HomeMy WebLinkAboutOrdinance 16647-10-2005Ordinance No ~G 7~°/~ ~b~
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE SEWER CAPITAL PROJECT FUND IN THE
AMOUNT OF $157 620 FROM AVAILABLE FUNDS FOR THE PURPOSE OF
FUNDING A CONTRACT WITH COOPER GENERAL CONTRACTORS FOR THE
MEADOW LAKES LIFT STATION PROJECT MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES IN CONFLICT HEREWITH; AND
PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH
TEXAS
SECTION 1
That in addition to those amounts allocated to the various City departments for Fiscal Year 2005-
2006 in the Budget of the City Manager there shall also be increased estimated receipts and
appropriations in the Sewer Capital Project Fund in the amount of $157 620 from available funds
for the purpose of funding a contract with Cooper General Contractors for the Meadow Lakes Lift
Station Project.
SECTION 2
That should any portion, section or part of a section of this ordinance be declared invalid,
inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or
judgment shall in no way impair the remaining portions, sections, or parts of sections of this
ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No 16582 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance
are in direct conflict with such other ordinances and appropriations, in which instance said
conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed
SECTION 4
ADOPTED AND EFFECTIVE. V C~~~.C.L'~=~-J' ~~ ~ ~~~`~~S
This ordinance shall take effect upon adoption
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION Approved on 10/11/2005 Ordinance No 16647 10-2005
DATE Tuesday October 11 2005
LOG NAME 60MEADOW LAKES
REFERENCE NO *C-21081
SUBJECT
Adopt Appropriation Ordinance and Authorize Execution of a Contract with G P Cooper Industries
Inc d/b/a Cooper General Contractors for the Meadow Lakes Lift Station Project
RECOMMENDATION
It is recommended that the City Council
1 Authorize the transfer of $157 620 00 from the Retail Sewer Impact Fee to the Sewer Capital Project
Funds
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriation in the
Sewer Capital Project Fund in the amount of $157 620 00 from available funds and
3 Authorize the City Manager to execute a contract with G P Cooper Industries, Inc d/b/a Cooper
General Contractors in the amount of $617 000 00 for the Meadow Lakes Lift Station Project.
DISCUSSION
Due to terrain gravity wastewater service is not available to the proposed 70-acre Meadow Lakes
Addition The Meadow Lakes Addition is generally bound by Hodgkins Road to the west, Lakeside Street
to the south St. Thomas Place to the east and undeveloped land to the north Under this project, Cooper
General Contractors will install a wastewater lift station to serve the area discharging into a proposed 6"
diameter wastewater force main being constructed with the Meadow Lakes Addition
The Meadow Lakes Addition developer MKP and Associates, Inc. has contributed $250 000 00 towards
their share of the construction cost of the Meadow Lakes Lift Station along with the dedication of the lift
station site to the City
The project was advertised for Bid in the Commercial Recorder on July 21 and July 28 2005 On August
25 2005 the following bids were received
BIDDER TOTAL BID CONTRACT TIME
Cooper General Contractors $617 000 00 180 Calendar Days
North Texas Contracting $626 945 00
Steve Dake Construction $675 035 00
Red River Construction $693 330 00
Holloman Corporation $835 772.66
In addition to the contract cost, $25 000 is provided for project contingencies.
Logname 60MEADOW LAKES Page 1 of 2
This project is located in COUNCIL DISTRICT 7
Cooper General Contractors Inc. is in compliance with the City's M/V1/BE Ordinance by committing to 24%
M/WBE participation The City's goal on this project is 23%
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon adoption of the attached appropriation ordinance funds are
available in the current capital budget, as appropriated of the Sewer Capital Projects Fund
TO Fund/Account/Centers FROM Fund/AccountlCenters
1&2) P174 472058 070174013141 $157,620.00 1) PS58 .538040 070580200050 $157,620.00
2) P174 541200 070174013141 $157,620.00 3) P174 541200 070174013141 $617,000.00
Submitted for City Manager's Office b~ Marc Ott (8476)
Originating Department Head. S Frank Crumb (8207)
Additional Information Contact: S Frank Crumb (8207)
Logname 60MEADOW LAKES Page 2 of 2