AN ORDINANCE INCREASING THE ESTIMATED RECEII'TS AND APPROPRIATIONS IN THE
WATER CAPITAL PROJECTS FUND IN THE AMOUNT OF $293,896.50 AND IN THE SEWER
CAPITAL PROJECTS FUND IN THE AMOUNT OF $66,431 00 FROM AVAILABLE FUNDS FOR
THE PURPOSE OF FUNDING A CONTRACT WITH LARRY H. JACKSON CONSTRUCTION, INC.,
FOR WATER AND SEWER IMPROVEMENTS IN HANNA AVENUE, PROVIDING FOR A
SEVERABILITY CLAUSE, MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES,
REPEALING ALL PRIOR ORDINANCES IN CONFLICT HEREWITH, AND PROVIDING AN
EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1997-98 and in the Budget of
the City Manager, there shall also be increased estimated receipts and appropriations in the Water Capital Projects Fund in the
amount of $293,896.50 and in the Sewer Capital Projects Fund in the amount of $66,431 00 from available funds for the
purpose of funding a contract with Larry H. Jackson Construction, Inc., for water and sewer improvements in Hanna Avenue.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by
a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining portions, sections,
or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 13111 and all other ordinances and appropriations amending the
same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and
appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly
repealed.
SECTION 4
This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
~/L~
Assistant City ttorney
i~~ (9~
Date
i-a~-9~
Adopted
/--~7-~~
Effective
City of Fort Worth, Texas
~1-~Ayar And Cau~nc~l ~arr~ unacA~~an
DATE REFERENCE NUMBER LOG NAME PAGE
1/27/98 **C-16564 30HANNA 1 of 2
SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO LARRY H JACKSON
CONSTRUCTION, INC FOR WATER AND SEWER IMPROVEMENTS IN HANNA
AVENUE FROM AZLE AVENUE TO LORAINE STREET
RECOMMENDATION
It is recommended that the City Council
1 Authorize the transfer of $360,327 5p from the Water and Sewer Operating Fund to the Water
Capital Project Fund in the amount of $293,896 50 and the Sewer Capital Project Fund in the
amount of $66,431 00, and
2 Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water Capital Project Fund in the amount of $293,896 50 and the Sewer Capital Project Fund in the
amount of $66,431 00 from available funds, and -`-
3 Authorize the City Manager to execute a contract with Larry H Jackson Construction, Inc., in the
amount of $320,289 50 for the water and sewer construction in Hanna Avenue from Azle Avenue to
Loraine Street and sixty (60) working days.
DISCUSSION
The 1993 Capital Improvement Program included funds for the reconstruction of Hanna Avenue from
Azle Avenue to Loraine Street.
The Water Department has determined that the water and sewer mains in this street require
replacement prior to street reconstruction
This project was advertised on October 23 and 30, 1997 The following bids were received November
20, 1997
BIDDERS AMOUNT TIME OF COMPLETION
Larry H. Jackson Construction. Inc. $320.289.50 60 Working Days
Conatser Construction, Inc. 336,952 50
Atkins Brothers 525,444 50
Larry H Jackson Construction, Inc., is in compliance with the City's M/WBE Ordinance by committing to
8% M/V116E participation and documenting good faith effort. The City's goal on this project is 11
This project is located in COUNCIL DISTRICT 2, Mapsco 61 D and H
In addition to the contract cost, $13,062 00 and $2,953 00 are required for possible change orders for
water and sewer respectively
City of Fort Worth, Texas
M~Ayar and Council C~mmun;cAt~an
DATE
1/27/98 REFERENCE NUMBER
**C-16564 LOG NAME
30HANNA PAGE
2 of 2
SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO LARRY H JACKSON
CONSTRUCTION, INC FOR WATER AND SEWER IMPROVEMENTS IN HANNA
AVENUE FROM AZLE AVENUE TO LORAINE STREET
Contingencies for associated construction inspection and survey are $19,594 00 and $4,429 00 for
water and sewer respectively
FISCAL {NFORMAT{ON/CERTIFICATION
The Director of Fiscal Services certifies that upon approval and completion of recommendation 1, and
adoption of the attached appropriation ordinance, funds wilt be available in the current capital budgets,
as appropriated, of the Water and Sewer Capital Project Funds
MG:m
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
1&2 PW53 472045 060530174410 $293,896.50 ~~'+
Q~P~
Mike Groomer 6140 1&2 PS58 472045 070580173830 $ 66,431.00 a
~~ ~~~~
I
~
~~
Originating Department Head: 2) PW53 541200 060530174410 $274,302.50 ~~~ .a ~' ~s. I
°
'
2) PW53 531350 030530174410 $ 19,594.00
~
2) PS58 541200 070580173830 $ 62,002.00 ~
~~'~~
2) PS58 531350 030580173830 $ 4,429.00
f
A. Douglas Rademaker 6157 (from) c~~-~~~'~"~a
~ ~~
1) PE45 538070 0609020 $293,896.50 '0ity ~'~'
G;o7 of ~~'ti~`
Additional Information Contact: 1) PE45 538070 0709020 $ 66,431.00
3) PW53 541200 060530174410 $261,240.50
A. Douglas Rademaker 6157 3) PS58 541200 070580173830 $ 59,049.00