HomeMy WebLinkAboutOrdinance 18946-12-2009Ordinance No. 18946-12-2009
AN ORDINANCE fNCREASING THE ESTIMATED RECEIPTS AND APPROPRIATfONS
IN THE SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF $115,056.00, FROM
AVAILABLE FUNDS, FOR SANfTARY SEWER REHABILfTATION CONTRACT LX X60},
PART 2; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDfNANCE
CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR ORDINANCES
IN CONFLfCT HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2009-2010 and
in the Budget of the City Manager, there shall also be increased estimated receipts and appropriations in
the Sewer Capital Projects Fund in the amount of $715,056.OO, from available funds, for Sanitary Sewer
Rehabilitation Contract LX X60}, Part 2.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way
impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining
provisions shall be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance No.18809 and all other ordinances and appropriations
amending the same except in those instances where the provisions of this ordinance are in direct conflict
with such other ordinances and appropriations, in which instance said conflicting provisions of said prior
ordinances and appropriations are hereby expressly repealed.
SECTION 4,
This ordinance shall take effect upon adoption.
APPROVED A/ S~FjO FORM ANB-~~GALITY:
~` ~ ~
Assistant qty AttQ~y(ey
ADOPTED AND EFFECTIVE: December 8~ 2009
MAYOR AND COUNCIL COMMUNICATION MAP
ORDINANCE NO. 18846-12-2008 60SS60P2-BURNSCO
City of Forf Worth, Texas
Mayor and Council Communication
;J. ~ ~,;;4~i.~x;~,.,x a ";4ic a~ ~~~~ ~\: ~,~. <u \ ; t x •\; ',b\;'sc wi . ~' t •c,i a~,wu..~
.. , , , , .. o' M . 't. , ,~;zy,,,~c ti?i: r ?i,. ;3~Y3S„ x3~'S~ F~' ~ .;t,,,:~ ,• ~' ~., \a•'~' ~,.:~: ~~ ~~\ , i:aSy ~ o- ~ , ~.,,.,
C~UNCL AGT~ON; Approved an 1ZI8I2~0~ ~ Card. No.1894fi~1~~~Q~
.r ~ ~~%y~\.~,,.CW4.{{,'+L'tlC'+AO$.~~f~~~'~~t~~{ii~': ~i~{~',~'j~,~+?W~;Y:,; ~,.5.> '+~;5 ::~,~v`;,~3, i:34~a4"n. ~ h ~ ~~' ~'\,'~+, ;':~; }. ~o\~i~\,~\'\,, '\,J'•\i i' »\, k:'
:'- : , ~ : , ,.4 < i ~`~:,`~~`Vk'~'~i(~`o}r/'4'43, - ~~r~ ~'~~#.~'. ~,. ,.~ L°l~p nb.~ %`~..~:v. ?`:..: \... t E\ ........ .... .i'', i, t \ "", ~ r,a . «~\\
, ... ,,, , R,t , , ,• \,
DATE: Tuesday, December 08, 2009 REFERENCE ND.: **C-23951
LoG NAME: 60SS60P2-BURNSC~
SUBJECT:
Authorize a Contract in the Amount of $658,055.80 with Burnsco Construction, Inc., for Sanitary Sewer
Rehabilitation Contract LX, Par# 2, on Tierney Road, Tierney Court North and Adopt Appropriation
Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the transfer of $715,056.00 from the Water and Sewer operating Fund to the Sewer Capital
Projects Fund;
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Projects Fund in the amount of $715,056.00 from available funds; and
3. Authorize the City Manager to execute a contract in the amount of $658,055.80 with Burnsco
Construction, lnc., for Sanitary Sewer Rehabilitation Contract LX X60}, Part 2.
DISCUSSION:
On February 24, 2004, (M&C C-19973) the City Council authorized the City Manager to execute an
Agreement with Wade & Associates for Sanitary Sewer Rehabilitation Contract LX (60).
This project, Part 2, consists of the replacement of the deteriorated sanitary sewer mains on Tierney Road
(Brentwood Stair Road to Barnett Street) and Tierney Court North (Tierney Road to West Cul-de-Sac).
The project was advertised for bid on July 30, 2009 and August 6, 2009, in the Fort Worth Star-Telegram.
4n September 3, 2009, the following bids were received:
Bidders , .Amount ......u ......Time of _Compl
etion
Burnsco Construction, Inc. $658,055.80150 Calendar Days
Tri-Tech Construction $141,132.00
Conatser Construction TX, LP $113,952.50
Jackson Construction, Inc. $113,952.50
........................ .
:William J. Schultz, Inc., dlbla Circle "C"Construction Co. $198,215.00
... ... ..................
Burnsco Construction, lnc., is in compliance with the City's MIVVBE ordinance by committing to 11 percent
MIVUBE participation. The City's goal on this project is 11 percent.
Lo~name; bOSS60P2-BURNSC4 Pale 1 of 2
In addition to the contract cost, $32,000.00 is required for construction staking project management,
material testing and inspection and $25,000.20 is provided for project contingencies.
This project, Part 2, is located in COUNCIL DISTRICT 8, Mapsco 65X.
FISCAL INF~RMATI~N !CERTIFICATION:
The Financial Management Services Director certifies that upon approval of the above recommendations
and the adoption of the attached appropriation ordinance, funds will be available in the current capital
budget, as appropriated, of the Sewer Capital Projects Fund.
FUND CENTERS:
TO FundlAccountlCenters
1 &2 P258 476045 7011701006ZZ
2~P258 531350 701170100652
2} P258. 541200 701170100687
2} P258 531200 701170100684
2} P~58__ _531350 701170100684
2] P258 531350 701170100685
FRAM FundlAccountlCenters
715 056.00 1 PE45 538040 0709020
$6,000.00 3~ P258 541200 701170100687
683 056.00
4 000.00
2 ooa.oo
~Za,ooo.oa
715 056.00
658 055.80
CERTIFICATIONS:
Submitted for Cit Mana er's office b
~rig.inatn~Department Head:.
Additional Information Contact:
Fernando Costa (6122)
S. Frank Crumb (8207)
Susan Schwinger (6529)