Loading...
HomeMy WebLinkAboutOrdinance 16542-08-2005Ordinance No lC~~-~ -o~~~'- AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE WATER CAPITAL PROJECT FUND IN THE AMOUNT OF $400 000 FROM AVAILABLE FUNDS FOR THE PURPOSE OF FUNDING THE EXECUTION OF A RENEWAL OF A CONTRACT WITH WESTHILL CONSTRUCTION, INC FOR UTILITY CUT REPAIR CONTRACT 2005 (M&C C-20662, CITY SECRETARY CONTRACT NO 31859); MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE. BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH TEXAS SECTION 1 That in addition to those amounts allocated to the various City departments for Fiscal Year 2004-2005 and in the Budget of the City Manager there shall also be increased estimated receipts and appropriations in the Water Capital Project Fund in the amount of $400 000 from available funds for the purpose of funding the execution of a renewal of a contract with Westhill Construction, Inc. for Utility Cut Repair Contract 2005 (M&C C-20662, City Secretary Contract No 31859). SECTION 2. That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect. SECTION 3. That this ordinance shall be cumulative of Ordinance No. 16061 and all other ordinances and appropriations amending the same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed. SECTION 4 ADOPTED AND EFFECTIVE. ~~ c~S ~ 9J a4~.S This ordinance shall take effect upon adoption. City of Fort Worth, Texas Mayor and Council Communication COUNCIL ACTION Approved on 8/9/2005 Ordinance No 16542-08-2005 DATE Tuesday August 09 2005 LOG NAME 30WESTHILLRENEW REFERENCE NO *C-20900 SUBJECT Adopt Appropriation Ordinance and Authorize Renewal of Contract with Westhill Construction Inc. for Utility Cut Repair Contract 2005 RECOMMENDATION It is recommended that the City Council 1 Authorize the transfer from the Water and Sewer Operating Fund to the Water Capital Project Fund in the amount of $400 000 00• 2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water Capital Projects Fund in the amount of $400000 00 from available funds, and 3 Authorize the City Manager to execute the second renewal of a contract with Westhill Construction Inc. in the total sum amount of $400 000 00 365 calendar days for Utility Cut Repair Contract 2005 revising the total contract to $1,200 000 00 DISCUSSION On April 19 2005 (M&C C-20662) the City Council authorized the award of a contract in the amount of $400 000 00 with the option of three renewals to Westhill Construction Inc. for Utility Cut Repair Contract 2005 On July 26 2005 (M&C C-20877) the City Council authorized the first renewal of the original contract. As a result of several sizeable utility main breaks and repairs throughout the City (Miller Street, West Cleburne Road Beach Sreet, Clear Lake Road Walton Avenue) the initial contract and first renewal funds have been depleted therefore the Water Department wishes to exercise the second of three options at this time as a means in keeping up with and ensuring the funding of the ongoing and future utility repairs. The work to be performed under this contract consists of utility cut street repairs, which are necessary after main replacements and repairs are made by the Water Department's Field Operations crews. The Water Department is not staffed or equipped to deal with some of the larger repairs. This contract is necessary to maintain a reasonable repair schedule minimize disruption to the motoring public and ensure the street repairs do not adversely impact the life of the remaining street. Westhill Construction Inc. is in compliance with the City's MMBE Policy by committing to 20% M/WBE participation on this renewal option The City's goal for this project is 18% This contract is located in All Council Districts. Logname 30WESTHILLRENEW Page 1 of 2 FISCAL INFORMATION/CERTIFICATION The Director of Fiscal Services certifies that upon approval and completion of recommendation 1 and the adoption of the appropriation ordinance funds required will be available in the current capital budgets as appropriated of the Water Capital Projects Fund TO Fund/Account/Centers FROM Fund/Account/Centers 1&2)P264 472045 601170013500 $400,000.00 1)PE45 538070 0609020 $400.000.00 2)P264 541200 601170013583 $400.000.00 3)P264 541200 601170013583 $400.000.00 Submitted for City Manager's Office by' Marc Ott (8476) Originating Department Head A. Douglas Rademaker (6157) Additional Information Contact: A. Douglas Rademaker (6157) Logname 30WESTHILLRENEW Page 2 of 2