HomeMy WebLinkAboutOrdinance 13989Ordinance No.~~ ~ l
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER CAPITAL PROJECTS FUND IN THE AMOUNT OF $310,213.00 AND IN THE SEWER
CAPITAL PROJECTS FUND IN THE AMOUNT OF $324,595 40 FROM AVAILABLE FUNDS FOR
THE PURPOSE OF FUNDING A CONTRACT WITH JACKSON CONSTRUCTION, INC., FOR
WATER AND SANITARY SEWER REPLACEMENTS IN SHARONDALE STREET, PROVIDING FOR
A SEVERABILITY CLAUSE, MAKING THIS ORDINANCE CUMULATIVE OF PRIOR
ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN CONFLICT HEREWITH, AND
PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1999-00 and in the Budget of
the City Manager, there shall also be increased estimated receipts and appropriations in the Water Capital Projects Fund in the
amount of $310,213 00 and in the Sewer Capital Projects Fund in the amount of $324,595 40 from available funds for the
purpose of funding a contract with Jackson Construction, Inc., for water and sanitary sewer replacements in Sharondale Street.
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by a
court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining portions, sections, or
parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 13886 and all other ordinances and appropriations amending the
same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and
appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly
repealed.
SECTION 4
This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
Assistant 'ty Attorney
~ ~~~~~ ~
Date
(-~- ~~ y
Adopted
~t' ~~`~~
Effective
City of Fort Worth, Texas
~1-~uy~~ and Caunc;l C~mmun~cAt~an
DATE REFERENCE NUMBER LOG NAME PAGE
11/2/99 **C-17725 30REPLACE 1 of 2
SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO JACKSON
CONSTRUCTION, INC FOR WATER AND SANITARY SEWER REPLACEMENTS IN
SHARONDALE STREET FROM JAMES AVENUE TO HODGSON STREET
RECOMMENDATION
It is recommended that the City Council
1 Authorize the transfer of $634,808 40 from the Water and Sewer Operating Fund to the Water
Capital Projects Fund in the amount of $310,213 00 and Sewer Capital Projects Fund in the amount
of $324,595 40, and
2 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water Capital Projects Fund in the amount of $310,213 00 and the Sewer Capital Projects Fund in
the amount of $324,595 40 from available funds, and
3 Authorize the City Manager to execute a contract with Jackson Construction, Inc. in the amount of
$569,914 40 and 60 working days for Water and Sanitary Sewer Replacements in Sharondale
Street from James Avenue to Hodgson Street.
DISCUSSION
The Water Department has determined that the water and sewer lines in Sharondale Street from James
Avenue to Hodgson Street need to be replaced due to the age and condition of the existing lines
This project was advertised for bid August 12 and 19, 1999 The following bids were received
September 9, 1999
BIDDERS AMOUNT TIME OF COMPLETION
Jackson Construction. Inc. $569.914.40 60 Working Days
Tri-Tech Construction, Inc $578,884 00
B & H Utilities, Inc. $653,376 00
Conatser Construction, Inc. $660,943 00
William J Schultz, Inc. d/b/a Circle "C" Construction Co $671,855 00
Long Construction and Engineering, Inc. $721,371 75
The low bidder (Jackson Construction, Inc.) is in compliance with the City's M/WBE Ordinance by
committing to 6% M/WBE participation and documenting good faith effort. The City's goal on this
project is 27%
Water contingencies for change orders are $12,500 00, and $20,488 00 for associated construction
inspection and survey Sewer contingencies for change orders are $12,500 00 and $19,406 00 for
associated construction inspection and survey
City of Fort Worth, Texas
M,Ayor and Caunc~l CommunicAtian
DATE
11/2/99 REFERENCE NUMBER
**C-17725 LOG NAME
30REPLACE PAGE
2 of 2
suB~ECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO JACKSON
CONSTRUCTION, INC FOR WATER AND SANITARY SEWER REPLACEMENTS IN
SHARONDALE STREET FROM JAMES AVENUE TO HODGSON STREET
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of recommendation 1, and adoption of
the attached appropriation ordinance, funds will be available in the current capital budget, as
appropriated, of the Water and Sewer Capital Projects Funds
MGj
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
1 &2) PW53 472045 060530175040 $310,213.00
Mike Groomer 6140 1 &2) PS58 472045 070580174250 $324,595.40
Originating Department Bead: 2) PW53 541200 060530175040 $289,725.00 I~PPRQVED
2) PW53 531350 030530175040 $ 20,488.00 CITY COUNCIL
2)PS58 541200 070580174250 $305,189.40
2) PS58 531350 030580174250 $ 19,406.00 N1~~ ~ 1999
A. Douglas Rademaker 6157 (from)
1) PE45 538070 0609020 $310,213.00
~~
Additional Information Contact: 1) PE45 538070 0709020 $324,595.40 ''
~'~'~
3) PW53 541200 060530175040 $277,225.00 Clty Secretary of the
Citp of Fort Worth, Texas
A. Douglas Rademaker 6157 3) PS58 541200 070580174250 $292,689.40