HomeMy WebLinkAboutIR 7749 INFORMAL REPORT TO C COUNCIL MEMBERS No 7749 August 3, 1993 mt SOR�4 To the Mayor and Members of the City Council CP 0 ti P e V = Subject: •T,x,y RESPONSE TO REQUEST FROM THE FORT WORTH PUBLIC LIBRARY FOUNDATION ORIGINAL PROJECT On March 22, 1986,voters approved a Capital Improvement Program that included $5,600,000 to expand the Central Library. On January 12, 1988,the City Council approved the hiring of the O'Brien Partnership as the architect for the expansion project (M&C C-10738). On March 24, 1988, the City Council approved the hiring of Rone Engineers to provide geotechnical and testing services (M&C C-10858). In December of 1988, a City Council Committee composed of Council Members Garey Gilley, Estil Vance and Louis Zapata, sent a memo to the full Council outlining the project to include basic library expansion, a parking garage, the Heritage Center, the public access cable television studio, and water infiltration abatement. In that memo,the committee anticipated that the funding would be a combination of I986 Capital Improvement Program bond funds for the library expansion, revenue bonds for the parking garage,private donations for the Heritage Center,and private funding through the agreement with Sammons Cable Television Company for the cable tv studio. The plans were expected to be ready for bid advertisement during the Summer of 1989, provided funding was available. After much design,the total expenditure of$598,000 of the original$5,600,000 and an inability to secure sufficient private donations to complete the Heritage Center,the contract with the O'Brien Partnership was canceled on January 17, 1992. Unfortunately, the problem of water infiltration into the existing library was still at hand. CURRENT PROJECT In February of 1992,Growald Architects was retained by the City Council to design a ground floor shell structure to cover the underground library site, to allow for future expansion of the library utilizing the shell structure and to prevent rain water from entering the existing library. A budget was prepared and Growald Architects was told that all of the work would have to stay within that budget. Through a gift from the Sid Richardson Foundation,the services of David 0. Schwarz,Architects,were provided to assist Growald Architects in preparing a conceptual design. Since then elements have been added and deleted and the planned appearance has gone.through several changes; however, Growald Architects' goal of staying within the budget has not changed. Due to the complexity and the phased construction schedule for this project, the City Council also hired Thos. S. Byrne, Inc., as the construction manager for the project. Thos. S. Byrne, Inc., is providing day- to-day inspection and administration services in conjunction with the architect and the City staff. A summary of the current budget is as follows: nFF�e1�` R1CO�Q Phase 1 (Actual Contract Price) $ 019RLIMY Change Order 1 (Entrance Gates) $ 621 �L Change Order 2 (Security Fence) $ 1,056 e♦• %01% IM Change Order 3 (Temp. Waterproofing) $ 1,319 1"1 ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS ----- INFORMAL REPORT TO C'y COUNCIL MEMBERS No. 7749 August 3, 1993 AWOLex To the Mayor and Members of the City Council Page 2 of 6 Subject: RESPONSE TO REQUEST FROM THE FORT WORTH PUBLIC LIBRARY FOUNDATION Change Order 4 (Misc.) $ 4,799 Total Phase I Change Orders $ 7,795 Phase II (Actual Contract Price) $ 1,921,004 Change Order 1 (Adj. Start Date) $ 0 Change Order 2 (Column Upgrade) $ 150,556 Change Order 3 (Ped. Walkway) $ 1,824 Pending Change Orders (Misc.) $ 105,341 Total Phase 11 Change Orders $ 257,721 Asbestos Abatement (Actual Contract Price) $ 99,000 Joint Sealing (Actual Contract Price) $ 1,200 Phase III(Actual Low Bid Price) $ 2,254,750 Phase Illa (Street & Sidewalk) (Estimate) $ 350,000 Pending CO (Enhanced Fire Protection) $ 63,800 Phase IV (Cable TV Studio) (Estimate) $ 609,000 Cable TV Equipment (Estimate) $ 500,000 Architectural, Engineering, Management, and Testing $ 945,000 Construction Contingencies for Phases III and IV $ 140,000 Available for Enhancements $ 124,730 Total Project Budget $ 7,572,000 The sources of these funds are as follows: Library Bonds (Total Remaining from 1986 CIP) $ 5,002,000 Street Bonds $ 500,000 Cable TV Funds $ 1,700,000 Lamar Street Closure Funds $ 370,000 Total Funds Available $ 7,572,000 The construction of the Library Expansion and Cable TV Studio is being carried out in four phases. Phase I included installation of short extensions to the basement piers in preparation for the structural steel columns. Phase ll includes the structural steel columns, roof system, and parapet wall along with the drainage system to handle the roof and street water. Phase III includes the installation of the exterior walls, and the finish out of the page (library materials handling) area and conference rooms. Phase IIIa is a portion of Phase III that includes street, sidewalk and drainage construction. Staff'decided that it is better to bid Phase IIIc separately. Phase IV provides for the finisli-out of the Cable TV Studio. Construction of Phase I was completed on March 8, 1993. Phase II is under construction with the installation of the grade beam complete, the drainage system virtually complete and structural steel erection underway. Phase II includes three significant change orders. They include the upgrading of the columns to allow for expansion through the third floor and provisions to allow full expansion at some future date, and the addition of a "French" drain system to intercept subsurface water.fbe awarded on June 8 and the contractor expectsto begin site work in early September. WiPRECORD Phases I, II and III, all of the project that is to be paid with bonds approved for the libr ;eETAeyawarded. AIthough some additional change orders can be expected, it is clear that we areL tinfunding available. Phase IIIa (streets) is under design and the construction contract shoISSUED BY THE CITY MANAGER FORTWORTH, TEXAS -- INFORMAL REPORT TO CI7--44 COUNCIL MEMBERS �No. 7749 August 3, 1993 `o�ioa,4 To the Mayor and Members of the City Council Page 3 of 6 0 V = •Tf XPy Subject: '813RESPONSE TO REQUEST FROM THE FORT WORTH PUBLIC LIBRARY FOUNDATION in early October. The funding for Phase IIIc comes from street bonds. Phase IV (cable tv studio) is in final design stages and should be awarded in late September. The funding for Phase IV comes from cable TV studio funds. The construction has been proceeding with no major interruptions or delays. We are reminded of the purpose of the project,to control leakage into the basement level,each time it rains. The contractors have been very cooperative working with staff and the construction manager controlling leaks resulting from installation of the walls and piers. A bit of information pertinent to this discussion is the estimated amount of space available on each floor of the planned library structure. The following is the architect's best estimate: AVAILABLE FLOOR AREA INCREMENTAL CUMULATIVE CUMULATIVE GROSS GROSS NET LIBRARY LIBRARY LIBRARY FLOOR AREA (s.f.) AREA (s.f.) AREA (s.f.) Main Level (Basement) Existing Library 101,200 101,200 81,000 Vault 1,000 102,200 Plaza Level (Ground Floor) Library Uses: Existing Space 18,900 121,100 96,100 Phase III Addition 10,200 131,300 104,200 Service Yard 7,700 139,000 104,200 Future Expansion 42,500 181,500 138,200 79,300 Other Uses: Cable TV Studio (10,400 S.F.) Retail Area (8,200 S.F.) Second Level 42,200 223,700 172,000 Third Level 36,500 260,200 201,200 Fourth Level 36,500 296,700 230,400 Fifth Level 36,500 333,200 259,600 Sixth Level 36,500 369,700 288,800 Seventh Level 36,500 406,200 ale RECORDCRETARYIn 1959, it .vas determined that the Central Library needed 150,000 s.f. to operate proph�i�'. aAs can be seen from the above table, the current library has a total of only 96,100 s.f. rary space. Even by 1959 standards, the present Central Library has insufficient space today. Projections of library usage,population growth and facility needs included in a study of the Fort Worth Library System ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS INFORMAL REPORT TO C}11-v COUNCIL MEMBERS No. 7749 August 3, 1993 qw- PE To the Mayor and Members of the City Council Page 4 of 6 Subject: RESPONSE TO REQUEST FROM THE FORT WORTH PUBLIC LIBRARY FOUNDATION titled "Facilities Long Range Planning Study, 1982-2000" have proven to be very accurate. That study said the Central Library would need 200,000 s.f. of net library space (about 258,000 s.f. gross) by 1990, and 300,000 s.f. of net library space (about 383,000 s.f. gross) between the years 2005 and 2010. The concepts that produced those projections are still valid. Those concepts are: 1. A central library provides materials not cost effectively duplicated at multiple sites, i.e., Genealogy, Business & Technology, Government Documents, etc. 2. Centralized support services and headquarters are necessary for a library system. 3. Although continuing advances in the electronic delivery of information reduces the space needed for storage, new technology adds to and creates the need for additional space to house the technology and to seat new users. There will be a transfer of much information to new formats (video cassettes,compact discs,computerized data bases, etc.)but the need for printed material will continue for the foreseeable future for materials such as popular reading, children's books, art prints, etc. and as the cheapest, most convenient method of individual distribution. 4. Although a branch library is able to stock a variety of materials, a central facility is necessary to provide a depth of materials unavailable in any single branch library due to the limited space available at the branch sites. By having a fully stocked central library,branch libraries can draw from the central library to meet local needs and user demands. The needs and projections included in the 1982 study have not diminished, but have been proven quite accurate. Along with the need to stay within the funding available, every decision that has been made to date has retained the flexibility to expand to the ultimate seven floor configuration with minimal rework. By retaining flexibility today we will undoubtedly avoid the enonnous costs that have recently been experienced by other major cities that are building new central libraries. For example the Denver Central Library is now underway at a cost of about $90,000,000 and San Francisco is building a new central library at a cost of about $125,000,000. Even a small central library in New Haven, Connecticut, is expected to cost over $16,000,000. Based on direction from the City Council at the Pre-Council Meeting of April 20, 1993, and recognizing that funds are not currently available, staff'reviewed the alternatives available for roughing-in the second floor of the Central Library. During that investigation, staff also considered the rough-in construction,of the first floor. The Construction Manager recommends that, if funds can be made available, the rough-in construction of both the first and second floors would be desirable as an additional, separate phase to the project. In order to assess the full costs of using the full first floor, the construction costs for Phasc V (rough i of first and second floors), Phase VI (finish out of the first floor), the furnishing costs, an grataVA costs have been estimated as follows: PHASE V ISSUED BY THE CITY MANAGER — FORT WORTH, TEXAS INFORMAL REPORT TO CITY CuJNCIL MEMBERS No. 7749 l_ August 3, 1993 roc 1041�o To the Mayor and Members of the City Council Page 5of 6 v�s RESPONSE TO REQUEST FROM THE FORT WORTH PUBLIC •rcx�ti Subject: LIBRARY FOUNDATION Construct First Floor, Rough-in Only Construction $ 340,000 Arch., Engr., Mgmt. & Testing $ 51,000 Contingencies $ 20,000 Total First Floor Rough-in $ 411,000 Construct Second Floor, Rough-in Only Construction Structure $ 538,500 Reinforce Columns $ 42,500 Spray Fireproofing $ 55,000 Fire Protection $ 85,000 Fire Exits & Stairs $ 33,000 Minimum HVAC $ 27,500 Add. Lighting, Etc. $ 41,000 Miscellaneous $ 17,500 Construction Total $ 840,000 Arch., Engr., Mgmt. & Testing $ 126,000 Contingencies $ 48,000 Total Second Floor Rough-in $ 1,014,000 TOTAL PHASE V $ 1,425,000 PHASE VI Phase VI Complete First Floor (Funds are to be solicited privately) Construction $ 1,464,000 Furnishings $ 2,000,000 Amenities $ 762,000 A/E, Mgmt, Contingency $ 274,000 TOTAL PHASE VI CAPITAL COSTS $ 4,500,000 OPERATIONAL COSTS Increased Operational Costs for completed first floor areas starting in FY 95-96 (1993 dollars): Moving (First Year) $ 3,000 Personnel $ 61,143 OFFICIAL RECORD Supplies $ 2,000 Telephone leased lines $ 3,000 CITY SECKTARY Automation $ 900 Minor Equipment (first year) $ 2,000 FT.'WORTH. !�Lj Gas $ 3,700 ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS INFORMAL REPORT TO CITY iUNCIL MEMBERS No. 7749 •�., August 3, 1993 �oi1o4,wc To the Mayor and Members of the City Council Page 6 of 6 3O: RESPONSE -TO REQUEST FROM THE FORT WORTH PUBLIC rxP Subject: LIBRARY FOUNDATION Electricity (AC, Heating, $ 72,000 Lighting) Water $ 600 Repairs $ 1.000 TOTAL FIRST YEAR COSTS $ 149,343 TOTAL ANNUAL COSTS, Year 2 and beyond $ 144,343 Protect Schedule In order to proceed with the conceptual design of the final finish of the first floor (Phase VI), the structural and mechanical layout of the first and second floors (Phase V) must be finalized. Once the parameters for the interior envelope have been set, the information will be relayed to the Architect selected by the Library Foundation so he can complete the design concept. Depending on the status of funding, the City Council may approve the preparation of working drawings for Phase V so that the first and second floor can be.installed in preparation for the finish of the first floor. The attached project schedule illustrates the above scenario. The funds for the design of Phase V are available in the present budget. The construction costs for Phase V will have to be allocated from an additional source. When the Library Director and the Library Foundation is satisfied with the interior design and have raised sufficient funds, the Architect would be put under a City Design Contract to prepare the final design documents for Phase VI and assist the City during the finish out. Any delays in approving the amendment to Growald's contract to develop the design parameters for Phase V, in raising of funds, or in authorization of final design of Phase V or Phase VI will cause the final completion date to slip the scheduled completion date. If the City Council would like additional information, it will be furnished upon request. ;r'�—B errrelf 1 City Manager Attachment �aR ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS kNto�l—I iEhllAl 116RART E(FAA510N a CAME LS.510610 Rfsfois:cle As-et Date 25-Jul•03 12:0496 ScWWule File t A:%LDA7-93 93 91 93 96 Dur6ln Start End Jul Aug Seo Oct Nov Dec Jan Feb Nor AT,MAY Jun Jet A" Sep Oct Nov Def Ja9FNMar4rM4pJWnJuIWgSepOltNprW(JanieMar0.prnnJ■nJu lAua5e60c 1No.6fc task Nur IDarsl Date Dale I 1 1 1 1 I l I 1 1 I I I I 1 1 1 1 3 1 1 3 1 1 3 1 1 2 1 1 2 1 1 1 1 1 3 1 1 2 1 1 •FHASF I--DEROLII IONIFWNDAT 1011 257 25-Jun-92 B-Mu-93 . . . . . . . . . . . . . . . . . . . . . . . . . . . •PHASE I1--SIAUCIORf/ROOF/DRAIN 362 6-Oct-92 /-Oct-93 6111191116111111 ., • • • . . . . •1,U.VAULT CONSTRUCTION 192.5 24-ML-93 2'De(-93 43ai1114E1itiFEi!19lE6S . . . . . . . . . . . . . . . . . . . . PRASE 111--FACADE L INTERIOR 334 I-Apr-93 264eb-9/FE±!ieit t!iFtieel4ett}tits!Ea;EaEEt . . . . . . . . . . . . . . . . . . . . . . . . NC:TICE 10 BIDDERS 0 l-Aa-93 I-Apr-93 BIDS OUE 0 29-Apr-93 21-Apr-93 COUNCIL AWARD CONTRACT 0 8-Jun-931-JO-97 . . . . . . . . . . . . . . . CONTRACT EIECUIED 0 25-Jun-93 23-JUN-93 SHOP DRAWIWSS 15 29-Jul-93 12-Oct-93 _ . . . . . . . . . . . . . . PRE CONTRUC1iON CONE. 0 3I-W6-93 31-A9B-93 I A . . . . . . . . . . . . . . . . . . . . COhS IAU[iION IBD 2-Seo-93 26-Fe1-9/ . . . . . . . . . . . . . . . . . . . COMST.11 IGH COMPLETION 0 28-46-14 29Fe1-91 N REMOVE PAVEMENT 35 25-Jam-9/28ie6.9/ I Air PHASE IIIA--SIAEEISISIDENALI 201 12-W1-93 20-Feb-91 ! 111 a to 11111321 If Elf 1E EE 44 E F'_! . . . . . . . . . . . . . . . . . . . , NOTICE 10 BIDDERS 012-Am 431 I2-Ap-93 I A. . . . . . . . . ... . . . . . . . . . . . . . . bIDS DUE I 9-Sep-93 9-Sed-9I ■ . . . . . . . . . . . . . . . . . . . . . . . COUNCIL AWARD CONTRACT 1 6-Oct-93 6-Oct-94 ■ CONTRACT EIECUIED I 15-Oct-93 15-Oct-93 I ■. PRE CONSTRUCTION CONF, 1 29-0(t-93 29-0(t-1S ■ CONSTRUCTION 120 1-Nor-93 21-Fel-9/ COWirRUCTTON COMPLETE 0 26-Fee-91 26-Fee-9/ n PHASE IV--[ABLE LV.STUDIO 230 26-WO-93 12-Air-9iiiaiLliiti 11 ll!l44i}}EE!'_14lttt NOTICE TO BIDDERS 0 26-W1-17 21-Atq-93 M . . . . . . . . . . . . . . . . . . . . . . . . BIDS DUE 1 27-fe9-93 23-Sep-93 It . . . . . . . . . . . . . . . . . . . . . . . COtNCIL AWARD CONTRACT 1 19-Oct-93 I"ct-93 ■. CONTRACT EIECUIED I i9-Oct-13 29-Oct-13 • TRE COwIRUC110N CONE, 1 29-Oft-93 29-Oct-93 ■ CONSTRUCliON-ROUGH-iN 43 I-Nor-93 I3-Dec-9I . . . . . . . . . . CONSTRUCTIOm-FINISR WOR( 120 I/-Dec-13 I2-W-9/ . . . . . . . . . . . . . .. . iO%SIRUCIION COM%LEtE 0 12-A9r-9/12-AN-91 I .A PHASE V--FIRST a SECOND FLOOR 379 menuiuuuumeuuuuul4nLLLLLnuuuuL. PREPARE 910 DOCUMNE IS 90 NOTICE TO I,DDERS 9 '7.71 T .7 M. .� . , . . . . Il PIGS DUE 1 I to. W COUNCIL AWARD CONIAACI I i •, . . . WMTRAMA EIECUIED 1 i ■ . . . • • • • ,� • ORDER MATERIAL 90 i. (DTRUCTION SECOND FLOOR 120 ti'•aFFL1E!!=_iL�a. . . . . . . . . . • • • • • O1E0 STEEL 3V . . . . . . . . . . . . . . . n T UnFLEIE CONitAUCIION 30 I �, �T O IAEi Fl.;OA hOUfiN IN SLAB NO Jen 9S—App.15 a_•, 1-4IRST FLOOR FINISH 675 I %� i!fFEFtieiitE!!Ei1i!iiEi iEEii'_EiiES!2!EEEEEE44E1ii 3EIEf LEEP iEEL liiiiEifiiEL i!E!L!f4li 4f lltEs , . . . ti Sol 100 DES16W 160 a� 'FEF;T FUNDS 113 . . . . . . . . . . . . y S �7 E aAE 610 JOCunENIS Ill ; . . . . . , . . D DUE I 1. . . . . . . .■. . . . . . . . �•C I;a■a:uv7Nt6atT l 1 ,•, ��aa� ACI EIECUTED 1 ■ .V c-.„xETF,k�IOh CAME. I i ■ . . . FF IE =