.0100 Conc Ret Wall with Side TPW 50.00 SF 35.00 ,75 .
24-DECR 3291.0100 Topsoil TPW 107.00 CY 16.00 .7
25-DECR 3301.0002 Post-CCTV Inspection TPW 33.00 LF 5.00 5.
30-DECR 3349.5001 10'Curb Inlet TPW 4.00 EA 2,400.00
TPW $18,404.00
Water $0.00
Sewer $0.00
Sub Total Deletions $18,404.001
Change Order Deletions Page 1 of 1
M/SBE Breakdown for this Change Order
M/SBE Sub Type of Service Amount for this CO
N/A
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
One 7/18/2013 $500.00
Two 2/19/2014 $4,000.00
Total $4,500.00
CFW Change Order Approval St-COApp03 Page 2 of 3
FORT WORTH. C'ty of Fort Worth
Change Order Request Approval
(Change Order Breakdown Available in Links)
For Change Order Submittal No.: 3
Change Order No.: St-COApp03 Date Started: ,2015-08-24
City Sec. No.: Date Due: 2015-10-13
Project Name: Davenport Ave Winified Ave - 2008 CIP 3A
Project Numbers: 01275 "DOE Numbers:
DOE 6169
Project 2008 CIP Neighborhood Street Project 3A
Description:
Project Manager: Roy Teal City Inspector: Ariel Duarte
Contractor: Stabile & Winn, Inc.
COUNCIL ACTION (If Required):
M&C Log Name:
M&C Number: M&C Date:
COST AND DAYS SUMMARY:
Requested
Department: Cost($) Fund Account Center: Days:
TPW $ 15,560.78 C204541200203400127583 192
Total Cost: $ 15,560.78 Total Requested Days: '192
Approval Status:
https://projectpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?Siteld=51500&Processld... 9/3/2015
CFW Change Order Approval St-COApp03 Page 3 of 3
Approved: Yes
Comments:
User: Tara Fishback
Date: 2015-08-27 10:58 AM
Approved: Yes
Comments:
User: Jerry Henderson
Date: 2015-08-28 8:26 AM
;Approved: Yes
Comments:
User: Gopal Sahu
Date: 2015-08-28 2:35 PM
Approved: Yes
Comments:
User: Najib Fares
Date: 2015-08-31 7:43 AM
Approved: Yes
Comments: See Attached Comments
User: Andy Anderson
Date: 2015-09-03 8:32 AM
Approved: Yes
Comments:
User: Doug Wiersig
Date: 2015-09-03 10:11 AM
Approved: Yes
Comments:
User: Doug Black
Date: 2015-09-03 10:24 AM
Approved: Yes
Comments:
User: Jay Chapa
Date: 2015-09-03 10:53 AM
Action Required:
https://projeetpoint.buzzsaw.com/ bz web/Forms/FormPrint.aspx?SiteId=51500&ProcessId... 9/3/2015
CFW Change Order Approval St-COApp03 Page 1 of 3
Routing
Assigned To: Due Date:
Assigned By: Due Time:
Links 1
fortworthgov/Infrastructure Proiects/01275 - Davenport Ave Winified Ave - 2008 CIP 3A/Contractor/Change
Orders/Change Order 3 REVISED Breakdown - FinaLxls