HomeMy WebLinkAboutOrdinance 15355ti
_. ~, ~~
Ordinance No ~~~-~.J
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE SEWER CAPITAL PROJECT FUND IN THE
AMOUNT OF $78,481.50 FROM AVAILABLE FUNDS FOR THE PURPOSE OF
FUNDING AMENDMENT NO 3 WITH DUNAWAY AND ASSOCIATES, INC FOR
THE DESIGN OF A SANITARY SEWER LIFT STATION TO PROVIDE
WASTEWATER SERVICE TO THE GREENWAY ADDITION MODEL BLOCK,
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES IN
CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS
SECTION 1
That in addition to those amounts allocated to the various City departments for Fiscal Year 2002-
2003 in the Budget of the City Manager, there shall also be increased estimated receipts and
appropriations in the Sewer Capital Project Fund in the amount of $78,481 50 for the purpose
funding Amendment No. 3 with Dunaway and Associates, Inc. for the design of a sanitary sewer lift
station to provide wastewater serviced to the Greenway Addition Model Block.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid,
inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or
judgment shall in no way impair the remaining portions, sections, or parts of sections of this
ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No 15184 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance
are in direct conflict with such other ordinances and appropriations, in which instance said
conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed
SECTION 4
This ordinance shall take effect upon adoption
APPROVED AS TO FORM AND LEGALITY
t -~/
Assistant Attorney
ADOPTED AND EFFECTIVE. f`~ ~ ~~
City of Fort Worth, Texas
Mayor and Council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
12/3/02 **C-19371 60DUN 1 of 2
SUBJECT APPROPRIATION ORDINANCE_AND .AMENDMENT N_O 3 TO THE ENGINEERING
AGREEMENT WITH ~DUNAWAY AND ASSOCIATES, INC ~ FOR THE GREENWAY
ADDITION MODEL BLOCK" -` `~ " `- ' ~`` ~J
RECOMMENDATION
It is recommended that the City Council
1 Authorize the transfer of $78,481 50 from the Water and Sewer Operating Fund to the Sewer
Capital Project Fund, and
2 Adopt the attached appropriation ordinance increasing estimated receipts and appropriation in the
Sewer Capital Project Fund in the amount of $78,481 50 from available funds, and
3 Authorize the City Manager to execute Amendment No 3 with Dunaway and Associates, Inc. for the
design of a sanitary sewer lift station to provide wastewater service to the Greenway Addition Model
Block, thereby increasing the amount of the contract by $78,481 50, from $244,251 30 to
$322,732 80
DISCUSSION
On Jufy 11, 2000 (M&C C-18120), the City Council authorized $1,200,000 00 to fund the Greenway
Model Blocks program for reconstruction of roadways, gutters, curbs, and sidewalks within the
Greenway Addition
On October 2, 2001 (M&C C-18759), the City Council authorized the City Manager to execute an
engineering agreement with Dunaway and Associates, Inc in the amount of $203,647 50 for the
preparation of plans and specifications for water and sanitary sewer relocations for the Greenway
Addition Model Block.
On March 19, 2002 (M&C C-18998), the City Council authorized the City Manager to execute
Amendment No 1 in the amount of $29,453 80, thereby increasing the contract amount to
$233,101 30 Amendment No 1 consisted of the work to replace approximately 2,100 linear feet of
sanitary sewer main 63, located in Clayton Avenue and Cold Springs Road
On August 29, 2002, Amendment No 2 was authorized by the City Manager (City Secretary Contract
No 27945) in the amount of $11,150 00, thereby increasing the contract amount to $244,251 30
Amendment No 2 consisted of the work to prepare plans and specifications for the design of 515 linear
feet of water main along Leota Street and for the preparation of railroad permits
Amendment No 3 consists of the preparation of plans and specifications to install a sanitary sewer lift
station to serve the Greenway Addition and the surrounding 200 acres Currently, existing sanitary
sewer lines located in and passing through the Greenway Addition are extremely shallow, laid at flat
grades, and susceptible to backwater conditions from the West Fork 72-inch diameter trunk main,
resulting in long-term maintenance, capacity, and odor problems The new lift station will pump
wastewater collected from the Greenway Addition and surrounding 200 acres directly into the 72-inch
diameter West Fork trunk main
City of Fort Worth, Texas
Mayor and Council Communication
DATE
12/3/02 REFERENCE NUMBER
**C-19371 LOG NAME
60DUN PAGE
2 of 2
SUBJECT APPROPRIATION ORDINANCE AND AMENDMENT NO 3 TO THE ENGINEERING
AGREEMENT WITH DUNAWAY AND ASSOCIATES, INC FOR THE GREENWAY
ADDITION MODEL BLOCK
This project is located in COUNCIL DISTRICT 8
Dunaway and Associates, Inc. is in compliance with the City's M/WBE Ordinance by committing to an
additional 36% M/V1/BE participation on this amendment.
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of recommendation No 1, and
adoption of the attached appropriation ordinance, funds will be available in the current capital budget,
as appropriated, of the Sewer Capital Project Fund
MO.k
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
1 &2) PS58 472045 070580175450 $78,481.50
Marc Ott 8476 2) PS58 531200 070580175450 $78,481.50
Originating Department Head:
Dale Fisseler 8207. (from) APPROVED 12/03/02
3) PS58 531200 070580175450 $78,481.50 ORDINANCE NO 15355
Additional Information Contact: 1) PE45 538070 0709020 $78,481.50