HomeMy WebLinkAboutOrdinance 16646-10-2005Ordinance No # ~ ~~/~i °';~~~~5
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN
THE WATER CAPITAL PROJECT FUND IN THE AMOUNT OF $100180 FROM
AVAILABLE FUNDS FOR THE PURPOSE OF FUNDING COOPER GENERAL
CONTRACTORS FOR THE JENKINS HEIGHTS PUMP STATION REHABILITATION
PROJECT MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES IN
CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS
SECTION 1
That in addition to those amounts allocated to the various City departments for Fiscal Year 2004-2005 in the
Budget of the City Manager there shall also be increased estimated receipts and appropriations in the
Water Capital Project Fund in the amount of $100 180 from available funds for the purpose of funding
Cooper General Contractors for the Jenkins Heights Pump Station Rehabilitation Project.
SECTION 2
That should any portion, section or part of a section of this ordinance be declared invalid inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No 16061 and all other ordinances and appropriations
amending the same except in those instances where the provisions of this ordinance are in direct conflict
with such other ordinances and appropriations, in which instance said conflicting provisions of said prior
ordinances and appropriations are hereby expressly repealed.
SECTION 4
This ordinance shall take effect upon adoption
AS Tj~ FO~bI'/~ND LEGALITY
ADOPTED AND EFFECTIVE. ~(~ ~j,(L,1- ~ I ,~
City of Fort Worth, Texas
Mayor and Council Communication
SUBJECT
Adopt Appropriation Ordinances and Authorize Execution of Contract with G P Cooper Industries
Inc d/b/a Cooper General Contractors for the Jenkins Heights Pump Station Rehabilitation Project
RECOMMENDATION
It is recommended that the City Council
1 Adopt the attached appropriation ordinance increasing estimated receipts and appropriation in the Water
Capital Project Fund in the amount of $461 820 00 from Impact Fees,
2. Authorize the transfer of $461 820 00 from the Water Capital Project Fund-Impact Fee to the Water
Capital Project Fund
3 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water Capital Project Fund in the amount of $461 820 00 from available funds,
4 Authorize the transfer of $100 180 00 from the Water and Sewer Operating Fund to the Water Capital
Project Fund
5 Adopt the attached appropriation ordinance increasing estimated receipts and appropriation in the Water
Capital Project Fund in the amount of $100 180 00 from available funds, and
6 Authorize the City Manager to execute a contract with G P Cooper Industries, Inc. d/b/a Cooper
General Contractors in the amount of $537 000 00 for the Jenkins Heights Pump Station Rehabilitation
Project.
DISCUSSION
The Jenkins Heights pump station was constructed in the 1960's, with a rated capacity of 2 5 million
gallons per day The water master plan recommends expanding this pump station to 5 million gallons per
day firm pumping capacity
The scope of work within this construction contract is to replace aged electrical switchgear install larger
pumps and motors, replace piping valves and fittings, replace meter and meter vault, add a handicap
ramp landscaping and larger parking area.
The project was advertised for Bid in the Commercial Recorder on August 11 and August 18 2005 On
September 15 2005 the following bids were received
BIDDER TOTAL BID CONTRACT TIME
Logname• 60JENKINS Page 1 of 2
Cooper General Contractors
Steve Dake Construction
$537 000 00 180 Calendar Days
$611 110 00
In addition to the contract cost, $25 000 is provided for project contingencies.
This project is located in COUNCIL DISTRICT 7
G P Cooper Industries, Inc. d/b/a Cooper General Contractors, is in compliance with the City's M/WBE
Ordinance by committing to 22% M/WBE participation The City's goal on this project is 18%
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of the above recommendations and the
adoption of the attached appropriation ordinances, funds will be available in the 2004-05 capital budget, as
appropriated of the Water Capital Projects Fund
TO Fund/Account/Centers
2&3) P164 472045 060164016001 $461,820.00
3) P 164 541200 060164016001 $461.820.00
4 ~ 5) P164 472045 060164016001 $100.180.00
5) P164 541200 060164016001 $100.180.00
1) PW53 488023 060530200050 $461.820.00
FROM Fund/Account/Centers
2) PW53 538040 060530200050
4) PE45 538070 0609020
6) P164 541200 060164016001
$461,820.00
$100.180.00
$537,000.00
Submitted for City Manager's Office b~. Marc Ott (8476)
Originatina Department Head S Frank Crumb (8207)
Additional Information Contact: S Frank Crumb (8207)
Logname 60JENKINS