HomeMy WebLinkAboutContract 36324-A7 AMENDMENT No. 7
y TO CITY SECRETARY CONTRACT
WHEREAS, the City of Fort Worth (CITY) and Kimley-Horn
and Associates, Inc. , (ENGINEER) made and entered into City
Secretary Contract No. 36324, (the CONTRACT) which was
authorized by M&C C-22555 on the 4th day of December, 2007 in
the amount of $251,355 . 00; and
WHEREAS, the CONTRACT was subsequently revised by:
Amendment Number 1 in the amount of $138, 730 . 00 which was
authorized by M&C C-25028 on July 19, 2011, Amendment No. 2 in
the amount of $49, 600 . 00 which was administratively authorized
on August 23, 2012 , Amendment No. 3 in the amount of
$27 ,000 . 00 which was administratively authorized on December
6, 2012 , Amendment No. 4 in the amount of $48,300 . 00 which was
administratively authorized on July 24, 2013, Amendment No.5
in the amount of $41, 700 . 00 which was administratively
authorized on January 6, 2014 and Amendment No. 6 in the amount
of $35,000 . 00 which was administratively authorized on
February 26, 2015; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
Water and Sanitary Sewer Relocations for State Highway
121T, Part 3; and
ER , it has become necessary to execute Amendment
No. 7 to the CONTRACT to include an increased scope of work and
revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the
additional engineering services specified in a proposal dated
September 17, 2015, a copy of which is attached hereto and
incorporated herein. The cost to City for the additional
design services to be performed by Engineer totals $38,300 . 00 .
2 .
Article II of the CONTRACT is amended to provide for an
increase in the fee to be paid to Engineer for all work`°`"`"and` "
services performed under the Contract, as amended, so RECORD
COT Y +a
Page -1- E a 9 v %."('� "T"X
total fee paid by the City for all work and services shall be
an amount of $629, 985.00 .
3 .
All other provisions of the Contract, which are not
expressly amended herein, shall remain in full force and
effect.
EXECUTED and EFFECTIVE as of the date last written by a
signatory, below.
APPROVED: ENGINEER
City of Fort Worth Kimley-Horn and Associates,Inc.
Jesus J. Chapa Glenn A Gary, P.E.
Assistant City Manager Senior Vice-President
DATE: DATE:
APPROVAL RECOMMENDED:
Andrew T. Cronber . P.E.
Assistant Directo!)Water Department
APPROVED AS TO FORM AND LEGALITY: M&C: N/A
Date: N/A
I'll wzm�a
Douglas W. Black
Senior Assistant City Attorney
ATTEST:
Mary 571,, Y e 1.,, � � f �� g,'C� ,4��e& n ` f �y V�� r. 7,kHm RE'V)H'D�
7r
City S, crettry
CITY
R,,,t,,T H, TX
Page
i >>
September 17, 2015
Mr. Liam Conlon
Project Manager
City of Fort Worth Water Department
1000 Throckmorton Street
Fort Worth, TX 76102
Re: Water and Sanitary Sewer Relocations for SH-121T (Southwest Parkway), Part 3
Additional Services—Amendment No. 7
KHA No. 061018049
City Project No. 00899
Dear Liam:
This is an amendment to a contract between Kimley-Horn and Associates, Inc. and the City of Fort
Worth ("the City") dated 12-19-2007 referred to herein as the"Contract".
This amendment will provide for Additional Construction Phase Services as indicated below:
ITT 1 (CONSTRUCTION PHASE SERVICES): $38,300Kimley-born
(Water$0, Serer$38,300)
Kimley-Horn will provide additional construction phase services as defined in the Contract Exhibit"A-
1" Part D—Construction Phase Services including:
• Review up to 25 Additional Shop Drawings
• Attend up to 12 Additional Progress Meetings and Prepare Meeting Notes
• Perform up to 10 Additional Site Observations
• Provide clarification for up to 4 Contractor Requests for Information (RFI)
We recommend that the City increase the budget by$38,300 for these additional services. From the
additional services listed above, the recommended breakdown for water and sewer services is as
follows:
Description Water Sewer Total
Item 1 —Construction Phase $38,300 $0 $38,300
Services
Total $38,300 $0 $38,300
Kimley)))Horn Page 2
The following table summarizes the fee per Work Phase:
Total
Work Phase Water Fee Sewer Fee Fee
31 $0 $0 $0
32 $0 $0 $0
33 $38,300 $0 $38,300
51 $0 $0 $0
Total $38,300 $0 $38,300
The following table summarizes our recommended budget revisions by Item (please see attached
Fee Breakdown for an hourly breakdown of each item):
Description Item 1 Total
Pre-Engineering $0 $0
Conceptual Engineering $0 $0
Preliminary Construction $0 $0
Plans
Final Construction Plans $0 $0
Pre-Construction $0 $0
Services
Construction Phase
$38,300 $38,300
Services
Total $38,300 $38,300
Kimley)))Horn Page 3
The following table summarizes our recommended budget revisions and shows the revised contract
amount:
Original Amend Amend Amend Amend Amend Amend Amend Revised
Description Fee No. 1 No. 2 No. 3 No. 4 No. 5 No. 6 No. 7 Contract
Pre-Engineering $35,900 $35,400 $5,200 $4,800 $81,300
Conceptual $62,980 $8,900
$71,880
Engineering
Preliminary
Construction $49,665 $32,130 $81,795
Plans
Final
Construction $85,010 $46,300 $44,400 $43,200 $ 18,600 $237,510
Plans
Pre-
Construction $3,600 $5,000 $ 5,100 $13,700
Services
Construction $14,200 $11,000 $22,200 $23,100 $35,000 $38,300 $143,800
Phase Services
Total Project $251,355 $138,730 $49,600 $27,000 $48,300 $41,700 $35,000 $38,300 $629,985
No additional M/WBE participation is proposed for this amendment
Total Contract
Description Per Amend No. 6
Contract Amount $591,685
Total Contract M/WBE $93,840
Total Contract M/WBE 15.8%
Percentage
MIMMMI=oil=
KimlepMorn Page 4
The following table summarizes our revisions to the water and sanitary sewer design fees:
Description Original Amend. Amend. Amend. Amend. Amend. Amend. Amend. Total
No. 1 No.2 No.3 No.4 No. 5 No.6 No.7
Water $133,377 $108,695 $36,300 $0 $0 $0 $0 $38,300 $316,672
Sewer $117,978 $30,035 $1.3,300 $27,000 $48,300 $41,700 $35,000 $0 $313,313
We appreciate the opportunity to be of continued service to the City. Please contact us if we need to
provide any further information.
Very truly yours,
KIMLEY-HORN AND ASSOCIATES, INC
Glenn A. Gary, P.E.
Sr. Vice President