HomeMy WebLinkAboutContract 26089 CITY SECRETARY -
CONTRACT NO. O
CITY SECRETARY
D.O.E. FILE SPECIFICATIONS
CONTRACTOR'S BONDING CO- AND
- CONTRUCi'ION'S COPY
CLIENT DEPARTMENT
CONTRACT DOCUMENTS
STORM DRAIN IMPROVEMENTS OF
COMO DRAINAGE SYSTEM
PROTECT NO. C111-030111028886
DOE NO. 0761
IN THE CITY OF FORT WORTH,TEXAS
FILE No. SD-2
2000
KENNETH L. BARR BOB TERRELL
MAYOR CITY MANAGER
HUGO A.MALANGA, PE -DIRECTOR
DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS
I
A. DOUGLAS RADEMAKER, PE - DIRECTOR
DEPARTMENT OF ENGINEERING
®ft� x%
TES°aa
0
Ji,hA B YAN BECK
0'.0' 8457. . . . . . . . . %
4
City of Fort Worth, Texas
"rigor andCommunication
Coundl
DATE REFERENCE NUMBER LOG NAME PAGE
7/11/00 **C-18105 30CNJ 1 of 2
SUBJECT MODIFICATION OF THE SCOPE OF THE 1993 CAPITAL IMPROVEMENT PROJECT
FOR EAST COMO DRAINAGE SYSTEM AND AWARD OF CONTRACT TO CNJ
CONSTRUCTION, INC. FOR STORM DRAIN IMPROVEMENTS TO EAST COMO
DRAINAGE SYSTEM FROM LOVELL AVENUE TO FARON STREET
RECOMMENDATION:
It is recommended that the City Council:
1. Find that a material change has occurred making construction of the East Como Drainage System,
as originally proposed, unnecessary; and
2. Approve the modification of the scope of the 1993 Capital Improvement Program project for the
East Como Drainage System (bond amount $1,013,000.00) to storm drain improvements at a
reduced scope along a natural channel within the area of the East Como Drainage System; and
3. Authorize the City Manager to execute a contract with CNJ Construction, Inc. in the amount of
$23,066.80 and 25 working days for Storm Drain Improvements to the East Como Drainage System
from Lovell Avenue to Faron Street within the area of the Como Drainage System.
DISCUSSION:
In each Capital Improvement Program (CIP), the City Council retains the right to abandon or modify a
project if, in the City Council's opinion, conditions materially change so that the project is unwise or
unnecessary.
The 1993 CIP included $1,013,000.00 for the construction of the East Como Drainage System Project.
The East Como Drainage System is located in the Como community south of Camp Bowie Boulevard,
east of Bryant Irvin Road, west of Bourine Street and north of West Vickery Boulevard.
Preliminary engineering analysis determined that recent reconstruction of several streets which
included storm drain improvements within the East Como watershed have made the original scope of
this project unnecessary. Staff is recommending that this project be modified and reduced in scope to
provide storm drain improvements to the East Como Drainage System from Lovell Avenue to Faron
Street.
This project was advertised for bid on March 9 and 16, 2000. On April 6, 2000, the following bids were
received:
City of Fort Worth, Texas
"avow and council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
7/11/00 **C-18105 1 30CNJ 2 of 2
SUBJECT MODIFICATION OF THE SCOPE OF THE 1993 CAPITAL IMPROVEMENT PROJECT
FOR EAST COMO DRAINAGE SYSTEM AND AWARD OF CONTRACT TO CNJ
CONSTRUCTION, INC. FOR STORM DRAIN IMPROVEMENTS TO EAST COMO
DRAINAGE SYSTEM FROM LOVELL AVENUE TO FARON STREET
BIDDERS AMOUNT TIME OF COMPLETION
CNJ Construction, Inc. $23,066.80 25 Working Days
Ed A.Wilson, Inc. $24,410.00
Walt Williams Construction, Inc. $24,810.49
Intrepid Contractors, Inc. $25,167.00
Burnsco Construction, Inc. $33,111.00
Carter Construction, Inc. $33,803.14
Burleson Utilities, Inc. $34,045.90
Southern Paradise, Inc. $35,565.00
Allison Broyles, Inc. $37,445.98
The contingency for possible change orders is $2,307.00.
The Policy for Council Districts' Undesignated Capital Improvements Funds, adopted March 14, 1996
(M&C G-11420), provides for surplus funds resulting from the elimination or significant alteration of a
district project will remain within the Council District and be added to the Undesignated Account for that
district. Modification of the project scope for the East Como Drainage System Project will provide a net
increase to the Undesignated Account for Council District 7 by $989,933.20, bringing the total amount
in this account to $1,631,220.82.
The M/WBE Ordinance does not apply to a construction contract less than $25,000.00.
This project is located in COUNCIL DISTRICT 7, Mapsco 74M.
FISCAL INFORMATION/CERTIFICATION:
The Finance Director certifies that funds are available in the current capital budget, as appropriated, of
the Street Improvements Fund.
MG:k
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
APPROVED
Mike Groomer 6140 CITY COUNCIL
Originating Department Head:
A.Douglas Rademaker 6157 (from) JUL 11 2000
C111 541200 020111028886 $23,066.80
Additional Information Contact: Ciy�g�ry of the
city of Port Worth,Texas
A.Douglas Rademaker 6157
TABLE OF CONTENTS
TABLE OF CONTENTS
1. Notice to Bidders
2. Special Instructions to Bidders
3. Proposal
4. Vendor Compliance to State Law
5. Minority and Women Business Enterprises Specifications
6. Special Provisions
7. Permits/Easements
8. Certificate of Insurance
9. Contractor Compliance With Worker's Compensation Law
10. Equipment Schedule
11. Experience Record
12. Performance Bond
13. Payment Bond
14. Contract
I
�s.
I
6. WAGE RATES:All bidders will be required to comply with provision 5159a of"Vernons Annotated
Civil Statutes"of the State of Texas with respect to the payment of prevailing wage rates as established
by the City of Fort Worth,Texas and set forth in Contract Documents for this project.
7. FINANCIAL STATEMENT: A current certified financial statement may be required by the
Department of Engineering if required for use by the CITY OF FORT WORTH in determining the
successful bidder. This statement,if required,is to be prepared by an independent Public Accountant
holding a valid permit issued by an appropriate State Licensing Agency.
8. INSURANCE: Within ten(10)days of receipt of notice of award of contract,the Contractor must
provide,along with executed contract documents and appropriate bonds,proof of insurance for
Worker's Compensation and Comprehensive General Liability(Bodily Injury-$250,000 each person,
$500,000 each occurrence;Property Damage-$300,000 each occurrence). The City reserves the right
to request any other insurance coverages as may be required by each individual project.
�. NONRESIDENT BIDDERS: Pursuant to Article 601g,Texas Revised Civil Statutes,the City of Fort
Worth will not award this contract to a non resident bidder unless the nonresident's bid is lower than the
lowest bid submitted by a responsible Texas resident bidder by the same amount that a Texas resident
bidder would be required to underbid a nonresident bidder to obtain a comparable contract in the state in
which the nonresident's principal place of business is located.
"Nonresident bidder"means a bidder whose principal place of business is not in this
state,but excludes a contractor whose ultimate parent company or majority owner
has its principal place of business in this state.
"Texas resident bidder"means a bidder whose principal place of business is in this
state,and includes a contractor whose ultimate parent company or majority owner
has its principal place of business in this state.
This provision does not apply if this contract involves federal funds.
The appropriate blanks of the Proposal must be filled out by all non resident bidders in order for its bid to
meet specifications. The failure of a nonresident contractor to do so will automatically disqualify that
` bidder.
10. MINORITY AND WOMEN BUSINESS ENTERPRISES: In accord with City of Fort Worth
Ordinance No. 11923,as amended,the City of Fort Worth has goals for the participation of minority
business enterprises and women business enterprises in City contracts. A copy of the Ordinance can
be obtained from the office of the City Secretary.In addition,the bidder shall submit the MBE/WBE
UTILIZATION FORM,PRIME CONTRACTOR WAIVER FORM and/or the GOOD FAITH
EFFORT FORM("Documentation")as appropriate. The Documentation must be received no later
than 5:00 p.m.,five(5)City business days after the bid opening date. The bidder shall obtain a receipt
from the appropriate employee of the managing department to whom delivery was made. Such receipt
shall be evidence that the Documentation was received by the City. Failure to comply shall render the
bid non-responsive.
Upon request,Contractor agrees to provide to owner complete and accurate information regarding
actual work performed by Minority Business Enterprise(WBE)on the contract and payment therefore.
Contractor further agrees to permit an audit and/or examination of any books,records or files in its
possession that will substantiate the actual work performed by an MBE and/or WBE. The
misrepresentation of facts(other than a negligent misrepresentation)and/or the commission of fraud
by the Contractor will be grounds for termination of the contract and/or initiation action under
OL
pa
appropriate federal,state or local laws or ordinances relating to false statement;further,any such
misrepresentation(other than a negligent misrepresentation)and/or commission of fraud will result in
the Contractor being determined to be irresponsible and barred from participation in City work for a
period of time of not less than three(3)years.
11. AWARD OF CONTRACT:Contract will be awarded to the lowest responsive bidder.The City
reserves the right to reject any and/or all bids and waive any and/or all irregularities. No bid may be
withdrawn until the expiration of forty-nine(49)days from the date the M/WBE UTILIZATION
FORM,PRIME CONTRACTOR WAIVER FORM and/or the GOOD FAITH EFFORT FORM
("Documentation")as appropriate is received by the City. The award of contract,if made,will be
within forty-nine(49)days after this documentation is received,but in no case will the award be made
until the responsibility of the bidder to whom it is proposed to award the contract has been verified.
12. PAYMENT:The Contractor will receive full payment(minus 5%retainage)from the City for all
work for each pay period. Payment of the remaining amount shall be made with the final payment,
and upon acceptance of the project.
13. ADDENDA: Bidders are responsible for obtaining all addenda to the contract documents prior to the
bid receipt time and acknowledging them at the time of bid receipt. Information regarding the status
of addenda may be obtained by contacting the Department of Engineering Construction Division at
(817)871-7910.Bids that so not acknowledge all applicable addenda may be rejected as non-
responsive.
14. CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW:
A.Workers Compensation Insurance Coverage
a.Definitions:
*� Certain of coverage("certificate").A copy of a certificate of insurance,a certificate of
authority to self-insure issued by the commission,or a coverage agreement(TWCC-81,
TWCC-82,TWCC-83,or TWCC-84),showing statutory worker's compensation insurance
coverage for the person's or entity's employees providing services on a project,for the
duration of the project.
Duration of the project-includes the time from the beginning of the work on the project until
the contractor's/person's work on the project has been completed and accepted by the
governmental entity.
Persons providing services on the project("subcontractor"in§406.096)-includes all persons
or entities performing all or part of the services the contractor has undertaken to perform on
the project,regardless of whether that person contracted directly with the contractor and
regardless of whether that person has employees. This includes,without limitation,
independent contractors,subcontractors,leasing companies,motor carriers,owner-operators,
employees of any such entity,or employees of any entity which furnishes persons to provide
services on the project. "Services"include,without limitation,providing,hauling,or
delivering equipment or materials,or providing labor,transportation,or toner services related
to a project."Services"does not include activities unrelated to the project,such as
food/beverage vendors,office supply deliveries,and delivery of portable toilets.
b. The contractor shall provided coverage,based on proper reporting of classification codes
and payroll amounts and filing of any coverage agreements,which meets the statutory
requirements of Texas Labor Code,Section 401.011 (44)or all employees of the
contractor providing services on the project,for the duration of the project.
c. The Contractor must provide a certificate of coverage to the governmental entity prior to
being awarded the contract.
d. If the coverage period shown on the contractor's current certificate of coverage ends
during the duration of the project,the contractor must,prior to the end of the coverage
rr period,file a new certificate of coverage with the governmental entity showing that
coverage has been extended.
e. The contractor shall obtain from each person providing services on a project,and provide
to the governmental entity:
(1) a certificate of coverage,prior to that person beginning work on the project,so the
governmental entity will have on file certificates of coverage showing coverage for
all persons providing services on the project;and
(2) no later than seven days after receipt by the contractor,a new certificate of coverage
showing extension of coverage,if the coverage period shown on the current
certificate of coverage ends during the duration of the project.
im f. The contractor shall retain all required certificates of coverage for the duration of the
project and for one year thereafter
g. The contractor shall notify the governmental entity in writing by certified mail or
personal delivery,within ten(10)days after the contractor knew or should have known,
of any change that materially affects the provision of coverage of any person providing
services on the project.
h. The contractor shall post on each project site a notice,in the text,form and manner
prescribed by the Texas Worker's Compensation Commission,informing all persons
providing services on the project that they are required to be covered,and stating how a
person may verify coverage and report lack of coverage.
I. The contractor shall contractually require each person with whom it contracts to provide
services on a project,to:
(1) provide coverage,based on proper reporting on classification codes and payroll
amounts and filing of any coverage agreements,which meets the statutory
requirements of Texas labor Code,Section 401.011 (44)for all of its employees
providing services on the project,for the duration of the project;
(2) provide to the contractor,prior to that person beginning work on the project,a
certificate of coverage showing that coverage is being provided for all employees of
the person providing services on the project,for the duration of the'prc ject;
(3) provide the contractor,prior to the end of the coverage period,a new certificate of
coverage showing extension of coverage,if the coverage period shown on the
Oro current certificate of coverage ends during the duration of the project;
(4) obtain from each other person with whom it contracts,and provide to the contractor:
(a) a certificate of coverage,prior to the other person beginning work on the
project;and
(b) a new certificate of coverage showing extension of coverage,prior to the end
of the coverage period,if the coverage period shown on the current certificate
of coverage ends during the duration of the project;
(5) retain all required certificates of coverage on file for the duration of the project and
for one year thereafter.
(6) notify the governmental entity in wiring by certified mail or personal delivery,
within ten(10)days after the person knew or should have known,of any change that
materially affects the provision of coverage of any person providing services on the
project;and
(7) contractually require each person with whom it contracts,to perform as required by
paragraphs(1)-(7),with the certificates of coverage to be provided to the person for
whom they are providing services.
j. By signing this contract or providing or causing to be provided a certificate of coverage,
the contractor is representing to the governmental entity that all employees of the
contractor who will provide services on the project will be covered by worker's
compensation.coverage for the duration of the project,that the coverage will be based on
proper reporting of classification codes and payroll,amounts,and that all coverage
agreements will be filed with the appropriate insurance carrier or,in the case of a self
,. insured,with the commission's Division of Self-Insurance Regulation. Providing false or
misleading information may subject the contractor to administrative,criminal,civil
penalties or other civil actions.
k. The contractor's failure to comply with any of these provisions is a breach of contract by
the contractor does not remedy the breach within ten days after receipt of notice of
breach from the governmental entity.
B. The contractor shall post a notice on each project site informing all persons providing services on the
project that they are required to be covered,and stating how a person may verify current coverage and
report failure to provide coverage. This notice does not satisfy other posting requirements imposed by
the Texas Worker's Compensation Act or other Texas Worker's Compensation Commission rules.
This notice must be printed with a title in at least 30 point bold type and text in at least 19 point normal
type,and shall be in both English and Spanish and any other language common to the worker
population. The text for the notices shall be the following text,without any additional words or
changes:
"REQUIRED WORKER'S COMPENSATION COVERAGE"
The law requires that each person working on this site or providing services related to this construction
project must be covered by worker" compensation insurance.This includes persons providing,hauling
A or delivering equipment or materials,or providing labor or transportation or other service related to the
project,regardless of the identity of their employer or status as an employee".
Call the Texas Worker's Compensation Commission at 512-440-3789 to receive information on the
legal requirement for coverage,to verify whether your employer has provided the required coverage,
or to report an employer's failure to provide coverage".
15. NON DISCRIMINATION: The contractor shall not discriminate against any person or persons
because of sex,race,religion,color,or national origin and shall comply with the provisions of City
Ordinance 7278,as amended by City Ordinance 7400(Fort Worth City Code Sections 13A-21 through
13A-29),prohibiting discrimination in employment practices.
16. AGE DISCRIMINATION: In accordance with the policy("Policy")of the Executive Branch of the
federal government,contractor covenants that neither it nor any of its officers,members,agents,or
employees,will engage in performing this contract,shall,in connection with the employment,
advancement or discharge of employees or in connection with the terms,conditions or privileges of
their employment,discriminate against person because of their age except on the basis of a bona fide
occupational qualification,retirement plan or statutory requirement.
Contractor further covenants that neither it nor its officers,members,agents,or employees,or person
acting on their behalf,shall specify,in solicitations or advertisements for employees to work on this
Contract,a maximum age limit for such employment unless the specified maximum age limit is based
upon a bona fide occupational qualification,retirement plan or statutory requirement.
Contractor warrants it will fully comply with the Policy and will defend,indemnify and hold City
harmless against any and all claims or allegations asserted by third parties against City arising out of
Contractor's alleged failure to comply with the above referenced Policy concerning age discrimination
in the performance of this Contract.
17. DISCRIMINATION DUE TO DISABILITY: In accordance with the provisions of the Americans
with Disabilities Act of 1990("ADA"),Contractor warrants that it will not unlawfully discriminate on
the basis of disability in the provision of services to the general public,nor in the availability,terms
and/or conditions of employment for applicants for employment with,or current employees of
Contractor.Contractor warrants it will fully comply with ADA's provisions and any other applicable
federal state and local laws concerning disability and will defend indemnify and hold City harmless
against any claims or allegations asserted by third parties against City arising out of Contractor's
alleged failure to comply with the above-referenced laws concerning disability discrimination in the
performance of this Contract.
Revised March 15, 1996
PM
CITY OF FORT WORTH
HIGHWAY CONSTRUCTION
PREVAILING WAGE RATE FOR 2000
CLASSIFICATION HOURLY RATE
Asphalt Raker $10.32
Asphalt Shoveler $9.75
Batching Plant Weigher $9.65
Carpenter(Rough) $13.64
Concrete Finisher-Paving $10.16
Concrete Finisher Helper(Paving) $9.70
Concrete Finisher-Structures $13.44
® Flagger $7.00
Form Builder-Structures $13.44
Form Setter-Paving &Curbs $10.25
Form Setter-Structures $9.75
Laborer-Common $7.64
Laborer-Utility $8.64
Mechanic $13.25
Servicer $10.13
Pipe Layer $7.35
Pipe Layer Helper $6.75
Asphalt Distributor Operator $11.45
Asphalt Paving Machine Operator $11.09
Concrete Paving Saw $10.53
Crane, Clamshell, Backhoe, Derrick, Dragline, Shovel (< 1 1/2 CY) $10.00
Crane, Clamshell, Backhoe, Derrick, Dragline, Shovel (> 1 1/2 CY) $11.52
Front End Loader(2 1/2 CY&less) $9.94
Front End Loader(over 2 1/2 CY) $9.32
Milling Machine Operator $8.00
Mixer $11.00
Motor Grader Operator(Fine Grade) $12.31
Motor Grader Operator $13.75
Pavement Marking Machine $11.00
Roller, Steel Wheel Plant-Mix Pavements $9.88
Roller, Steel Wheel Other Flatwheel or Tamping $12.12
Roller, Pneumatic, Self-Propelled Scraper $8.02
Traveling Mixer $10.00
Reinforcing Steel Setter(Paving) $9.75
Truck Driver-Single Axle(Light) $8.00
Truck Driver-Tandem Axle Semi-Trailer $10.22
Truck Driver-Lowboy/Float $10.54
Truck Driver-Transit Mix $10.63
Truck Driver-Winch $9.80
PROPOSAL
TO: Mr. Bob Terrell
City Manager
Fort Worth,Texas
FOR: STORM DRAIN IMPROVEMENTS OF COMO DRAINAGE SYSTEM
PROJECT NO.C111-030111028886
FILE NO.SD-2
DOE#: 0761
Pursuant to the foregoing"Notice to Bidders",the undersigned has thoroughly examined the plans,
specifications and the site,understands the amount of work to be done,and hereby proposes to do all the work
and furnish all labor,equipment,and materials necessary to complete all the work as provided in the plans and
specifications,and subject to the inspection and approval of the Department of Engineering Director of the City
of Fort Worth.
Upon acceptance of this proposal by the City Council,the bidder is bound to execute a contract and furnish
Performance and Payment Bond approved by the City of Fort Worth for performing and completing said work
within the time stated and for the following sums,to-wit:
SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT BID
S.P. 1. 1 LS. UTILITY ADJUSTMENT
ONE THOUSAND Dollars&
NO Cents Per LS. $1,000.00 $1,000.00
S.P. 2. 2 EA. PROJECT DESIGNATION SIGNS
THREE HUNDRED Dollars&
NO Cents Per EA. $300.00 $600.00
510 3. 80 LF. REMOVE&REPLACE EXIST.CHAIN
LINK FENCE
SIX Dollars& $ 6.25 a 500.00
TWENTY FIVE Cents Per LF.
440 4. 7.5 LF. PROP.24"CL.III R.C.P.
ONE HUNDRED TWENTY FOUR Dollars&
SIXTY SIX Cents Per LF. $ 124.66 $
440 5. 15 LF. PROP.54"CL.III R.C.P.
�+ ONE HUNDRED FORTY Dollars&
NO Cents Per LF. $ 140.00 $ 2,100.0
406 6. 9.3 CY. PROP.5'x5'BOX CULVERT
(CLASS A CONCRETE)
NINE HUNDRED SIXTY SEVEN Dollars& $ 967.74 $ 990
SEVENTY FOUR Cents Per CY.
110 7. 75 CY. UNCLASSFIED CHANNEL EXCAVATION A
TWENTY Dollars&
THIRTY THREE Cents Per CY. $20.33 $
r" l JIZ�• �
S.P. 8. 13 CY. PROP. 18"ROCK RIP-RAP
ONE HUNDRED Dollars&
NO Cents Per CY. $ 100.00 $ t .3oo_n0
406 9. 8 CY. PROP,CONCRETE FOR HEADWALLS,
WINGWALLS,TOEWALLS&APRONS
FIVE HUNDRED SIXTY NINE Dollars&
NO Cents Per CY. $ 569.00 $ 5,0 .00
525 10. 44 LF. TRENCH SAFETY
S.P. TWENTY TWO Dollars&
SEVENTY THREE Cents Per LF. $22.73 $ 1,000.00
112 11. 25 CY. PROP.BORROW
FIFTEEN Dollars&
NO Cents Per CY.
$ 15.00 $375.00
S.P. 12. 20 CY. TOP SOIL
314 NINE Dollars&
NO Cents Per CY. $9.00 $ 180.00
TOTAL BID $ 23,5 0
z3, 0 r
SG
This contract is issued by an organization which qualifies for exemption pursuant to the provision of
Article 20.04(F)of the Texas Limited Sales,Excise and Use Tax Act,
Taxes. All equipment and materials not consumed by or incorporated into the project construction,are
subject to State sales taxes under House Bill 11,enacted August 15, 1991.
The successful Bidder shall be required to complete the attached Statement of Materials and Other
Charges at the time of executing the contract.
The Contractor shall comply with City Ordinance 7278,as amended by City Ordinance 7400(Fort
Worth City Code Sections 13-A-21 through 13-A-29),prohibiting discrimination in employment
practices.
The undersigned agrees to complete all work covered by these contract documents within Twenty Five
(25)Working Days from and after the date for commencing work as set forth in the written Work
Order to be issued by the Owner and to pay not less than the"Prevailing Wage Rates for Street,
Drainage and Utility Construction'as established by the City of Fort Worth,Texas.
Within ten(10)days of receipt of notice of acceptance of this bid,the undersigned will execute the
formal contract and will deliver an approved Surety Bond for the faithful performance of this contract.
The attached deposit check in the sum of 5% BID BOND Dollars
($ )is to be forfeited in the event the contract and bond are not executed within
the time set forth,as liquidated damages for delay and additional work caused thereby.
(Uwe), acknowledge receipt of the following addenda to the plans and specifications,all of the
provisions and requirements of which have been taken into consideration in preparation of the
foregoing bid:
Addendum No. 1 (Initials) Addendum No.3(Initials)
Addendum No.2(Initials) Addendum No.4(Initials)
Respectfully submitted:
By Q� A-\.� - L)VA,,P�
AdCzsrTcN.T rnNgtgu '.TTn1 Tw
955 CEDARVIEW
CEDAR HILL, TEXAS 75104
Telephone 979-299-6166
(SEAL)
Date 4-6-00
=o ANDREA WAITERS
Or V, NOTARYPUBLIC
; State of Texas
it!,1 cOmm. EV 10-03-2001
VENDOR COMPLIANCE TO STATE LAW
� r
The 1985 Session of the Texas Legislature passed House Bill 620 relative to the award of contracts to
nonresident bidders. This law provides that,in order to be awarded a contract as low bidder,nonresident bidders
_.. (out-of-State contractors whose corporate offices or principal place of business are outside of the State of Texas)
bid projects for construction,improvements,supplies or services in Texas at an amount lower than the lowest
Texas resident bidder by the same amount that a Texas resident bidder would be required too underbid a
nonresident bidder in order to obtain a comparable contract in the State in which the nonresident's principal
place of business is located. The appropriate blanks in Section A must be filled out by all put-of-State or
nonresident bidders in order for your bid to meet specifications. The failure of out-of-State or nonresident
contractors to do so will automatically disqualify that bidder. Resident bidders must check the box in Section B.
A. Nonresident vendors in (give State),our principal place of business,are required to
be percent lower than resident bidders by State law. A copy of the Statute is attached.
Nonresident vendors in (give State),our principal place of business,are not
required to underbid resident bidders.
B. Our principal place of business or corporate offices are in the State of Texas.
A
BIDDER:
C N, Cc►ts"h'tyGT►DLJ{Is.�C By: S d N S• �A Ztt S
(Please print)
q�� C►dt>htyt� SignatorVLOF
• _
CtrAAec 4Art 157%04 Title: N
City State Zip (Please print)
THIS FORM MUST BE RETURNED WITH YOUR QUOTATION
m
w
CITY OF FORT WORTH,TEXAS
DEPARTMENT OF ENGINEERING
SPECIAL PROVISIONS
FOR: STORM DRAIN IMPROVEMENTS OF COMO DRAINAGE SYSTEM
PROJECT NO.Clll-030111028886
FILE NO.SD-2
DOE#: 0761
1. SCOPE OF WORK: The work covered by these plans and specifications consist of storm drain extensions
and accompanying headwalls and all other miscellaneous items of construction to be performed as outlined
in the Plans and Specifications which are necessary to satisfactorily complete the work.
2. AWARD OF CONTRACT:Contract may not necessarily be awarded to the lowest bidder. The City
Engineer shall evaluate and recommend to the City Council the best bid which is considered to be in the
best interest of the City. Contract will be awarded to the lowest responsive bidder.
3. WORK ORDER DELAY:All utilities and right-of-way are expected to be clear and easements and/or
permits obtained on this project within sixty(60)days of advertisement of this project. The work order for
subject project will not be issued until all utilities,right-of-ways,easements and/or permits are cleared or
obtained.The Contractor shall not hold the City of Fort Worth responsible for any delay in issuing the work
order for this Contract.
4. WORKING DAYS:The Contractor agrees to complete the Contract within the allotted number of working
days.
5. INCREASE OR DECREASE IN QUANTITIES: The quantities shown in the proposal are approximate. It
is the Contractor's sole responsibility to verify all the minor pay item quantities prior to submitting a bid.
When the quantity of work to be done or materials to be furnished under any major pay item of the contract
is more than 125%of the quantity stated in the contract,whether stated by Owner or by Contractor,then
either party to the contract,upon demand,shall be entitled to negotiate for revised consideration on the
portion of work above 125%of the quantity stated in the contract.
When the quantity of the work to be done or materials to be furnished under any major pay item of the
contract is less than 75%of the quantity stated in the contract,whether stated by Owner or by Contractor,
then either party to the contract,upon demand,shall be entitled to negotiate for revised consideration on the
portion of work below 75%of the quantity stated in the contract. This paragraph shall not apply in the
event Owner deletes a pay item in its entirety from this contract.
A major pay item is defined as any individual bid item included in the proposal that has a total cost equal to
or greater than 5 percent of the original contract.
A minor pay item is defined as any individual bid item included in the proposal that has a total cost less than
5 percent of the original contract.
In the event Owner and Contractor are unable to agree on a negotiated price,Owner and Contractor agree
that the consideration will be the actual field cost of the work plus 15%as described herein below,agreed
upon in writing by the Contractor and Department of Engineering and approved by the City Council after
"' said work is cortipleted,'subject to all other conditions of the contract.'As used herein,field cost of the work
will include the cost of all workmen,foremen,time keepers,mechanics and laborers;all materials,supplies,
trucks,equipment rental for such time as actually used on such work only,plus all power,fuel,lubricants,
water and similar operating expenses;and a ratable portion of premiums on performance and payment
bonds,public liability,Workers Compensation and all other insurance required by law or by ordinance. The
Director of the Department of Engineering will direct the form in which the accounts of actual field cost
will be kept and will recommend in writing the method of doing the work and the type and kind of
equipment to be used but such work will be performed by the Contractor as an independent Contractor and
not as an agent or employee of the City. The 15%of the actual field cost to be paid to the Contractor shall
cover and compensate him for profit,overhead,general supervision and field office expense and all other
elements of cost and expense not embraced with the actual field cost as herein specified upon request,the
Contractor shall provide the Director of Engineering access to all accounts,bills and vouchers relating
thereto.
6. RIGHT TO ABANDON:The City reserves the right to abandon,without obligation to the Contractor,any
part of the project or the entire project at any time before the Contractor begins any construction work
authorized by the City.
7. CONSTRUCTION SPECIFICATIONS:This contract and project are governed by the two following
published specifications,except as modified by these Special Provisions:
STANDARD SPECIFICATIONS FOR STREET AND STORM DRAIN CONSTRUCTION
CITY OF FORT WORTH
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION
NORTH CENTRAL TEXAS
A copy of either of these specifications may be purchased at the Office of the Department of Engineering,
1000 Throckmorton Street,2'Floor,Municipal Building,Fort Worth,Texas 76102. The specifications
applicable to each pay item are indicated in the call-out for the pay item by the Engineer. If not shown,then
.� applicable published specifications in either of these documents may be followed at the discretion of the
Contractor. General Provisions shall be those of the Fort Worth document rather than Division 1 of the
North Central Texas document.
8. CONTRACT DOCUMENTS:Bidders shall not separate,detach or remove any portion,segment or sheets
from the contract documents at any time. Failure to bid or fully execute contract without retaining contract
documents intact may be grounds for designating bids as"nonresponsive"and rejecting bids or voiding
-� contract as appropriate and as determined by the Director of the Department of Engineering.
9. MAINTENANCE STATEMENT:The Contractor shall be responsible for defects in this project due to
faulty materials and workmanship,or both,for a period of one(1)year from date of final acceptance of this
project by the City Council of the City of Fort Worth and will be required to replace at his expense any part
or all of the project which becomes defective due to these causes.
10. CONSTRUCTION STAKING:Construction stakes for line and grade will be provided by the City as
outlined on page 17,Standard Specifications for Construction,City of Fort Worth.
y. 11. TRAFFIC CONTROL: The contractor shall be responsible for providing traffic control during the
construction of this project consistent with the provisions set forth in the"1980 Texas Manual on Uniform
Traffic Control Devices for Streets and Highways"issued under the authority of the"State of Texas
Uniform Act Regulating Traffic on Highways,"codified as Article 6701 d Vernon's Civil Statues,pertinent
�. sections being Section Nos.27,29,30 and 31.
The Contractor will not remove any regulatory sign,instructional sign,street name sign or other sign which
has been erected by the City. If it is determined that a sign must be removed to permit required
construction,the Contractor shall contact the Transportation and Public Works Department. Signs and
Markings Division (phone number 871-8075),to remove the sign. In the case of regulatory signs,the
Contractor must replace the permanent sign with a temporary sign meeting the requirements of the above
referenced manual and such temporary sign must be installed prior to the removal of the permanent sign. If
the temporary sign is not installed correctly or if it does not meet the required specifications,the permanent
sign shall be left in place until the temporary sign requirements are met. When construction work is
completed to the extent that the permanent sign can be reinstalled the Contractor shall again contact the
Signs and Markings Division to reinstall the permanent sign and shall leave his temporary sign in place until
such reinstallation is completed.
e
12. DELAYS: The Contractor shall receive no compensation for delays or hindrances to the work,except when
direct and unavoidable extra cost to the Contractor is caused by the failure of the City to provide
information or material,if any,which is to be furnished by the City. When such extra compensation is
claimed a written statement thereof shall be presented by the Contractor to the Engineer and if by him found
correct shall be approved and referred by him to the Council for final approval or disapproval;and the
action thereon by the Council shall be final and binding. If delay is caused by specific orders given by the
Engineers to stop work or by the performance of extra work or by the failure of the City to provide material
or necessary instructions for carrying on the work,then such delay will entitle the Contractor to an
equivalent extension of time,his application for which shall,however,be subject to the approval of the City
Council;and no such extension of time shall release the Contractor or the surety on his performance bond
foam all his obligations hereunder which shall remain in full force until the discharge of the contract.
13. DETOURS AND BARRICADES: The Contractor shall prosecute his work in such a manner as to create a
minimum of interruption to traffic and pedestrian facilities and to the flow of vehicular and pedestrian
traffic within the project area. Contractor shall protect construction as required by Engineer by providing
barricades.
Barricades,warning and detour signs shall conform to the Standard Specifications"Barriers and Warning
and/or Detour Signs,"Item 524 and/or as shown on the plans.
Construction signing and barricades shall conform with"1980 Texas Manual on Uniform Traffic Control
Devices,Vol.No. I."
14. DISPOSAL OF SPOIL/FILL MATERIAL: Prior to the disposing of any spoil/fill material,the contractor
shall advise the Director of the Department of Engineering acting as the City of Fort Worth's Flood Plain
Administrator("Administrator"),of the location of all sites where the contractor intends to dispose of such
material. Contractor shall not dispose of such material until the proposed sites have been determined by the
Administrator to meet the requirements of the Flood Plain Ordinance of the City of Fort Worth(Ordinance
No. 10056). All disposal sites must be approved by the Administrator to ensure the filling is not occurring
within a flood plain without a permit. A flood plain permit can be issued upon approval of necessary
engineering studies. No fill permit is required if disposal sites are not in a flood plain. Approval of the
contractors disposal sites shall be evidenced by a letter signed by the Administrator stating that the site is
not in a known flood plain or by a Flood Plain fill Permit authorizing fill within the flood plain. Any
expenses associated with obtaining the flll permit,including any necessary engineering studies,shall be at
the contractors expense. In the event that the contractor disposes of spoil/fill materials at a site without a fill
permit or a letter from the administrator approving the disposal site,upon notification by the Director of
+.. Engineering,contractor shall remove the spoil/fill material at its expense and dispose of such materials in
accordance with the Ordinance of the City and this section.
15. ZONING REOUIREMENTS:During the construction of this project,the Contractor shall comply with
present zoning requirements of the City of Fort Worth in the use of vacant property for storage purposes.
16. QUALITY CONTROL TESTING:
(a) The contractor shall furnish,at its own expense,certifications by a private laboratory for all materials
proposed to be used on the project,including a mix design for any asphaltic and/or Portland cement
concrete to be used and gradation analysis for sand and crushed stone to be used along with the name of
the pit from which the material was taken. The contractor shall provide manufacturer's certifications
for all manufactured items to be used in the project and will bear any expense related thereto.
(b) Tests of the design concrete mix shall be made by the contractor's laboratory at least nine days prior to
the placing of concrete using the same aggregate,cement and mortar which are to be used later in the
concrete. The contractor shall provide a certified copy of the test results to the City.
(c) Quality control testing of in situ material on this project will be performed by the City at its own
expense. Any retesting required as a result of failure of the material to meet project specifications will
be at the expense of the contractor and will be billed at commercial rates as determined by the City.The
failure of the City to make any tests of materials shall in no way relieve the contractor of its
responsibility to furnish materials and equipment conforming to the requirements of the contract.
(d) Not less than 24 hours notice shall be provided to the City by the contractor for operations requiring
testing. The contractor shall provide access and trench safety system(if required)for the site to be
tested and any work effort involved is deemed to be included in the unit price for the item being tested.
(e) The contractor shall provide a copy of the trip ticket for each load of fill material delivered to the job
site. The ticket shall specify the name of the pit supplying the fill material.
17. PROPERTY ACCESS:f Access to adjacent property shall be maintained at all times unless otherwise
directed by the Engineer.
18. SAFETY RESTRICTIONS-WORK NEAR HIGH VOLTAGE LINES:
The following procedures will be followed regarding the subject item on this contract:
(a) A warning sign not less than five inches by seven inches, painted yellow with black letters that are
legible at twelve feet shall be placed inside and outside vehicles such as cranes, derricks, power
shovels,drilling rigs,pile drivers,hoisting equipment or similar apparatus. The warning sign shall read
as follows:
"WARNING—UNLAWFUL TO OPERATE THIS EQUIPMENT WITHIN SIX FEET OF HIGH
VOLTAGE LINES."
(b) Equipment that may be operated within ten feet of high voltage lines shall have an insulating cage-type
of guard about the boom or arm, except back hoes or dippers and insulator links on the lift hood
connections.
(c) When necessary to work within six feet of high voltage electric lines, notification shall be given the
- power company (TU Electric Service Company) which will erect temporary mechanical barriers, de-
energize the line or raise or lower the line. The work done by the power company shall not be at the
expense of the City of Fort Worth. The notifying department shall maintain an accurate log of all such
calls to TU Electric Service Company and shall record action taken in each case.
(d) The contractor is required to make arrangements with the TU Electric Service Company for the
temporary relocation or raising of high voltage lines at the contractor's sole cost and expense.
(e) No person shall work within six feet of a high voltage line without protection having been taken as
outlined in Paragraph(c).
19. WATER DEPARTMENT PRE-QUALIFICATIONS: Any contractor performing any work on Fort Worth
water or sanitary sewer facilities must be pre-qualified with the Water Department to perform such work in
accordance with procedures described in the current Fort Worth Water Department General Specifications
which general specifications shall govern performance of all such work.
20. RIGHT TO AUDIT:
(a) Contractor agrees that the City shall, until the expiration of three (3) years after final payment under
this contract have access to and the right to examine and photocopy any directly pertinent books,
documents, papers and records of the contractor involving transactions relating to this contract.
Contractor agrees that the City shall have access during normal working hours to all necessary
contractor facilities and shall be provided adequate and appropriate work space in order to conduct
audits in compliance with the provisions of this section. The City shall give contractor reasonable
advance notice of intended audits.
(b) Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the
subcontractor agrees that the City shall,under the expiration of three(3)years after final payment under
the subcontract, have access to and the right to examine and photocopy any directly pertinent books,
documents, papers, and records of such subcontractor involving transactions to the subcontract and
further,that City shall have access during normal working hours to'all subcontractor facilities and shall
be provided adequate and appropriate work space in order to conduct audits in compliance with the
provisions of this article together with subsection(c) hereof. City shall give subcontractor reasonable
advance notice of intended audits.
(c) Contractor and subcontractor agree to photo copy such documents as may be requested by the City.
The City agrees to reimburse contractor for the cost of copies as follows:
1. 50 copies and under $0.10 per page.
2. More than 50 copies $0.85 for first page plus$0.15 for each page thereafter.
(d) "Contractor agrees that the City shall, until the expiration of three (3)years after final payment under
this contract have access to and the right to examine any directly pertinent books, documents, papers
and records of such subcontractor, involving transactions to the subcontract and further,that City shall
have access during normal working hours to all appropriate work space, in order to conduct audits in
compliance with the provisions of this article. City shall give subcontractor reasonable advance notice
of intended audits."
CONSTRUCTION
NON-PAY ITEM No. 1 -CLEARING AND GRUBBING:
All objectionable items within the limits of this project and not otherwise provided for shall be removed under
this item in accordance with Standard Specification Item 102, "Clearing and Grubbing." However, no direct_
payment will be made for this item and it shall be considered incidental to this contract.
NON-PAY ITEM No.2-SPRINKLING FOR DUST CONTROL:
All applicable provisions of Standard Specifications Item 200, "Sprinkling for Dust Control" shall apply.
However,no direct payment will be made for this item and it shall be considered incidental to this contract.
NON-PAY ITEM No.3-PROTECTION OF TREES,PLANTS AND SOIL:
All property along and adjacent to the Contractor's operations including lawns,yards,shrubs,trees,etc. shall be
preserved or restored after completion of the work to a condition equal or better than existed prior to start of
work.
By ordinance,the contractor must obtain a permit from the City Forester before any work(trimming,removal or
root pruning) can be done on trees or shrubs growing on public property including street rights-of-way and
designated alleys. This permit can be obtained by calling the Forestry Office at 871-5738. All tree work shall
be in compliance with pruning standards for Class II Pruning as described by the National Arborist Association.
A copy of these standards can be provided by calling the above number. Any damage to public trees due to
., negligence by the Contractor shall be assessed using the current formula for Shade Tree Evaluation as defined
by the International Society of Arboriculture. Payment for negligent damage to public trees shall be made to the
City of Fort Worth and may be withheld from funds due to the Contractor by the City.
To prevent the spread of the Oak Wilt fungus,all wounds on Live Oak and Red Oak trees shall be immediately
sealed using a commercial pruning paint. This is the only instance when pruning paint is recommended.
NON-PAY ITEM No.4-CONCRETE COLORED SURFACE:
Concrete wheelchair ramp surfaces,excluding the side slopes and curb, shall be colored with LITHOCHROME
color hardener or equal. A brick red color, a dry-shake hardener manufactured by L.M. Scofield Company or
equal,shall be used in accordance with manufacturers instructions. Contractor shall provide a sample concrete
panel of one foot by one foot by three inches dimension,or other dimension approved by the Engineer,meeting
the aforementioned specifications. The sample,upon approval of the Engineer, shall be the acceptable standard
to be applied for all constriction covered in the scope of this Non-Pay Item. No direct payment will be made for
this item and it shall be considered incidental to this contract.
The method of application shall be by screen,sifter,sieve,or other means in order to provide for a uniform color
distribution.
NON-PAY ITEM No.5—PROJECT CLEAN-UP:
The Contractor shall be aware that keeping the project site in a neat and orderly condition is considered an
integral part of the contracted work and as such shall be considered subsidiary to the appropriate bid items.
Clean up work shall be done as directed by the Engineer as the work progresses or as needed. If,in the opinion
of the Engineer it is necessary,clean-up shall be done on a daily basis. Clean up work shall include,but not be
limited to:
• Sweeping the street clean of dirt or debris
• Storing excess material in appropriate and organized manner
• Keeping trash of any kind off of residents'property
If the Engineer does not feel that the jobsite has been kept in an orderly condition,on the next estimate payment
(and all subsequent payments until completed)of the appropriate bid item(s)will be reduced by 25%.
Final cleanup work shall be done for this project as soon as the paving and curb and gutter has been constructed.
No more than seven days shall elapse after completion of construction before the roadway and right-of-way is
cleaned up to the satisfaction of the Engineer.
NON-PAY ITEM No.6—PROJECT SCHEDULE:
Contractor shall be responsible for producing a project schedule at the pre-construction conference. This
schedule shall detail all phases of construction,including project clean up,and allow the contractor to complete
the work in the allotted time. Contractor will not move on to the jobsite nor will work begin until said schedule
has been received and approval secured from the Construction Engineer. However,contract time will start even
if the project schedule has not been turned in. Project schedule will be updated and resubmitted at the end of
every estimating period. All costs involved with producing and maintaining the project schedule shall be
considered subsidiary to this contract.
NON-PAY ITEM No.7—NOTIFICATION OF RESIDENTS:
In order to cut down on the number of complaints from residents due to the dust generated when saw-cutting
joints in concrete pavement,the Contractor shall notify residents,in writing,at least 48 hours in advance of saw-
cutting joints during the constriction of paving projects.
All costs involved with providing such written notice shall be considered subsidiary to this contract.
PAY ITEM No. 1 -UTILITY ADJUSTMENT:
This item is included for the basic purpose of establishing a contract price which will be comparable to the final
cost of making necessary adjustments required due to street improvements to water, sanitary sewer and natural
gas service lines and appurtenances where such service lines and appurtenances are the property owner's
responsibility to maintain. An arbitrary figure has been placed in the Proposal;however,this does not guarantee
any payment for utility adjustments, neither does it confine utility adjustments to the amount shown in the
Proposal. It shall be the"Contractor" responsibility to provide the services of a licensed plumber to make the
utility adjustments determined necessary by the Engineer. No payment will be made for utility adjustments
except those adjustments determined necessary by the Engineer. Should the contractor damage service lines due
to his negligence, where such lines would not have required adjustment or repair otherwise, the lines shall be
repaired and adjusted by the contractor at the contractor's expense. The payment to the contractor for utility
adjustments shall be the actual cost of the adjustments plus ten percent (10%) to cover the cost of bond and
overhead incurred by the contractor in handling the utility adjustments.
PAY ITEM No.2-PROJECT DESIGNATION SIGN:
The contractor shall construct and install two(2)Project Designation Signs and it will be the responsibility of
the contractor to maintain the signs in a presentable condition at all times on each project under construction.
Maintenance will include painting and repairs as directed by the Engineer.
It will be the responsibility of the Contractor to have the individual project signs lettered and painted in
accordance with the enclosed detail. The quality of the paint, painting and lettering on the signs shall be
approved by the Engineer. The height and arrangement of the lettering shall be in accordance with the enclosed
detail. The sign shall be constructed of 3/4" fir plywood, grade A-C (exterior) or better. These signs shall be
' installed on barricades or as directed by the Engineer and in place at the project site upon commencement of
construction.
The work,which includes the painting of the signs, installing and removing the signs, furnishing the materials,
supports and connections to the support and maintenance shall be to the satisfaction of the Engineer.
The unit price bid per each will be full payment for materials including all labor, equipment, tools and
incidentals necessary to complete the work.
PAY ITEM No.8—PROP. 18"ROCK RIP-RAP:
The following material specifications shall apply to all rock rip-rap. All rock rip-rap shall be roughly round in
shape with no dimension exceeding any other dimension by a ratio of more than 3:1. Required gradations are as
follows:
18"Rock Rip-Rap Gradations
_ Size '%Passing by Weigth
18" 100
15" 50-80
12" 0-40
8" 0-10
Filter fabric will be provided under all rock rip-rip placements. Filter cloth will be non-woven fabric and
provide an equivalent opening size(EOS)no finer than the U.S.Standard Sieve No. 100 and no courser than the
U.S. Standard Sieve No.70. Filter fabric will be considered subsidiary to the unit price bid per C.Y.for"18"
Rock Rip-Rap."
PAY ITEM No. 10-TRENCH SAFETY:
Description: This item will consist of the basic requirements which the contractor must comply with in order to
provide for the safety and health of workers in a trench. The contractor shall develop,design and implement the
trench excavation safety protection system. The contractor shall bear the sole responsibility for the adequacy of
the trench safety system and providing"a safe place to work"for the workman.
The trench excavation safety protection system shall be used for all trench excavations deeper than five(5)feet.
The Excavating and Trenching Operation Manual of the Occupational Safety and Health Administration,U.S.
Department of Labor,shall be the minimum governing requirement of this item and is hereby made a part of this
specification. The contractor shall,in addition,comply with all other applicable Federal,State and local rules,
regulations and ordinances.
Measurement and Payment: All methods used for trench excavation safety protection shall be measured by the
linear foot of trench and paid at the unit price in the Proposal,which shall be total compensation for furnishing
design,materials,tools,labor,equipment and incidentals necessary,including removal of the system.
PAY ITEM No. 12-TOP SOIL:
The proposed quantities shown are calculated to provide topsoil 4 to 6 inches in depth(compacted)over the
parkway area and do not include deeper than design depth behind the curb. The pay item is intended to pay for
topsoil that must be imported where suitable material is either not available on the job or cannot reasonably be
stored on-site. Payment will be made on the basis of loose truck volume(full truck with sideboards up)tickets
and material must meet City of Fort Worth standards for topsoil. Only the volume imported will be paid for and
may be substantially less than the proposal quantities listed.
i
2-I
PROJECT DESIGNATION SIGN
11/4
6' Citi o Fort Wort ,2V2" 31
1
11/4,
S V2'
s'
R- r-0ject Title
:
4"
11/2' Contractor:
1/2
211!• contractors Name
4.-0•
T 3/4"
w
V4 14 Scheduled Completion Date
11/2" Ye Q r
7w
I !
11/2"
4'-0'
LONGHORN WHITE (BLUE BACKSROMD W/WHITE LETTERS)
LETTERINO'CITT Of FORT WORTH-BOOKYAM DEMI ITALIC
PROJECT TPTL,E CONTRACTOR 6 DATE IN HELVETICA
{twgt>w/is s ..n m Q If 31
0f U
IYOp I :G l U� to J - 9 - G Z [:
Ilk
W _ W m u m 1 9
Nw H a � � _I
,Q = O �3 f
a ai. Z
N y
LL: _ a 3 0 3
m J '.....T: = Ny ZO 8# w EO ��
¢� K� - �o �
f;/ U m m
Or L'3 c o z
t9 O V a�p N _ LLJ
¢ j�U N 1 _ Eo ¢V `/ ^e
WCL
Z Bim` ,43 .N .Z
41�c.mm.m :a9 j GF.`n �i� �' `i •i ti W aEiU �a
e. ^IFFV2W v_oc Uj 3.m
h�nn000 � a.rc x+p bpi .... • rn W EarQ �° � Qg$de
O�N Z ,
e0 bbm.4l .� � Ei mFC I„pN (J OJ aN r - V 1 �6n ae
Qo a 4-.0 N
=x
1 H 1 9 oz
2
9 c ao 1 y 3Q a Tx m �{ yWat °-s-_ (nor€tl
O u Fo ¢ v�oo o 2'�l9 b bas m ti O &�f' r E m-3 0
�. •'h ti•nV °- Og5A-q,—+S'0+: > U I��1p �Ox NmE" 2n
ow
g41e �`0 ta��0
Qh mlv mmrn N y ~ aN R` 4•�2 W CL a wQE>, Ea
C1 Q M F`h h b y Q 0@ Oir
0 / -:. Q F - E- z _
q�0 .� _ ao
2 k as�1.i. N 1 _ 14
�
\2°iam nen ,21+N•.( � � � °°c oia
�V•0\\•�hnnn NNNN nnnnn NNiNNM 00°000'�'n ^+'nro Nryry rynnnnn�tyyNNNtty,00h 00hh Mn,�� r\nnhn NNNNN Oabwooqqrv�m�n'n•��' Nh'�.0^)'7'hM^l@@@@FQ QQQ hhV7hh bh h'n`•1bV"�Vlab Qp�b@hQ QQ M�h`�l yl yl ylb�M V19V Vl9�FhQ@@M`•Ihvlb hhyl ylM l9 l4V VVV
��'�2 o0 NNN Ra V7 wt9b\q nn��O NtiRRR rytiNtiry ryNNtihN b�9�9W C1\00�m 000001N,NNIN, NNtr h h "D-,o 000 ONNNNN trh Ftrhh
� NNNNN NNNMNN NNNNN ryNNNN NNNNMN
p�'Q 00'��`'\`1`fb b\om0 NNNNN NtiHNry NHNNry NNN^Oi^pi"oi b0m�Nh'�NN NNNNN nnnnn grno.p9Oo t� rn
NNNNN NNN^f'h'h NNNNN�ntrhQh has NNN h'll Nqi"0iR"Di
ate'\Z'�
� ��^IRRR h`nhh i9lvbla nnnnn��O�q�Ad000p O���la t9b19 i�l�f�,l�i� 0b�b-0,�dof,o,00000`��I�flrinl���rD�q gO�WOD OOti���
nn °+hhtrvF•nvF-v�u nnmm�'n hhhbb N•nPtl h•nPPPm�@hh CF' 'nhl"FPlnhhtD lNgPH4-Inhtrinh hQhhh P.Fhnhm
Q x�N NNn oot"19 lae�NINN NO 000E MhhVInm 019 t9 c9 VNNNPO 0D00 OON PFVV00 bNNN400000 b0 OON Py.V bOA
1lJ �Q@ ylh�bt9Vm t9n00 nn00`b\����\Nryd""��Vbgq bnD�\n D
\•\ '^`\' \ \ ^O�'`��\'�\�O�NN�h Vn00`n OON OO NN \\N NI\9 vl
U�O oVO�\q DOryN NFFb FVV VO4)00NN ggM•rynvlppy NNN
0
NhFF0 VVV0pp VVOO@OQlNNbO NhFhO b'DVOpp VVOOh 047NNV0
.�ti NNN'h ryN'h0 NN'ti"IF Nq^IQh MMFFF�O RNh•'�NN'h0 N`h^1QQ"1'•IhhQ 0"IQ hQ`�l NN0'hh N'n"ttrh 4�^1bF@'h"IFFhyI
Q¢Qovo'a og c 90 b�a�v'v9h' 'e a` ' mOa`h�u9a�g'9o�'oda`:do�w�hwro`�'om0t�t9eool9'rob�9o�\ a'ro b
mX NFh Q@b @Fb�9 Qb19� bbo lata ��y00h wb q
<} � .i.,.. ii . ..�. a0\rN.a\+�iN NNN��RRhti@V\\Qb�1910,b��RR��RRN�V\RRryH @V�9�R V��NOi NOi\9`9RRh b0 ryRh0
�} 'w"�'w0'�000 �'ro 'rom'mwro�'m�ro'ro�ro�ro�'�b�,himro�'�ro���v
0h hh@ nnnn m00tp ggqqq 000000 OOOp Op O z 000b ggo�plq 00000 00000`
���0 � ����0 ggq0.m 0000 00000���O�O
NH Nhh'ti'N.NN hHh�tih'��h�hrytiN'�'� ��ry h'�hN'H`'0'b�b Om0'b0 4bb0'm m000�0 '0\
�l V.nn qqq mtTmq 0000` �h'�INgIN�����VQV'C\@R00'0�' Vb'b' '%0 O000m 0
\ \
\'" 0W 00 ggqqq 0000000000 \ \\\ggqqq 0000000000\O n\0\
\J'�'0'c O Ah \hhn QylnO hyla�m.FylnO q\ Fyl trNN @'�nO FvinOq hv�ntpq\ Qtnn hy�n0 try n0�hyln 0q\
-w F OF0 OF°ON OhONV Otr ONV\ Ob 000 OQ� ON Oh0NV 0haon�V\ pV0 OVON OQ bNV 0b0NV\��� N MN NNNN NNN•9 NNN'n'h NNN`h'�Q NN NNN NNNq NNN'h•y NNN•'1'h@ NNN NNry'b NMN'h0 NNNM'9h
�'3'O� v V'�n hhia o41 ivi:h`n 19n0 rh�'v1:� 'ti.h Gin%a vhl'a.�a • \\•\• \ �\ \
i.ni.'n i�l�nl�l�hl�i�f�Inn nen���y'b \tel yo iN l�n� ON hN-�yt11NN 0,040' \�l�i�1V`ry NiN'`O LI�I�'�vl,'�I
CJ �0 ��'�����L\ \��\\\\^N�LtiryH NNN•L rttN LCL-�\-��\ �Y�<NNNNN hNNIL•4N NNNNN N'NNryN NKltiryry<vryN'�N•C
�'e nnnn NNNN HNnl�n gggqp44hjH Vnjnn 000189 tq9 lq9 l9Vb000N b00hnNn\\nNN VVl9aQ'h Vy) yV g00m\bV19Vq nnnngol
V Q � h0'•I'ry VF@b'QQ'�•ri'h FhhQ`n wl9wgm 4)aj0\0\voo°y hdvvh`�iHhh�b���b m��a�0 nt�a�lOa�fQ.m q^O�nnnh�000001a
r
O9..„ S� �ooOSoayhhh;h
��o� vva8 v'avv'@vaav vvv"vv Qvc�lh avohh'�v'hvc avo-ov v@Vhli"Qvovc hhhhhh'hv@v�rh@hhv ylhhv,y hh��hh
0�4 p i9Nb .,Ih�Oo,ai.i�°r.����ia ia`tah,�,1'l`Ta�N l9h ybbyM nnnvbl�'�by'r�'.h'O�n�'rov�n��iv'l""ama 0'o`ro'N I"Pi.i.
�1�Vy 2h kR4b ANA#Q AA§h44h 4A 44Rh 44*9p<a it k4 4A4444"t Z #Q''np
VVVVV NNNN 4)0.0 N,N VVVVV NNNO 0N00NN00 uV Va 000N OVVV VV'V VVV 00 ONVV VVOV
11mm�g���ryryN��:ggg
� � b`,vgbbopv`v'v�rer'hvb'hoa''n.h.H'•ny,hh;ash.y.`?4Q-.�'.00,Qtr'Q'hhh;nhtn�nh'htp�?m;su�stsgb:oFo;ntntnb;�nia�o'm�n;s:aiats�p. \s
O Zd N"fh`n^1Qyl ls'hhvl l9n QH\9n�'�Vn�q hlo^OqO h'F yl t9^I<l yf i9't�Q'�I l9l�q hyyb��r:'vq yt iCn�g00'hGyl lan9l.�•119n0 V)C9 i:�d Yl i9lnbdp
OC gOOn has ON 0ty\NOq ONhy]N y10Nq N`h 09�y)0 MONO 19�A0 y���A bQl09nQ mh Oyl Q'0tl O�
y V' aMN\hC9W0FOVnV\O'hh191� q\oItrON\O Ovlpvl\V\Nd\.�
V(l"I NU
Vnn000g0�y\N'hO'\'h'9Vh00 n0q\nn00.y q�0'\\\\Va h1009O^On QD�MN�\\1b\R�0Rhi 4hinq�\'A��
�h 'o'S'o'o b o ob o 0 0 0 0'o ob'o��'-M'^�'M.M;�:�5r1'•�,;n;�'o b'o'o'o'o o b o�'�\' ' \ .\...
rOho 4 v,t��ai:In'lvi:v ti�io�:�m :roulo bgg�H
e2°� h191�°J��O I�md00 �,rogg�NM Vn0g0 n!p.olO��q`O->1.ry�d0-�`'\
INYy`M`IN i.n�b 0�.t9 41 SA'+C/W�OI 1�!�'n`�^+o(v+1+ . , . •N. . \ \
191919b H rohm nnn bbl9y
Aq AA hA44 k@4h444 A444p!h!�R 4§q t s a @t4 YQ4!444 A14 4
e NNNO O NN 0NN41
�0-6$ry��ryry h�y��goa vwmm ml�'vm mroroa�h�� �s� m�� �bo�oblabuwa
N RO`�`b0"bb �t9
0, OOppb nnbO 11ggbVVV hVVVO� lOV VVVV VI9^)4fFQ hh•nVV OQhtrm bFh\\hmoiq 0h
e ryNNM Qhhh VVnnh NNN'h V�9U\O OOODDO nn00 trFV1gq V
000nnh000 ONN 0VV �4S Nn�Rbymo Npq NONN hvlbgq�.
NNN'7'7 pp n h V b\0 0 N N V
J� '7'7 FQFFQ 49VVVV gm\"�\\\Q.QbQ hHh`hh nnnnn o0 oD0\h��`\VV Vbta.Ogolgqn NNN byIN'9 VIV
0.0•\-\.�\.x..0.0.\.0.
��� 'wro�'omro,3o�`v000}u'�;o,@b �3ob'o,o�,op'poro'�o'o��oP,Brobbgb'goo;obobb0000roro�°•°ro's.�O'oo'oo_D`ob0000b
1�0� Hhhhcclo bii ni.l:inn�mavq°''°goo 000 uis-oma nnnnn 0M00q gdmoo oob�C:is nasi:r: a gb��':
�mrovm a,o,Qog.,
Q~O �q agml�f0hf�io labia tv 000q).0 b1w919�m�'0�^at;'"nN��1vb�00'tnt9 t�91�'aml�'a'V�(b�0(0�n':nnl0
Aq�A49AAAk0.AAp@§d'ktl'A§ kRA4 A ZIP k#�ii44! �!Y 44R§�k hRS4 k 411(!,-klkk 4 it #b_k
FFO\\000'ry^I^10000000"1'h FFFFF 00 0 '•10000 0°FFb 0000 O�OQpb 4�¢�
V Vb V�000V19 VVVnnn bVbVlab Vhn.00000 V19�V1�nnnnnW n0000 RV It nhOOVSbwlg t4Vn
NNNq^)'•IbV hhnnlxV�V00VIN yyl y)Vb'VVbV VV Mhbtr FFh-bu Opp.Qhm bFb\\hggqqO hNV VV VNNNm hhO NnNylmm\
�+�0000000hI y�NNO�'96 'O bFO� O�Otl OO nh000Fygq^Khn O ONN 00VV 00 Nny�0+p pO
¢¢ NNNN@@@bylh`7 VVbl9V nnt�in gmgm�+�,0,0hti`hOQF nnnn Og'000 NNh N{� VVbVb D6+gR���rya
�rororororo m��bm�bo�o'r0000�;S,o'oo°o'o'ooD o0obob w'oa' 'obb 'o b'o bo hh �Oti��oobAroroo'D'ob'000b$R Rkb 'o'o'obb
R ^Yh VQO hh�nbi949 ca is nnnnn om0rc,a a`gaoo 006��:i9vi9�nnnnn-�0$�Om mggoo
¢Ogoo.��:i.r:r:Ri.�aawga�olrnd000'o:�.\.
�ti '�i.ca'oicrorororo m¢Imgafom�i�nnb'o0mm�'0nr�1�°j` �a�c+3"ro�ro�b �1..i.i.''�N�'laia��avvro'm�o�� �"' �faa�
9 9 v
Z a R k A 4 i R kq 4 4 i A 1 p k k R; k A R R b 4 a k A A k�knnnn 4b4 0R A R! }4�4�9
\Z rovmmol�c0a t9 l0a R5lz�
as�04nn nnnnn 1F9�1F9VV 109 t0a t0s l�[I�n b109 t09�109�t9nn�mm$ro C09 t0a 10910919 mm�nn� n'v0�m�10919 c0a 14 nn4Sro$:5t
h 4;N00vl g1nn\VO9jf ^V1n VVnn�nUat000��'�O ti�'09`�N`a 19Vn0 VR000•.iF 19 a \\0^i\Ao'.nN gin\\n'q '��40OOppj"VV�•90`VV
4' b0q 0m�g �-A, nOgO�QO`hNOt ��Qyu N�6n`4`1\Iry
jQ¢2Wp nNnNhq"0l "niO^nfoh0`�i�VhHNln Obnni�n�iap4a aQb0^hib�OOry"Nib VO^Oi t1�q'h\ b�nQb NUbnO`OOhnn Ql b`n y�NM 00°0
CNh N N`N q�lrygF gR�vl`0p y�^��9yF 0'y IOb ONN 1900.'hObOmm
ylyal tOn VVn00 Vas Dam'9FFy QFy)V)b 19V�Vn bn�0 n00 q 6p hFl , VVnO n0mm 0�0 m0p
b NV°OOD000000 bO00 p0000 D000o Oba00000000000D ODDOO DOOpp O00�00 D�0'00\ o0c5D00400D'�00000D OO\0
WSFh40 r;0�V0 1p O.14� F0^�vt plaglh��mMmgn V hOYO rN pp O h°�� hNFoV OOmPhN hasty 049mV qN0 Mm Mhh`Nb0
h IN hm 0.bi�40NP NAhtm9 o,0yhithp••`4,VIW wWwr N OFO Ntm9 �m19m'� nOh PO Pmo9NmkINN k�h�pb�h hh�Ohm MSO^ OO
I.� Q �'\�•�q 0,\ qn4� q Nti^>'^i'S•^i�^�'4R 0M1 Nlm•1 � .N b0yt 990 PO N�#0 Oh nO'�•1 i9Q hb�
Q Q NNNN NN^]^i Ni"'i 9Y'T'"1-tr'p7V yl'N'K.y pW'h'19'14 nn-n• 4I'b-R'tl y"r`n`tb9'�1�y9'lm9`l9'lM9'109'yNln�-gyh"^T'TRF"�4`T h"•(t9 lv V_�9 nen l�•n.n.ti�o+
OhQ 0W'C Na Olb9^binCOb bb�1V�1u9 y�yyy0 NgVbM hti,'�11q nh.��t^9 Ay�, �b�� b�\q nh��'�N�1��bq ynhf�oH!4.�1�•¢`N5i �bO\A�"'hOV VNnylm ^tno
O P V nO:'���`:�R�bhry�rvNNN rytiN•IOi"t"1^0i'Nih^`�iQ^5^Fi"010 b�f�ntih°NNNN ti�"01MT^O'�"Nf'1'0hh^Sas o'V O.V q�Vi�91�199M�'Fin`il yl�`�'{M'�V 00yRj�q
hN NN NN•n^t MM�I�F 4]•hF bb
77&:YYiY C\NNN q`m^00 aD�0Vi 19�9 t9 i9191919191D 191919191919 1919 i9(919N OOOa ip ip iO Cly Amo)m E, E)to Cram i 4 6, 000 000000 OHO OOOs\
T2-E,
'tu"'ir:r'^.nnn ro��oo0www�wa
NO/1.750 \\NNN.NN'h^I NN^]^'1^1 N^1^]^1^I'�]^]^J'h^]^t`•1'N^t^'l^1 NN•9^7 NN^I^1^I N^I^1^lM•9'h^f'y^1'h^l'h'�'yh NN43M^1N'h'h'•1'9'y^]'h•��h'h 41'h^1•nM
ddf1
jW Z NM NK97 NM9'71nMQ1AN InQhtor a#9 toren YI..mm....TO Mpt19 tD InQ�1or v+n toren vl nor@oI to lormOlQ l.lahmr alas lDrW vl lormm Nfor mTO
N x x x x x x x - _
GN-OS 8N-3S SN-SS
EQUIPMENT SCHEDULE
List of Equipment owned by Bidder that is in serviceable condition and
available for use:
Portions of work Bidder proposes to sublet in case of Award of
Contracts including amount and type:
EXPERIENCE RECORD
List of projects your organization has successfully completed:
Amount Of Contract Type of Work Date Accepted Name and Address of Owner
Award
r
List of projects your organization is now engaged in completing:
Amount Of Contract Type of Anticipated Name and Address of Owner
Award Work Date of
Completion
F
M' List Surety Bonds in force on above incomplete work:
^� Date of Contract Award Type of Work Amount of Name and Address of
i Bond Bond Surety
N
d
FROM : EMPLOYERS COMP FAX N0.
05/12!uu rata vt:iv r4A May. 12 2000 02:47PM P2
CF.RTIl�'t�_OF IN51�'$,L►jJCB
TO: CITY OF 1 ORT WORTH Dau; 5/12/00
N A.M a OF PROJEC I'.
PRO' ECT NUMBED.:
— IS TO CERTIFY TF.&.T: CW Ooastruction, ITbc.
is,at the date of this :esti rote,Insured by this Company with respect ro Ow bueinecs opexotlous has;hietler dum'bcd,for
the type of io,ur000t and accordance with yrovkiow of*0 standard policies used by this Couq ahay,end flkKh$r
Ix-rainaftar deseribet Fszceptims to nandord policynosed oo mveree aide bereaf.
WINK
r p Ethictive Rxamm heaths of L'
Workces,Com ensatio 378/00--
Comprehensive Gmtcrs Bodily Nw.
Liability insurance(Publ c Ea.Ocixtro cc S
Liability) Properly Dump!
Collapse of Building oti
OrucluVU adjacent to EL 00mmnee: S
cxcavatioma
Don tc to undergrowu
Utilities 8a."- S
Buaft's Risk
Comprehensive Bodily GglettY
AutomobileLialAlity Es.Person: S
Ea.Ocan tnov:S
Properly X)kmw~
Ea. .S
Bodily Injury;
Contractual Liability FAI-OcchasoMes S
Property DaA -,
— Ira S
Odepr
Locations Covered;_
Dacrfptioe of opwat ms coven
The above policies ei ser in the body thereof or by rppropriste eodora=cm provided drat they may trot be cha ged or
cgncclod bythe in"w r m less than five(3)days of a the inamd has received written notice of such chmjWor
cancethatian.
Where applioable los I laws or Togulatia<s rcquire more iteral five(S)dray#actual nntiras of Chante or cancalla m to be
assured,the above pu sales c"Win such special requirerttmta,either nh the body thereof or by mWoptiato endo"ement
thereto attae]md.
Agogi Dnployer's 99M Asaociatesr Inc.
F�r Wanh AgMt By
Ad&"s 16801 Addisqn ltd. #325 Title
Addison, '1'x 75001
ACORDn„ CERTIFICATE OF LIABILITY INSURANCE DATE
05 24/2000
PRODUCER 1 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
Coble-Cravens Insurance Agezicy ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
202 E. Border, Suite 201 ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
P. O. Box 429
TX 76004
Arlington, TINSURERS AFFORDING COVERAGE
A
INSURED CNJ Construction, Inc. INSURER A: MARYLAND CASUALTY CO
955 Cedarview INSURER B: SOUTHERN COUNTY MUTUAL INS CO
Cedar Hill, TX 75104 INSURER C:
INSURER D:
CNJCO2 INSURER E:
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES.AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR TYPE OF INSURANCEPOLICY NUMBER POLICY EFFECTIVE POLICY EXPIRATION LIMITS
A GENERAL LIABILITY SCP36318732 03/10/2000 03/10/2001 EACH OCCURRENCE $ 1000000
X COMMERCIAL GENERAL LIABILITY FIRE DAMAGE(Any one fire) $ 300000
CLAIMSMADE [i] OCCUR MED EXP(Any one person) $ 10000
PERSONAL&ADV INJURY $ 1000000
GENERAL AGGREGATE $ 2000000
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS-COMP/OPAGG $ 2000000
POLICY PRO LOC
B AUTOMOBILE LIABILITY CT108570 0206/2000 02/062001 COMBINED SINGLE LIMIT
(Ea accident) $
ANYAUTo 1000002
ALL OWNED AUTOS
BODILY INJURY $
X SCHEDULED AUTOS (Per person)
X HIRED AUTOS
BODILY INJURY $
X NON-OWNED AUTOS (Per accident)
PROPERTY DAMAGE $
(Per accident)
GARAGE LIABILITY AUTO ONLY-EA ACCIDENT $
ANYAUTO OTHER THAN EA ACC $
AUTO ONLY: AGG $
A EXCESS LIABILITY BND-CNJCO2- 58351 03/10/2000 03/10/2001 EACH OCCURRENCE $ 1000000
OCCUR ❑CLAIMSMADE AGGREGATE $ 1000000
DEDUCTIBLE ` $
RETENTION $ $
WC STATUS OETH-
R
W ORKERSCOMPENSATION AND
EMPLOYERS'LIABILITY E.L.EACH ACCIDENT $
E.L.DISEASE-EA EMPLOYEE $
E.L.DISEASE-POLICY LIMIT $
OTHER
DESCRIPTION OF OPERATIONSA.00ATIONSNEHICLESOEXCLUSIONS ADDED BY ENDORSEMENT/SPECIAL PROVISIONS
Job: Storm Drain improvements for Como Drainage System.
CERTIFICATE HOLDER ADDITIONAL INSURED; INSURER LETTER: CANCELLATION
Nikki McLeroy SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
City of Ft. Worth DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN
1000 Throckmorton NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,BUT FAILURE TO DO SO SHALL
Ft. Worth, TX 76102-6311 IMPOSE NO 0131.14G,7N OR LIABILITY OF ANY K UPON JE INSURER, ITS AGENTS OR
REPRESENTATIV
AUTHORIZED RE EN TIV
I - I PLM
ACORD 25-S(7/97) 0 A 6ORD CORPORATION 1988
CONTRACTOR COMPLIANCE WITH
WORKERS' COMPENSATION LAW
Pursuant to V.T.C.A Labor Code Section 406.096,Contractor certifies that it provides workers'
compensation insurance coverage for all its employees employed on city of Fort Worth Project Number C111-
030111028886
CNJ CONSTRUCTION INC.
CONTRACTOR
R n �.
Title
" 5 %0) - m
Date
STATE OF TEXAS §
COUNTY OF TARRANT §
BEFORE ME,the undersigned authority,on this day personally appeared fc�y1 s. Wa 14rS
known to me be the person whose name is subscribed to the foregoing instrument,and acknowledged to me that he
executed the same as the act and deed of C-FJ I &onsfrctc fioN, SAC for the purpose and consideration
therein expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this day of
. 20
Notary Public in and for
the State of Texas
ANDREA WALTERS
NOTARY PuBUC
State of Texas
COMM. E
........• xp 10-03-2001
CITY OF FORT WORTH, TEXAS
CONTRACT
THE STATE OF TEXAS
KNOW ALL MEN BY THESE PRESENTS
COUNTY OF TARRANT
JUL 112000
This agreement made and entered into this the_day of A.D., 19 by and
between the CITY OF FORT WORTH, a municipal corporation of Tarrant County, Texas,
organized and existing under and by virtue of a special charter adopted by the qualified voters
within said City on the 11 b day of December, A.D. 1924, under the authority (vested in said
voters by the "Home Rule" provision) of the Constitution of Texas, and in accordance with a
resolution duly passed at a regular meeting of the City Council of said city , and the City of Fort
Worth being hereinafter termed Owner, C11'110 CONSTRUCTION, INC. HEREINAFTER
CALLED Contractor.
WITNESSETH: That said parties have agreed as follows:
1.
That for and in consideration of the payments and agreements hereinafter mentioned to
be made and performed by the Owner, and under the conditions expressed in the bond bearing
even date herewith, the said Contractor hereby agrees with the said Owner to commence and
complete the construction of certain improvements described as follows: STORM DRAIN
IMPROVEMENTS OF COMO DRAINAGE SYSTEM
2.
That the work herein contemplated shall consist of furnishing as an independent
contractor all labor, tools, appliances and materials necessary for the construction and
completion of said project in accordance with the Plans and Specifications and Contract
Documents prepared by the Department of Engineering for the Transportation and Public Works
Department of the City of Fort Worth adopted by the City Council of the City of Fort Worth,
which Plans and Specifications and Contract Documents are hereto attached and made a part of
this contract the same as if written herein.
3.
The Contractor hereby agrees and binds himself to commence the construction of said
work within ten (10) days after being notified in writing to do so by the Department of
Engineering of the City of Fort Worth.
The Contractor hereby agrees to prosecute said work with reasonable dilJ10^1 } Qei�I
commencement thereof and to fully complete and finish the same ready for the inspection and
approval of the Department of Engineering of the City of Fort Worth and the City Council of the
City of Fort Worth within a period of TWENTY FIVE (25)working days.
If the Contractor should fail to complete the work as set forth in the Plans and Specifications and
Contract Documents within the time so stipulated, plus any additional time allowed as provided
in the General Conditions, there shall be deducted from any monies due or which may thereafter
become due him,the sum of SIXTY THREE DOLLARS($63.00)
Per working day, not as a penalty but as liquidated damages, the Contractor and his Surety shall
be liable to the Owner for such deficiency.
5.
Should the Contractor fail to begin the work herein provided for within the time herein
fixed or to carry on and complete the same according to the true meaning of the intent and terms
of said Plans, Specifications and Contract Documents, then the Owner shall have the right to
either demand the surety to take over the work and complete same in accordance with the
Contract Documents or to take charge of and complete the work in such a manner as it may deem
proper, and if in the completion thereof, the cost to the said City shall exceed the contract price
or prices set forth in the said plans and specifications made a part hereof, the Contractor and/or
its Surety shall pay said City on demand in writing, setting forth and specifying an itemized
statement of the total cost thereof, said excess cost.
6
Contractor covenants and agrees to indemnify City's engineer and architect, and their personnel
at the project site for Contractor's sole negligence. In addition, Contractor covenants and agrees
to indemnify, hold harmless and defend, at its own expense, the Owner, its officers, servants and
employees, from and against any and all claims or suits for property loss, property damage,
personal injury, including death,arising out of, or alleged to arise out of,the work and services to
be performed hereunder by Contractor, its officers, agents, employees, subcontractors, licensees
or invitees, whether or not any such injury, damage or death is caused, in whole or in
Part, by the negligence or alleged negligence of Owner, its ofFcers, servants, or
employees. Contractor likewise covenants and agrees to indemnify and hold harmless the
Owner from and against any and all injuries to Owner's officers, servants and employees and any
damage, loss or destruction to property of the Owner arising from the performance of any of the
terms and conditions of this Contract, whether or not any such injury or damage is caused
in whole or in part by the negligence or alleged negligence of Owner, its officers.
servtirts or employees..
In the event Owner receives a written claim for damages against the Contractor or its
subcontractors prior to final payment, final payment shall not be made until Contractor either(a)
submits to Owner satisfactory evidence that the claim has been settled and/or a release from the
claimant involved, or (b) provides Owner with a letter from Contractor's liability insurance
carrier that the claim has been referred to the insurance carrier.
The Director may, if he deems it appropriate, refuse to accept bids on other City of Fort Worth
public work from a Contractor against whom a claim for damages is outstanding as a result of
work performed under a City Contract.
II 47.
h 8'
Qffy
The Contractor agrees, on the execution of this Contract, and before beginning work, to
make, execute and deliver to said City of Fort Worth good and sufficient surety bonds for the
faithful performance of the terms and stipulations of the Contract and for the payment to all
claimants for labor and/or materials furnished in the prosecution of the work, such bonds being
as provided and required in Article 5160 of the Revised Civil Statutes of Texas, as amended, in
the form included in the Contract Documents, and such bonds shall be for 100 percent of the
total contract price, and said surety shall be a surety company duly and legally authorized to do
business in the State of Texas, and acceptable to the City Council of the City of Fort Worth.
8.
Said City agrees and binds itself to pay, and the said Contractor agrees to receive, for all
of the aforesaid work, and for all additions thereto or deductions therefrom, the price shown on
the Proposal submitted by the successful bidder hereto attached and made a part hereof. Payment
will be made in monthly installments upon actual work completed by contractor and accepted by
the Owner and receipt of invoice from the Contractor. The agreed upon total contract amount
(including/excluding) alternates N/A, shall be TWENTY THREE THOUSAND SIXTY SIX
AND80/100......................................................................................................
($23,066.80)
9.
It is further agreed that the performance of this Contract, either in whole or in part, shall
not be sublet or assigned to anyone else by said Contractor without the written consent of the
Director of the Department of Engineering.
10.
The Contractor agrees to pay at least the minimum wage per hour for all labor as the
same is classified,promulgated and set out by the City of Fort Worth, Texas, a copy of which is
attached hereto and made a part hereof the same as if it were copied verbatim herein.
11.
It is mutually agreed and understood that this agreement is made and entered into by the
parties hereto with references to the existing Charter and Ordinances of the City of Fort Worth
and the laws of the State of Texas with references to and governing all matters affecting this
Contract, and the Contractor agrees to fully comply with all the provisions of the same.
IN WITNESS THEREOF, the City of Fort Worth has caused this instrument to be signed in 8
counterparts in its name and on its behalf by the City Manager and attested by its Secretary, with
the corporate seal of the City of Fort Worth attached. The Contractor has executed this
instrument through its duly authorized officers in 8counterparts with its corporate seal attached.
JUL 112000
Done in Fort Worth, Texas,this the day of ,A.D., 19
RECOMMENDED: CITY OF FORT WORTH
BY:
U Ile WOO LIVI Va.
DIRECTOR,DEPARTMENT OF CITY MANAGER
ENGINEERING
APPRO
TRANSPORTATIONT1 LIC WORKS
DIRECTOR
ATTEST:
CNJ CONSTRUCITON,INC.
955 CEDARVIEW
CEDAR HILL,TX 75104
CONTRACTOR '
CITY ECRETARY
(SEAL)
B `� 5
TITLE
APPROVED AS TO FORM AND
LEGALITY:
ADDRESS
ASSI CITY.ATTORNEY
Contract Authorization
November 1960 _
Revised May 1986 r ��
Revised September 1992 Date
Clff19NLS�G?� 1"lly
H7