HomeMy WebLinkAboutOrdinance 15869ORDINANCE NO ~OJ ~`~~
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
`"~ APPROPRIATIONS IN THE SEWER CAPITAL PROJECT FUND IN THE
AMOUNT OF $97 451.80 FROM AVAILABLE FUNDS FOR THE PURPOSE OF
FUNDING CHANGE ORDER NO 3 TO CITY SECRETARY CONTRACT NO
28773 WITH OMEGA CONTRACTING, INC. FOR WATER AND SANITARY
SEWER REHABILITATION REPLACEMENT CONTRACT 2001 STM-L,
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND
REPEALING ALL PRIOR ORDINANCES IN CONFLICT HEREWITH, AND
PROVIDING AN EFFECTIVE DATE.
BE TT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year 2003/04 and in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the
Sewer Capital Fund in the amount of $97 451.80 from available funds for the purpose of funding Change Order
No. 3, to City Secretary Contract No 28773 with Omega Contracting, Inc. for Water and Sanitary Sewer
Replacement Contract 2001 STM-L.
SECTION 2.
Should any portion, ection or part of a section of this ordinance be declared invalid, inoperative void for any
reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the
remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall be and
remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No 15636 and all other ordinances and appropriations
amending the same except in those instances where the provisions of this ordinance are in direct conflict with
such other ordinances and appropriations, in which instance said conflicting provisions of said prior ordinances
and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY
G
Assistant City Attorney
ADOPTED AND EFFECTIVE. ~) ~~ ~'
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION Approved on 2/10/2004 Ordinance No 15869
DATE Tuesday February 10 2004
LOG NAME 30STML CHANGE 3
REFERENCE NO *C 19959
SUBJECT
Appropriation Ordinance and Change Order No 3 to Contract with Omega Contracting Inc. for
Water and Sanitary Sewer Replacement Contract 2001 STM-L
RECOMMENDATION
It is recommended that the City Council.
1 Authorize the transfer of $97 451 80 from the Water and Sewer Operating Fund to the Sewer Capital
Project Fund and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Project Fund in the amount of $97 451 80 from available funds, and
3 Authorize the City Manager to execute Change Order No 3 to City Secretary Contract No 28773 with
Omega Contracting Inc. in the amount of $97 451 80 for additional and increased pay item quantities,
thereby increasing the contract amount to $1 029,231 49
DISCUSSION
On April 29 2003 (M&C C-19558) the City Council authorized the City Manager to execute a contract with
Omega Contracting Inc. in the amount of $909,247 69 for Water and Sanitary Sewer Replacement
Contract 2001 STM-L. The contact was subsequently revised by two change orders as follows.
Change Order No 1 provided 60 additional calendar days to construct the project; and
Change Order No 2, in the amount of $22 532.00 provided for the replacement of a 260 foot
segment of a previously unknown severely deteriorated sewer lateral that was encountered during
construction at the immediate downstream end of a project sewer lateral (L 11780)
This project includes replacement of the existing undersized deteriorated water main located on Grayson
Street from Cravens Road to the IH-820 frontage road Currently the City does not provide sanitary sewer
service on the street, which has several vacant lots and the existing residences utilize private septic tanks.
The street is scheduled for reconstruction by the Transportation and Public Works Department after the
water main is installed
It is anticipated that the majority of the vacant lots on the street will be developed once the water main is
replaced In order to avoid cutting new street pavement in the near future to install a sanitary sewer lateral
staff recommends the sewer line be installed in conjunction with this project. The existing residents on the
street will be offered the opportunity to connect to the sewer main
Staff considers the proposed change order amount to be fair and reasonable and recommends approval
Logname 30STML CHANGE 3 Pale 1 of 2
Omega Contracting Inc. is in compliance with the City's M/WBE Ordinance by committing to an additional
17% M/WBE participation on this Change Order No 3 The City's goal on this change order is 17%
This project is located in COUNCIL DISTRICTS 5 Mapsco 79Y and Z.
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval of the above recommendations and adoption of the
attached appropriation ordinance funds will be available in the current capital budget, as appropriated of
the Sewer Capital Project Fund
TO Fund/Account/Centers FROM Fund/Account/Centers
1 &2) PS58 472045 070580175670 $97.451.80 3) PS58 541200 070580175670 $97,451.80
2) PS58 541200 070580175670 $97.451.80 1) PE45 .538070 .0709020 $97,451.80
Submitted for City Manager's Office b~ Marc Ott (8476)
Originating Department Head. A. Douglas Rademaker (6157)
Additional Information Contact: A. Douglas Rademaker (6157)
Logname 30STML CHANGE 3 Page 2 of 2