HomeMy WebLinkAboutOrdinance 15363
ORDINANCE No ~`~~~~
AN ORDINANCE ADOPTING A PER ACRE CHARGE FOR
THE 857 ACRES SERVED BY CITY INITIATED SEWER
MAIN M-321 FROM STATION 109+31.34 TO STATION
149+15 74, MAKING THIS ORDINANCE CUMULATIVE OF
OTHER ORDINANCES, REPEALING ALL ORDINANCES IN
CONFLICT HEREWITH, PROVIDING A SAVINGS CLAUSE,
AND PROVIDING AN EFFECTIVE DATE
WHEREAS, on May 14, 2002, the City Council adopted City of Fort Worth
Ordinance No 15095 providing for the adoption of per acre charges when certain criteria
are met; and
WHEREAS, the City of Fort Worth is constructing City initiated sewer main M-
321 from station 109+31 34 to station 149+15 74 and such City initiated sewer main is
15" or greater
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS
Section 1
The City Council finds, m accordance with City of Fort Worth Ordinance No
15095, the City is constructing a City imtiated sewer main (the "Main") to provide
wastewater service and that such Mam varies in size from 16" to 18" Further, the City
Council finds that the Mam from station 109+31.34 to station 149+15 74 will serve a
calculated sewer basin area of 857 acres, such sewer basin being more fully described m
the attached exhibit "A", which is attached hereto and made a part hereof for all
purposes.
~'`v.
Section 2
The City Council finds that $435,224 54 is the Development Cost for the Mam,
and that $507 85 is the per acre charge to be assessed within the calculated sewer basin.
The City Council further finds that the per acre charge has been calculated in accordance
with the requirements of City of Fort Worth Ordinance No 15095
SECTION 3
This ordinance shall be cumulative of all provisions of ordinances and of the
Code of the City of Fort Worth, Texas (1986), as amended, except where the provisions
of this ordinance are m direct conflict with the provisions of such ordinances and such
Code, m which event conflicting provisions of such ordinances and such Code are hereby
repealed.
SECTION 4.
It is hereby declared to be the intention of the City Council that the sections,
paragraphs, sentences, clauses and phrases of this ordinance are severable, and, if any
phrase, clause, sentence, paragraph or section of this ordinance shall be declared
unconstitutional by the valid judgment or decree of any court of competent ~unsdichon,
such unconstitutionality shall not affect any of the remaining phrases, clauses, sentences,
paragraphs and sections of this ordinance, since the same would have been enacted by the
City Council without the incorporation m this ordinance of any such unconstitutional
phrase, clause, sentence, paragraph or section.
SECTION 5.
This ordinance shall be effective upon adoption.
A
J `=
APPROVED ~TO FORM AND LEGALITY
Assistant Crty Attorney
ADOPTED Iv~-' ~1 - O~
t
i,
City of Fort Worth, Texas
Mayor and Council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
12/17/02 **G-13830 60PER 1 of 2
SUBJECT ADOPTION OF ORDINANCES FOR SEWER PER ACRE CHARGE FOR SEWER MAIN
M-321 AND SEWER MAIN M-423
RECOMMENDATION
It is recommended that the City Council adopt the attached ordinances and boundary maps which
• Establish $507 85 as the per acre charge for sanitary sewer Main M-321, and $690.21 as the
per acre charge for sanitary sewer Main M-423, and
• Establish the basin boundaries for these per acre charges
DISCUSSION
On August 8, 2000 (M&C C-18178), the City Council authorized the City Manager to execute a contract
for construction of the M-321 and M-423 sanitary sewer mains
Sanitary sewer Main M-321 from. station 109+31 34 to station 149+15 74 will serve a calculated sewer
basin area of 857 acres The qualified costs used to establish the $507 85 per acre charge for sewer
Main M-321 is determined by engineering, easement and construction costs as outlined below
M-321
Engineering cost $ 58,831 43
Easement cost $ 5,001 00
Construction cost $371.392.11
Total $435,224.54
Sanitary sewer Main M-423 from station 37+96 to station 251+56 will serve a calculated sewer .basin
area of 2,419 acres The qualified costs used to establish the $690 21 per acre charge for sewer Main
M-423 is determined by engineering, easement and construction costs as outlined below
M-423
Engineering cost $ 166,059 80
Easement cost $ 28,241 54
Construction cost $1,475,321.10
Total $1,669,622.44
These mains meet the criteria established under the per acre charge ordinance There is no restriction
to the time period in which the per acre charge will apply The reimbursement will be to the Fort Worth
Water Department.
'1 ..,~,
City of Fort T~Tjarth, Texas
Mayor and Council Communication
DATE
12/17/02 REFERENCE NUMBER
**G-13830 LOG NAME
60PER PAGE
2 of 2
SUBJECT ADOPTION OF ORDINANCES FOR SEWER PER ACRE CHARGE FOR SEWER MAIN
M-321 AND SEWER MAIN M-423
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that the Water Department is responsible for the collection and deposit of
funds due to the City as a result of this action
MO k
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
PE45 493542 0701000
Marc Ott 8476
Originating Department Head:
Dale Fisseler 8207 (from) APPROVED 12/17/02
ORDINANCE NO 15363
Additional Information Contact: & 15364
Dale Fisseler 8207