AMENDMENT No. 6 2
TO CITY SECRETARY CONTRACT No. 45895
WHEREAS, the City of Fort Worth (CITY) and CP&Y, Inc, (ENGINEER)
made and, entered into City Secretary Contract No. 45895, (the CONTRACT)
which was authorized by M&C C-26925 on the 19th day of August, 2014 in
the amount of $ 468, 966. 00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment Number
I in the amount of $8, 250 which was administratively authorized on
December 8, 2014, Amendment Number 2 in the amount of $73, 790 . 00 which
was authorized by M&C C-27157 on January 27, 2015, Amendment 3 in the
amount of $26, 511 . 00 which was administratively authorized on March 3,
2015, Amendment 4 in the amount of $3, 300 . 00 which was administratively
authorized on April 27, 2015, Amendment 5 in the amount of $19, 952 . 90
which was administratively authorized on May 5, 2015; and
WHEREAS, the CONTRACT involves engineering services for the
following project :
Airport Development Projects at Alliance Airport; and
WHEREAS, it has become necessary to execute Amendment No. 6 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated September 9, 2016, a
copy of which is attached hereto and incorporated herein. The cost to
City for the additional design services to be performed by Engineer
totals $ 74,350. 17.
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $675,120. 07.
City of Fort Worth
Professional Services Agreement Amendment Template .......... ............
PMO Official Release 8/1/2012
Page 1 of 2
I TV S
1�Ifill
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect .
EXECUTED and EFFECTIVE as of the date last written by a signatory, below.
APPROVED:
City of Fort Worth ENGINEER
CP&Y, Inc
Fernando Costa chael S. Hartzle
Assistant City Manager Senior Vice President
DATE: DATE: 2 A C
APPROVAL RECOMMENDED:
William Welstead
Director, Aviation Department
APPROVED AS TO FORM AND LEGALITY: M&C: �
Date :
Grant Jordan
Assistant City Attorney
Fop
AT T E ST.;,
64— ..o. ..._ ' ��
a y J. Kayser
"City Secretary NL Fw
,ti
iFF10AL R ECORD
City of Fort Worth �' 1�
Professional Services Agreement Amendment Template
PMO Official Release 8/1/2012 { A (), T0,,P'J y TX
Page 2 of 2
CP8tY--") P, r hers for a Heger QUality of Life
James A. McKenzie, PE
CP&Y
1820 Regal Row
Dallas,TX 75235
September 9,2015
RuseenaJohnson
City of Fort Worth Aviation Department
3951 Lincoln Ave
Fort Worth,TX 76106
RE: Airport Development Projects at Alliance Airport Amendment No. 6
Dear Ms.Johnson:
I am requesting an amendment to the Airport Development Projects at Alliance Airport for construction management
services on the RTR Duct Bank & Taxiway H Improvements project. The additional expenses were incurred due to
construction contract time extensions granted to the contractor.
The total contract amendment request is for$74,350.17.A summary of the change to the contract is shown below.
Original Contract Amount $468,966.00
Previous Amendments $131,803.90
RPR Services by Jacobs&PMA $46,231.06
CP&Y 10%Subconsultant Markup $4,623.11
CM Services by CP&Y $23,496.00
Amendment#6 Total $74,350.17
New Contract Total $675,120.07
DBE Participation
DBE Participation Arnount for Original Contract $72,262.00
DBE Participation for Previous Amendments $39,610.00
Additional DBE Participation for This Amendment $22,520.00
DBE Participation for New Contract Total $134,392.00
DBE Participation%for New Contract Total 19.9%
Thank you for your consideration of this request. Should you have any questions or comments regarding this matter,
please feel free to contact me at 214-589-6914 or by email at imckenzie@cpyi.com
Sincerely,
220 Regal Row,Suite 200
James A. McKenzie, PE taaH as.Texas 75235
(4')}'2'14.638 0500 En 224 638 3723
wwvv('Pp Corr
Proposal for Construction Phase Services
RTR Ductbank Pay
Fort Worth Alliance Airport
Phase Labor Cost Reimbursables CP&Y Fee Total
Construction Management
CP&Y CM Services $21,360.00 $0.00 $2,136.00 $23,496.00
PMA RPR Services $22,520.00 $2,252.00 $24,772.00
Jacobs RPR Services $23,711.06 $2,371.11 $26,082.17
Total - Cost Plus Fixed Fee $21,360.00 $46,231.06 $6,759.11 $74,350.17
Total Proposal Amount $74,350.17
8/24/2015
Proposal for Construction Phase Services
RTR Ductbank C P&Y
Fort Worth Alliance Airport
Construction Management Labor(Hours)
Project Civil Elec Hours by
Task Description Admin. Inspector Inspector Task
1 Pre-construction
Coordination
Pre-construction meeting
2 Construction
Coordination 120 120
Bi-Weekly Project meetings
QA 12 weeks
Pre-acceptance Inspection
Acceptance inspection
Maintain Project records
Change Orders
Pay Request 2
3 Punch List
Coordination
Final payment 1
4 Closeout
Coordination
Closeout documents
Hours by classification 1 1201 0 0 0 0 0 0 120
Direct Hourly Rate by classification 1 $178 $N1
Direct Labor Cost by classification 1 $21,360 $01 $0 $0 $0 $0 $0 $21,360
Construction Phase Services
Jacobs Fee Proposal
RTR Duct Bank-Additional Services
Alliance Airport, Fort Worth,Texas
Fee Proposal Hourly Hours Labor
Rate Cost
Resident Project Represetative(RPR) $ 66.44 160 $ 10,630.40
Salary Cost $ 10,630.40
Overhead Rate @ 91.85% $ 9,764.02
Sub-Total $ 20,394.42
Profit @ 10% $ 2,039.44
Labor Cost $ 22,433.86
Expenses
Mileage($0.56'280 miles per trip) $156.80 4 $ 627.20
Lodging($550 per month) $550.00 1 $ 550.00
Electric $100.00 1 $ 100.00
Taxi $0.00 0 $ -
Hotel(Per Diem) $0.00 0 $ -
Meals(Per Diem$56) $56.00 0 $
Airfare(Per trip) $0.00 0 $
Parking(Per Day) $0.00 0 $ -
Rental Car $0.00 0 $ -
Total Expenses $ 1,277.20
Jacobs Additional Total Cost $ 23,711.06
Total Additional Contract Cost $ 23,711.06
8/7/2015
V'V PROJECT MANAGEMENT ASSOCIATES
VCIS/L FNCINCERS AND CONSTRUCTION MANAGE MS
James A. McKenzie., P.E August 24,, 2015
Aviation Project Manager
CP&Y Engineers
1820 Regal Row
Dallas TX 75235
Dear Sir,
Amendment Request to Fort Worth Alliance Airport RTR Duct Bank and Taxiway A
Improvements Project
Project Management Associates PLLC (PMA) would like to request an amendment to its sub-
consultancy agreement with CP&Y Engineers to provide Resident Project Representative (RPR)
Services for the above mentioned project.
Due to time extension requests granted to the Contractor, the original contract execution time of
300 hours will be exceeded. It is envisaged that the project will now be completed within 581.5
hours.
Therefore, PMA is requesting that an additional $22,520.00 (twenty-two thousand, five hundred
and twenty dollars) representing an additional 281.5 hours at the hitherto agreed contract RPR
rate of $80.00/hr be added to the original not to exceed contract cost of $24,000.00. The new
Not To Exceed contract sum shall be $46,520.00 (forty - six thousand, five hundred and twenty
dollars). The scope of our services does not change.
Should you have any questions,- please do not hesitate to contact me at telephone number
(972)-302-7635.
Sincerely,
Project Management Associates PLLC.
Edward M. Andrews, P.E.
President
l
City of Fort Worth
ACCEPTANCE OF PREVIOUS DBE COMMITMENT FORM
(for use with CHANGE ORDERS or AMENDMENTS greater than$50,000)
To be Completed by City Project Manager
Amendment(for Professional Services Agreement)
Project Name: City Project Number
Airport Development Projects at Alliance Airport
na
City Project Manager
Consultant: Ruseena Johnson
CP&Y, Inc City's DBE Project Goal: 17
Original Amount of Agreement: $468,966,00 Accepted DBE Commitment: 17 %
Total of Previous Amendments: $131,803.90 Date of Last DBE Report:
Amount for this Amendment: $74,350.17 Amendment#: 6
Revised Amount of Agreement: $675,120.07 Date: 9/4/2015
Language to be inserted in the M&C for this Agreement
CP&Y, Inc agrees to maintain its initial DBE commitment of 17% that it made on the original
agreement and extend and maintain that same DBE commitment of 17% to all prior amendments
up to and inclusive of this Amendment No, 6. Therefore CP&Y, Inc remains in compliance with the
City's BIDE Ordinance and attests to its commitment by its signature on the Acceptance of
Previous DBE Commitment form executed by an authorized representative of its company.
To be Completed by the Representative of the Consultant
James McKenzie Project Manager
Printed Signature Title 'Authorize ignature/Date
CP&Y, Inc
Company Name Contact Name(if different)
1820 Regal Row jmckenzie @cpyi.com
Address E-mail address
Dallas,TX 75235 214-589-6914 214.638-3723
City/State/Zip Phone number Fax Number
14% as of 9/9/2015
DBE%Paid to Date Date
City Project Manager has reviewed t e work assoclatea with this Tkmenament,
considers it the same or similar to work in the original Agreement, and recommends that the
Consultant have the option to e in and con Ym 1 s existing SBE commitment
Ruseena Johnson
City Project Manager Ci Project anager Signature ate
MNVB om liance Staff ID# DBE Current%Level via Last Report Rec'd'
M BE Signature Date
EXHIBIT "B-3"
(Supplement to Attachment B)
On Call Agreement for
Certain Development Projects at Alliance Airport
SUMMARY OF TOTAL PROJECT FEES
Consulting Firm Prime Responsibility Amount %
Prime Consultant: Program management, 411,873.65 61.0
CP&Y airfield civil design,
construction management
Proposed M/WBE
Sub-Consultants Amount %
ANA Consultants, Survey services 30,000.00 4.4
LLC
Gorrondona & Geotechnical investigation 30,302.00 4.5
Associates, Inc. & construction materials
testing
Project Management Resident project 46,520.00 6.9
Associates, LLC representative services
Ferguson Consulting, Airfield electrical design 27,570.00 4.1
Inc.
Non-M/WBE
Consultants:
Jacobs Engineering Resident project 128,854.42 19.1
Group, Inc. representative services
Project Description Scope of Services Total Fee MWBE Fee Percent
Development Projects Engineering Design $600,769.90 $134,392.00 19.9%
At Alliance Airport & Construction
Management
City M/WBE Goal = 17%