HomeMy WebLinkAboutOrdinance 14931.~
Ordinance No ~ ~ ` "'
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE SEWER CAPITAL PROJECT FUND IN THE AMOUNT
OF $76,000 FOR THE PURPOSE OF FUNDING CHANGE ORDER NO 2 TO
SANITARY SEWER REHABILITATION CONTRACT XLIX (49) WITH JACKSON
CONSTRUCTION LTD , MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN CONFLICT
HEREWITH, AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City deparhnents for the Fiscal Year 2001-02 and in
the Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the
Sewer Capital Project Fund in the amount of $76,000 for the purpose of funding change order NO 2 to
Sanitary Sewer Rehabilitation Contract XLIX (49) with Jackson Construction Ltd.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opuuon or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No 14745 and all other ordinances and appropriations
amending the same except in those instances where the provisions of this ordinance are m direct conflict with
such other ordinances and appropriations, in which instance said conflicting provisions of said prior
ordinances and appropriations are hereby expressly repealed.
SECTION 4
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY
Assistant City Attorney
ADOPTED AND EFFECTIVE.
City of Fort Worth, Texas
Mayor and Council
Communication
DATE
1 /15/02 REFERENCE NUMBER
**C_18928 LOG NAME
30JAC PAGE
1 of 1
SUBJECT APPROPRIATION ORDINANCE AND CHANGE ORDER NO 2 TO SANITARY SEWER
REHABILITATION CONTRACT XLIX (49) WITH JACKSON CONSTRUCTION, LTD
RECOMMENDATION
It is recommended that the City Council
1 Authorize the City Manager to transfer $76,000 00 from the Water and Sewer Fund to the Sewer
Capital Project Fund, and
2 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Project Fund in the amount of $76,000 00 from available funds, and
3 Authorize the City Manager to execute Change Order No 2 to City Secretary Contract No 26720
with Jackson Construction, Ltd in the amount of $76,000 00 to provide for additional pay item
quantities, thereby increasing the total contract amount to $1,000,867 30
DISCUSSION
On April 24, 2001 (M&C C-18566), the City Council authorized the City Manager to execute a contract
with Jackson Construction, Ltd in the amount of $921,867 30 for Sanitary Sewer Rehabilitation,
Contract XLIX (49) The contract was revised by one previous amendment in the amount of $3,000 00
The change order will provide a pay item for additional pavement repair beyond the trench width to
comply with the latest City pavement repair requirements which were adopted after the project was
advertised for bid
Staff considers the proposed change order amount to be fair and reasonable
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of recommendation No 1, and
adoption of the attached appropriation ordinance, funds will be available in the current capital budget,
as appropriated, of the Sewer Capital Project Fund
MG k
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by• (to)
1 &2) PS58 472045 070580174310 $76,000 00
Mike Groomer 6140 2) PS58 541200 070580174310 $76,000.00
Originating Department Head:
Douglas Rademaker 6157 (from) APPROVED 01/15/02
3) PS58 541200 070580174310 $76,000 00 ORD.# 14931
Additional Information Contact: 1) PE45 538070 0709020 $76,000.00
Douglas Rademaker 6157