HomeMy WebLinkAboutOrdinance 14741e :~. Ordinance No AN ORDINANCE INCREASING THE ESTIMATED RECEII'TS AND APPROPRIATIONS IN THE WATER CAPITAL PROJECT FUND IN THE AMOUNT OF $16,410 FROM AVAILABLE FUNDS FOR THE PURPOSE OF FUNDING CHANGE ORDER NO 1 TO THE CONTRACT WITH WILLIAM J SCHULTZ, INC., D/B/A CIRCLE "C" CONSTRUCTION FOR CONSTRUCTION OF SANITARY SEWER MAINS D 104D, D 105, D l OSA, AND D 109 REHABILITATION PART II AND WATER LINE IMPROVEMENTS IN HOUSTON STREET AND THROCKMORTON STREET, MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE. BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS SECTION 1 That in addition to those amounts allocated to the various City departments for the Fiscal Year 2000-01 and in the Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water Capital Project Fund in the amount of $16,410 from available funds for the purpose of funding Change Order No. 1 to the contract with William J Schultz, Inc., d/b/a Circle "C" Construction for construction of Sanitary Sewer Mains D104D, D105, DlOSA and D109 Rehabilitation Part II and water line improvements in Houston Street and Throckmorton Street. SECTION 2. That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect. SECTION 3 That this ordinance shall be cumulative of Ordinance No. 14286 and all other ordinances and appropriations amending the same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and appropriations, inwhich instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed. SECTION 4 This ordinance shall take effect upon adoption. APPROVED AS TO FORM AND LEGALITY ssistant City ttomey ADOPTED AND EFFECTIVE. ~ ~ ~-O~ City of Fort Worth, Texas ~1-~A~a~ Anil Caunc~l cam~un~c~et~ian DATE REFERENCE NUMBER LOG NAME PAGE 8/9/01 **C-18703 30SEWER 1 of 2 SUBJECT APPROPRIATION ORDINANCE AND CHANGE ORDER NO 1 FOR CONTRACT WITH WILLIAM J SCHULTZ, INC D/B/A CIRCLE "C" CONSTRUCTION COMPANY FOR CONSTRUCTION OF SANITARY SEWER MAINS D104D, D105, D105A, AND D109 REHABILITATION PART II, AND WATER LINE IMPROVEMENTS IN HOUSTON STREET AND THROCKMORTON STREET RECOMMENDATION It is recommended that the City Council 1 Authorize the City Manager to transfer $16,410 00 from the Water and Sewer Operating Fund to the Water Capital Project Fund, and 2 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water Capital Project Fund in the amount of $16,410 00 from available funds, and 3 Authorize Change Order No 1 in the amount of $16,410 00 to City Secretary Contract No 26676 with William J Schultz, Inc. d/b/a Circle "C" Construction Company for construction of sanitary sewer Mains D104D, D105, D105A, and D109 rehabilitation Part II, and water line improvements in Houston Street and Throckmorton Street, revising the total to $1,874,773 00 DISCUSSION On April 10, 2001 (M&C C-18542), the City Council authorized the award of a contract to William J Schultz, Inc. d/b/a Circle "C" Construction Company for the construction of sanitary sewer Mains D104D, D105, D105A, and D109 rehabilitation Part II, and water line improvements in Houston Street and Throckmorton Street. During construction of the water line in Houston Street, the contractor found railroad ties from an old trolley track within its trench line The presence of these railroad ties forced the contractor to widen the permanent paving repair beyond what is normally required The contractor also encountered a natural gas service line that was not identified on the plans. In order to meet the deadlines established, the contractor provided a trench to relocate the natural gas service line and is requesting payment for this additional work. The net effect of the proposed change order is as follows Original Contract Cost $1,858,363 00 Extras to Date 0 00 Proposed Change Order No 1 $ 16,410.00 Revised Contract Cost $1,874,773.00 Original Contract Time 150 Calendar Days Additional Approved Time to Date -0- Calendar Days Additional Time for this Change Order 4 Calendar Days Total ,Contract Time 154 Calendar Days City of Fort Worth, Texas ~1-~a~a~ and caun~il ainmun~cA~ian DATE REFERENCE NUMBER LOG NAME PAGE 8/9/01 **C-18703 30SEWER 2 of 2 SUBJECT APPROPRIATION ORDINANCE AND CHANGE ORDER NO 1 FOR CONTRACT WITH WILLIAM J SCHULTZ, INC D/B/A CIRCLE "C" CONSTRUCTION COMPANY FOR CONSTRUCTION OF SANITARY SEWER MAINS D104D, D105, D105A, AND D109 REHABILITATION PART II, AND WATER LINE IMPROVEMENTS IN HOUSTON STREET AND THROCKMORTON STREET Engineering Department staff have reviewed the proposed changes and found them to be reasonable FISCAL INFORMATION/CERTIFICATION The Finance Director certifies that upon approval and completion of recommendation No 1, and adoption of the attached appropriation ordinance, funds will be available in the current capital budget, as appropriated, of the Water Capital Project Fund MG n Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY Office by: (to) 1&2) PW53 472045 060530176120 $16,410 00 APPROVED Mike Groomer 6140 2) PW53 541200 060530176120 $16,410.00 CITY COUNCIL Originating Department Head: AUG 9 2001 A. Douglas Rademaker 6157 (from) 1) PE45 538070 0609020 $16,410.00 ~ Additi l I f ti C t 3 ° '""'"~`~ ona n orma on on act: ) PW53 541200 060530176120 $16,410.00 City Secretary of the Texas City of fort 1it'orth A. Douglas Rademaker 6157 , adopted l~rdin~n~ ~d; -~~