HomeMy WebLinkAboutOrdinance 13434Ordinance No. ,3
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER CAPITAL PROJECT FUND IN THE AMOUNT OF $224,017 00 AND IN THE SEWER
CAPITAL PROJECT FUND IN THE AMOUNT OF $192,127.00 FROM AVAILABLE FUNDS FOR
THE PURPOSE OF FUNDING A CONTRACT WITH KEBO SERVICES, INC., FOR UNIT 1 WATER
MAIN AND SANITARY SEWER MAIN REPLACEMENT IN CAMPBELL STREET AND
THANNISCH AVENUE, PROVIDING FOR A SEVERABILITY CLAUSE, MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES, REPEALING ALL PRIOR ORDINANCES
IN CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1997-98 and in the Budget of
the City Manager, there shall also be increased estimated receipts and appropriations in the Water Capital Project Fund in the
amount of $224,017.00 and in the Sewer Capital Project Fund in the amount of $192,127 00 from available funds for the
purpose of funding a contract with Kebo Services, Inc., for Unit 1 water main and sanitary sewer main replacement in
Campbell Street and Thannisch Avenue.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by
a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the remaining portions, sections,
or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 13111 and all other ordinances and appropriations amending the
same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and
appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly
repealed.
SECTION 4
This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
LLJ
~~.BePut3r.City orney
Date
~ - ~ ~-rj ~
Adopted
~-a~-~~
Effective
City of Fort T~orth, Teacas
Ayor and Caunc;t ~,ammunic~t~an
DATE REFERENCE NUMBER LOG NAME PAGE
4/28/98 **C-16741 30CAMP 1 of 2
SUBJECT APPROPRIATION. ORDINANCE AND AWARD OF CONTRACT TO KEBO SERVICES,
INC , FOR UNFT 1 WATER MAIN AND SANITARY SEWER MAIN REPLACEMENT IN
CAMPBELL STREET (BERRY STREET T'O FITZHUGH AVENUE). AND THANNISCH
AVENUE tVAUGHN BOULEVARD TO CAMPBELL STREET)
RECOMMENDATION
{t is recommended that the City Council
1 Authorize the transfer of $416,144 00 from. the Water and Sewer Operating Fund to the Water
Capital Project Fund ($224,01'7 00) and the Sewer Capital Fund ($192,127 00); and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the
Water Capital. Project Fund in the amount of $224,017 00 and the Sewer Capital Project Fund in the
amount of $192,127 00, from available funds, and
3 Authorize the City Manager to execute a contract with Kebo Services, Inc. in the amount of
$369,904 00 for Unit 1 water main and sanitary sewer main replacement in Campbell Street (Berry
Street to Fitzhugh Avenue) and Thannisch Avenue (Vaughn Boulevard to Campbell Street)
The Water Department has determined that the water and sewer lines in Campbell Street and the water
line in Thannisch Avenue need to be replaced prior to street reconstruction Both streets are scheduled
for reconstruction in conjunction with the City's 1993 Capital Improvement Program
This project was advertised on January 29 and February 5, 1998 The following bids were received on
February 26, 1998
BIDDERS AMOIDNT TIME OF COMPLETION
60 Working Days
Davila Construction, Inc. 377,561 00
Larry H Jackson Construction, Inc. 407,039 00
Texas Tech Construction, Inc. 452,920 00
Conatser Construction, Inc. 486,407 00
Atkins Bros. Equipment Co ,Inc. 681,609 00
Kebo Services, Inc., is in compliance with the City's M/WBE Ordinance by committing to 14% M/V1/BE
participation The City's goal on this project is 10%
This project is located in COUNCIL DISTRICT 5, Mapsco 78T and 78U
City of Fort Worth, Texas
~1-~ay~r and aumc~l ~,c~~rtmurt~cati~n
,DATE
4/28/98 REFERENCE NUMBER
**C-16741 LOG NAME
30CAMP .PAGE
2 of 2
SUBJECT APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO KEBO SERVICES
INC , FOR UNIT 1 WATER MAIN AND SANITARY SEWER MAIN REPLACEMENT IN
CAMPBELL STREET (BERRY STREET TO FITZHUGH AVENUE) AND THANNlSCH
AVENUE (VAUGHN BOULEVARD TO CAMPBELL STREET)
The water contingency for change orders is $9,957 00 and $14,935 00 for associated construction,
inspection and survey services. The sewer contingency for change orders is $8,539.00 and $12,809 00
for associated inspection and survey services.
FISCAL INFORMATION/ .FRTIFlC;ATIf?N
The Director of Fiscal Services certifies that upon approval and completion of recommendation 1, and
adoption of the attached appropriation ordinance, funds will be available in the current capital budgets,
j as appropriated, of the Water and Sewer Capital Project Funds.
MG:m
s
i
I
I
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by: (to)
1&2)PW53 472045 060530174030 $153,583.00
~ Mike Groomer 6140 1&2) PS58 472045 070580173460 $192,127.00
Originating Department Head: 2) PW53 541200 060530174030 $143,278.00
2) PW53 531350 030530174030 $ 10,305.00 APPR®d
2) PS58 541200 070580173460 $179,318.00 ~~~~ ~j'~~~{~
2) PS58 531350 030580173460 $ 12,809.00 v ! v
2) PW53 541200 060530174050 . $ 65,804.00 ,, ~ ~ ~
2) PW53
531350
030530174050
$ 4,630.00 ~
1&2) PW53 472045 060530174050 $ 70,434.00
~~
A. Douglas Rademaker 6157 (from) ~'
'~~
Ciff 5~~°t~g'
1) PE45 538070 0609020 $224,017.00 Citg of ~
Additional Information Contact: 1) PE45 538070 0709020 $192,127.00
3) PW53 541200 060530174030 $136,408.00
3) PS58 541200 070580173460 $170,779.00
A. Douglas Rademaker 6157 3) PW53 541200 060530174050 $ 62,717.00