HomeMy WebLinkAboutOrdinance 14094Ordinance No.~~"l~ ~~
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER CAPITAL PROJECT FUND IN THE AMOUNT OF $22,608 00 AND SEWER CAPITAL
PROJECT FUND IN TT-IE AMOUNT OF $5,439.27 FROM AVAILABLE FUNDS FOR THE PURPOSE
FUNDING A CONTRACT TO TRANSYSTEMS CORPORATION FOR THE DESIGN OF THE WATER
AND SEWER MAIN REPLACEMENTS ALONG UNIVERSITY DRIVE AT CAMP BOWIE
BOULEVARD AND 7TH STREET, PROVIDING FOR A SEVERABILITY CLAUSE, MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR
ORDINANCES IN CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1999-00 and in the Budget of
the City Manager, there shall also be increased estunated receipts and appropriations in the Water Capital Project Fund in the
amount of $22,608.00 and Sewer Capital Project Fund I the amount of $5 439.27 from available funds for the purpose of
funding a contract to Transystems Corporation for the design of the water and sewer main replacements along University Drive
at Camp Bowie Boulevard and 7''' Street.
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by a
court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining portions, sections, or
parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 13886 and all other ordinances and appropriations amending the
same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and
appropriations, in which instance said conflicting provisions of said }prior ordinances and appropriations are hereby expressly
repealed.
SECTION 4
This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
~~
Assistant City Attorney
~i~~~
Dat-~-
~-l5-oc~
Adopted
~~ co c~y
Effective
City of Fort Worth, Texas
~11~A~a~ And Caunc~l amirtun~cAt~ian
C
DATE I REFERENCE NUMBER LOG NAME .PAGE
2/15/00 **C-17853 30DESIGN 1 of 2
SUBJECT APPROPRIATION ORDINANCE AND AMENDMENT OF ENGINEERING SERVICES
AGREEMENT TO TRANSYSTEMS CORPORATION FOR THE DESIGN OF THE WATER
AND SEWER MAIN REPLACEMENTS ALONG UNIVERSITY DRIVE AT CAMP BOWIE
BOULEVARD AND 7TH STREET
RECOMMENDATION
It is recommended that the City Council
1 Authorize the transfer of $28,047.27 from the Water and Sewer Operating Fund to the Water Capital
Project Fund ($22,608 00) and the Sewer Capital Project Fund ($5,439.27) respectively; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water Capital=Project Fund in the amount of $22,608 00 and Sewer Capital Project Fund in the
amount of $5,439.27 from available funds, and
3 Authorize the City Manager to execute Amendment No 1 to City Secretary Contract (No 25016)
with TranSystems Corporation in the amount of $31,089.27 to provide for additional design
services, thereby increasing the contract amount to $110,489.27
DISCUSSION
On June 29, 1999 (M&C C-17503), the City Council authorized the City Manager to execute an
engineering services agreement with TranSystems Corporation in the amount of $79,400 00 for the
preparation of plans and specifications for water and sewer improvements to the University Drive,
Camp Bowie, 7th Street and Bailey Avenue intersection
The improvements include Changing the alignment and/or adjustments to the water line, requiring that
five of the plan and profile sheets be revised, Extending "A" an additional 265 feet along Camp Bowie,
Adding approximately 100 feet of 8-inch water line across Camp Bowie to connect water mains on
either side, Extending the sewer main along Camp Bowie to terminate at Arch Adams, Providing
additional design for the revised and relocated valve vaults and paving sections, and Incorporating site
grading sheets along University Avenue between Lancaster Avenue and Camp Bowie Boulevard into a
completed set of drawings
TranSystems Corporation is in compliance with the City's M/WBE Ordinance by committing to an
additional 18% M/WBE participation on this amendment.
,~ ,
The project is located in COUNCIL DISTRICTS 7 and 9, Mapsco 76A.
City of Fort Worth, Texas
~1-~Aya~ and Caunc~l ea~nntun;cAt~an
DATE REFERENCE NUMBER LOG NAME PAGE
2/15/00 **C-17853 30DESIGN 2 of 2
SUBJECT APPROPRIATION ORDINANCE AND AMENDMENT OF ENGINEERING SERVICES
AGREEMENT TO TRANSYSTEMS CORPORATION FOR THE DESIGN OF THE WATER
AND SEWER MAIN REPLACEMENTS ALONG UNIVERSITY DRIVE AT CAMP BOWIE
BOULEVARD AND 7TH STREET
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of the above recommendation and
adoption of the attached appropriation ordinance, funds will be available in the current capital budgets,
as appropriated, of the Water Capital Project Fund, the Sewer Capital Project Fund and the Street and
Related Improvements Fund
MGj
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
1&2) PW53 472095 060530175630 $22,608.00 ~~~
Mik
G
e
roomer 6140 1&2)PS58 472095 070580174800 $ 5,439.27 //~~ AAii//~~
Originating Department Head: 2) PW53 531200 060530175630 $22,608.00 CVU,~J V~L
1 &2) PS58 531200 070580174800 $ 5,439.27
A. Douglas Rademaker 6157 (from) FEg 15 ?QQo
1) PE45 538070 0609020 $22,1,608.00 , /
Additional Information Contact:
1) PE45
538070
0709020
$ 5,439.27 )
(~{,~°-"k ~',Erv,.~.r,i
3) PW53 541200 060530175630 $22,608.00 ~~~ &rcx~tarp at tRe
3) PS58 541200 070580174800 $ 5,439.27 Oitg~ aI Pert 1TJ'orth, Tex
A. Douglas Rademaker 6157 GS30 531200 020300212020 $ 3,042.30
.Adopted Ordinance No.~ ~' ~;