HomeMy WebLinkAboutOrdinance 14356f
Ordinance No. / ~~ ~ (~
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
PARK IlVIPROVEMENTS FUND IN THE AMOUNT OF $8,710 FROM AVAILABLE FUNDS FOR
THE PURPOSE OF FUNDING A CONTRACT WITH M. A. VINSON CONSTRUCTION, INC. FOR
WALKS AND TRAIL REPLACEMENT AT EIGHT PARK SITES, MAKING THIS ORDINANCE
CUMULATIVE. OF PRIOR ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN
CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS
SECTION 1.
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1999-00 and in the Budget
of the City Manager, there shall also be increased estimated receipts and appropriations .in the Park Improvements Fund
in the amount of $8,710 from available funds for the purpose of funding a contract with M. A. Vinson Construction, Inc.
for walks and trail replacement at eight park sites.
SECTION 2.
'Should .any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by
a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining portions,
sections, or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and
effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 13886 and all other ordinances and appropriations amending
the same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances
and appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby
expressly repealed.
SECTION 4
This ordinance shall take effect and be in full force after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
L~
Assistant City orn
S ~ ~o~
Date
2 ~- O®
Adopted
1-27-Oo
Effective
City of Fort Worth, Texas
~11~A~or And aunci( OIr11r1un1cAtlOn
c e
DATE _ REFERENCE NUMBER LOG NAME PAGE
9/26/00 **C-18255 80EXPAND 1 of 3
SUBJECT APPROPRIATION ORDINANCE AND APPROVAL OF CHANGE ORDER FOR
EXPANDED CREEK BANK STABILIZATION UNDER THE EXISTING CONTRACT
WITH M A. VINSON CONSTRUCTION COMPANY, INC FOR WALKS AND TRAIL
REPLACEMENT AT EIGHT PARK SITES
RECOMMENDATION
It is recommended that the City Council
Authorize the City Manager to transfer $22,410 00 from the Water and Sewer Operating Fund to the f
Sewer Capital Project Fund, and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Sewer Capital Project Fund in the amount of $22,410 00 from available funds, and
3 Accept $8,710 00 from TranSystems Corporation as cash compensation for the construction of
expanded creek bank stabilization at Foster Park North, and
4 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Park Improvements Fund by $8,710 00 from available funds, and
5 Authorize the City Manager to execute a change order in the amount of $44,820 00 for expanded
creek bank stabilization in Foster Park North
,DISCUSSION
The 1998 Capital Improvement Program allocated $505,000 00 for replacement of deteriorated walks at
seven park sites and along selected areas of the bike trail on the Clearfork of the Trinity River The
park sites include the Trinity Park shelter area, Clearfork-Trinity River Trail, Candleridge, Foster North,
Foster South, Meadowood, Oakland Lake, and Overton Parks Allocated funds also include the
replacement of an existing pedestrian bridge along the Trinity River Trail
On February 2, 1999 (M&C C-17259), the City Council approved the award of contract for design
services to TranSystems Corporation in the amount of $65,425 00 for the design of walks and trails at
all eight sites
As part of the scope of services to be performed by TranSystems Corporation under City Secretary
Contract (No 24665), TranSystems Corporation was to examine the site and make recommendations
for a solution to an undercut slope embankment along the Foster Park North creek bank, resulting in
the re-alignment of the existing trail The design solution determined by TranSystems Corporation
called for the slope grading of the existing vertical creek bank and installation of gabion baskets
interspersed along the impacted creek bank to deflect water flow at impact points, thus reducing the
creek bank erosion
City of Fort Worth, Texas
~1-~Ayar And aun~l a~rt~»un~cAt~ion
C C
DATE REFERENCE NUMBER LOG NAME PAGE
9/26/00 **C-18255 80EXPAND 2 of 3
suB~EC-r APPROPRIATION ORDINANCE AND APPROVAL OF CHANGE ORDER FOR
EXPANDED CREEK BANK STABILIZATION UNDER THE EXISTING CONTRACT
WITH M A. VINSON CONSTRUCTION COMPANY, INC FOR WALKS AND TRAIL
REPLACEMENT AT EIGHT PARK SITES
On March 7, 2000 (M&C C-17906), the City Council approved an award of contract to M A. Vinson
Construction Company, Inc. in the amount of $401,473 84 for walks and trail replacement at all eight
sites. Project construction commenced on April 11, 2000 In late May 2000, while the contractor was
performing the specified slope embankment grading at Foster Park North, a utility trench was
uncovered which was not identified on the plans. After site review by both the Parks and Community
Services Department (PACs) and the Water Department, it was determined that there was an 18-inch
sanitary sewer line located within the proposed slope embankment area The location of this facility
should have been known to the design engineer Transystems Corporation prepared three design
options, which would provide protection to both the sanitary sewer line and the slope embankment at an
estimated cost to Transystems Corporation of $3,315 00 The three options were submitted to the
contractor for a price proposal
In early July 2000, both City staff and the consultant concurred that installation of a gabion revetment
mattress would be the appropriate solution The contractor submitted a price of $44,820 00 for this
solution, and staff has determined this price to be fair and reasonable.
Due to the need to provide creek bank protection to the existing sanitary sewer line, the Water
Department will fund 50% of the cost in the amount of $22,410 00 The consultant has agreed to
provide $8,710 00 as compensation to rectify its error, in addition to providing an additional $3,315 00
of engineering services. The remaining fund amount of $13,700 00 is comprised of project savings
from various sites included in the walks and trails replacement project.
The PACs Department has determined that the compensation provided by TranSysterns Corporation is
fair and reasonable and exhibits an appropriate, responsible action by Transystems Corporation
M.A. Vinson Construction Company, Inc. is in compliance with the City's M/WBE Ordinance by
committing to an additional 15% M/VVBE participation on this change order The City's goal on this
change order is 11
The Foster Park North project site is located in COUNCIL DISTRICT 3
City of Fort Worth, Texas
~1-~A~a~ And C,~unc~l Ca~»r»un~cAt~an
DATE REFERENCE NUMBER LOG NAME PAGE
9/26/00 **C-18255 80EXPAND 3 of 3
suB.1ECT APPROPRIATION ORDINANCE AND APPROVAL OF CHANGE ORDER FOR
EXPANDED CREEK BANK STABILIZATION UNDER THE EXISTING CONTRACT
WITH M A. VINSON CONSTRUCTION COMPANY, INC FOR WALKS AND TRAIL
REPLACEMENT AT EIGHT PARK SITES
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of recommendations 1 through 4, and
adoption of the attached appropriation ordinances, funds will be available in the current capital budgets,
as appropriated, of the Sewer Capital Projects Fund and the Parks and Community Services
Fmprovement Fund
LW:k
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
3&4) 0188 488104 080188300050 $ 8,710.00 ~~~~~E~
Libby Watson 6183 3&4) C188 541200 080188300050 $ 8,710.00 9 1hI
Originating Department Bead:
1 &2) PS58
472045
070580175280
$22,410.00 ~~ ~ ~ ~®
~~~
l3 i V
2) PS58 541200 070580175280 $22,410.00
Richard Zavala 5704
(from) S ~ F ~ 6 2000
1) PE45 538070 0709020 $22,410.00 yy
Additi
l I
f
ti
C
t C188
5 488104 080188300050 $ 8
710
00 ~
l;ti`~
ona
n
orma
on
on
act: ) ,
. ~,~,
e,.~.~,
5) PS58 541200 070580175280 $22,410.00 City Sscsaty.*y ai cLa
Richard Zavala 5704 5) C181 541200 080181050020 $13,700.00 Citq of F~:t `;s~crth; `:r:r~.s
/~3~5 Adopted Ori#inanre No.~ ~ ~3 S~
Adopted Ordnance No,