Ordinance No / ~..~
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER CAPITAL PROJECT FUND IN THE AMOUNT
OF $529,810 AND IN THE SEWER CAPITAL PROJECT FUND IN THE AMOUNT OF
$219,835 FOR THE PURPOSE OF FUNDING A CONTRACT TO ROPE
CONSTRUCTION, INC FOR WATER AND SEWER REPLACEMENTS AT WHITE
SETTLEMENT ROAD FROM UNIVERSITY DRNE TO WESTVIEW AVENUE,
MAKING THIS ORDINANCE CUMULATNE OF PRIOR ORDINANCES AND
REPEALING ALL PRIOR ORDINANCES IN CONFLICT HEREWITH, AND
PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year
2001-02 and in the Budget of the City Manager, there shall also be increased estimated receipts
and appropriations in the Water Capital Project Fund in the amount of $529,810 and in the Sewer
Capital Project Fund in the amount of $219,835 for the purpose of funding a contract to Rope
Construction, Inc. For water and sewer replacements at White Settlement Road from University
Drive to Westview Avenue.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid,
inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or
judgment shall in no way impair the remaining portions, sections, or parts of sections of this
ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No 14745 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance
are in direct conflict with such other ordinances and appropriations, in which instance said
conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed
SECTION 4
This ordinance shall take effect upon adoption
APPROVED AS TO FORM AND LEGALITY
/~/
Assistant City Attorney
ADOPTED AND EFFECTIVE. ~"~ O~'D~"
City of Fort Worth, Texas
Mayor and Council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
1/22/02 **C-18933 30WHITE 1 of 2
SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO ROPE
CONSTRUCTION, INC FOR WATER AND SEWER REPLACEMENTS AT WHITE
SETTLEMENT ROAD FROM UNIVERSITY DRIVE TO WESTVIEW AVENUE
RECOMMENDATION
It is recommended that the City Council•
1 Authorize the City Manager to transfer $749,645 00 from the Water and Sewer Fund to the Water
Capital Project Fund in the amount of $529,810 00 and Sewer Capital Project Fund in the amount of
$219,835 00, and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water Capital Project Fund in the amount of $529,810 00 and the Sewer Capital Project Fund in the
amount of $219,835 00, from available funds, and
3 Authorize the City Manager to execute a contract with Rope Construction, Inc. in the amount of
$677,238 00 and 85 working days for water and sewer replacements in White Settlement Road from
University Drive to Westview Avenue
DISCUSSION
'The Water Department has determined that the water and .sanitary sewer lines at White Settlement
Road need to be replaced Paving improvements will follow under one of the Transportation and Public
Works Department street maintenance contracts
BID ADVERTISEMENT -This project was advertised for bid on October 4 and 11, 2001 On November
1, 2001, the following bids were received
BIDDERS AMOUNT TIME OF COMPLETION
Rope Construction, Inc. $677,238.00 85 Working Days Specified
Cleburne Utility Construction, Inc. $722,427 00
William J Schultz, Inc. d/b/a Circle"C"
Construction Company $805,120 00
Southland Contracting, Inc. $82,858 00
Conatser Construction, Inc. $904,885 00
Jackson Construction, Ltd $928,972.00
Tri-Tech Construction, Inc. $931,513.20
S L. Siebert Company, Inc. $945,693 00
M/WBE -Rope Construction, Inc. is in compliance with the City's MNVBE Ordinance by committing to
16% M/WBE participation The City's goal on this project is 16%
City of Fort Worth, Texas
Mayor and Council Communication
DATE REFEKtNGt NUMtstK w~ rvruvi~ ~ ~~~-
1/22/02 **C-18933 30WHITE 2 of 2
SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO ROPE
CONSTRUCTION, INC FOR WATER AND SEWER REPLACEMENTS AT WHITE
SETTLEMENT ROAD FROM UNIVERSITY DRIVE TO WESTVIEW AVENUE
Water contingencies for change orders are $17,669 00 and $33,505 00 for associated construction
inspection and survey respectively Sewer contingencies for change orders are $7,331 00 and
$13,902.00 for associated construction inspection and survey respectively
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of recommendation No 1, and the
adoption of the attached appropriation ordinance, funds will be available in the current capital budgets,
as appropriated, of the Water and Sewer Capital Project Funds
MG.n
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
1&2) PW53 472045 060530175950 $529,810.00
Mike Groomer G 140 1 &2) PS58 472045 070580175230 $219,835.00
Originating Department Head: 2) PW53 541200 060530175950 $496,305.00
2) PW53 531350 030530175950 $ 33,505.00
2) PS58 541200 070580175230 $205,933.00
2) PS58 531350 030580175230 $ 13,902.00
Douglas Rademaker 6157 (from) APPROVED 01/22/02
11 PFdS 53A070 0609070 $529,810.00 ORD.# 14938
Douglas Rademaker 6157 ~ 3) PS58 ~ 541