HomeMy WebLinkAboutOrdinance 13579ORDINANCE NO 1 ~ 5 ? 9
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER CAPITAL PROJECTS FUND IN THE
AMOUNT OF $381,330.10 AND IN THE SEWER CAPITAL PROJECT FUND IN
THE AMOUNT OF $143,688.50 FROM AVAILABLE FUNDS FOR THE
PURPOSE OF FUNDING A CONTRACT WITH STOCKER ENTERPRISES, INC.
FOR WATER AND SANITARY SEWER LINE REPLACEMENTS ON OVERHILL
ROAD (VALHALLA TO S.H. 183) AND WILLIS AVENUE (BORDEN TO
OVERHILL), PROVIDING FOR A SEVERABILITY CLAUSE, MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING
ALL PRIOR ORDINANCES IN CONFLICT HEREWITH, AND PROVIDING AN
EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1997/98 and in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the
Water Capital Project Fund in the amount of $381,330.10 and in the Sewer Capital Project Fund in the amount of
$143,688.50 from available funds for the purpose of funding a contract with Stocker Enterprises, Inc. for water
and sanitary sewer line replacements on Overbill Road (Valhalla to S.H. 183) and Willis Avenue (Borden to
Overbill)
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any
reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair the
remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall be and
remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance No. 13111 and all other ordinances and appropriations
amending the same except in those instances where the provisions of this ordinance are in direct conflict with
such other ordinances and appropriations, in which instance said conflicting provisions of said prior ordinances
and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect and be in full force and effect from and after the date of its passage, and it is so
ordained.
APPROVED AS TO FORM AND LEGALITY
~~_
Assistant j ty Attorney
~i !~
Date
~l s~~~
Adopted
~ ~5~~
Effective
City of Fort Worth, Texas
~1-~Ayar And Caunc~l Cammun~cAt~an
Date Reference Number Log Name Page
9/15/98 **C-16990 30STOCKER 1 of 2
subject APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO STOCKER
ENTERPRISES, INC FOR WATER AND SANITARY SEWER LINE REPLACEMENTS
ON OVERNICE ROAD (VALHALLA TO S H 183) AND WILLIS AVENUE (BORDEN TO
OVERNICE)
RECOMMENDATION
It is recommended that the City Council
1 Authorize the transfer of $381,330 10 from the Water & Sewer Operating Fund to the Water Capital
Projects fund ($237,641 60) and Sewer Capital Projects Fund ($143,688 50), and
2 Adopt the attached appropriation ordinance increasing estimated receipts and appropriation in the
Water Capital Projects Fund in the amount of $237,641 60 and the Sewer Capital Project Fund in
the amount of $143,688 50 from available funds, and
3 Authorize the City Manager to execute a contract with Stocker Enterprises, Inc. in the amount of
$331,170 10 for water and sanitary sewer line replacements on Overhill Road (Valhalla to S H 183)
and Willis Avenue (Borden to Overhill)
DISCUSSION
The 1993 Capital Improvement Program included funds for the reconstruction of Overhill Road (Valhalla
to S H 183) and Willis Avenue (Borden to Overhill) The Water Department has determined that the
water and/or sanitary sewer lines on both streets are seriously deteriorated and should be replaced
prior to street reconstruction
The major work to be performed under this contract includes the replacement of 2,720 linear feet of 8,
12 and 24-inch water lines, and 1,880 linear feet of 8 and 10-inch sanitary sewer lines
The project was advertised on June 11 and 18, 1998 On July 16, 1998, the following bids were
received
BIDDER AMOUNT TIME OF COMPLETION
Stocker Enterprises. Inc. $331.170.10 60 Working Days
J D Vickers, Inc. 333,908 15
Larry H Jackson Construction, Inc. 397,699 10
This project is located in COUNCIL DISTRICT 3, Mapsco 74W
In addition to the contract cost, $34,000 00 is required for inspection and survey (water $21,000 00;
sewer $13,000 00), and $18,000 00 is provided for project contingencies (water $11,000 00, sewer
$7,000 00)
City of Fort Worth, Texas
M'Ayor And Council CammunicAtion
Date Reference Number Log Name Page
9/15/98 **C-16990 30STOCKER 2 of 2
Subject APPROPRIATION ORDINANCE AND AWARD OF CONTRACT TO STOCKER
ENTERPRISES, INC FOR WATER AND SANITARY SEWER LINE REPLACEMENTS
ON OVERHILL ROAD (VALHALLA TO S H 1831 AND WILLIS AVENUE (BORDEN TO
OVERHILL)
Stocker Enterprises, Inc. is in compliance with the City's M/WBE ordinance by committing to 20%
M/V1/BE participation The City's goal on this project is 20%
FISCAL INFORMATION/CERTIFICATION
The Finance Director certifies that upon approval and completion of recommendation 1, and the
adoption of the attached appropriation ordinance, funds will be available in the current capital budgets,
as appropriated, of the Water Capital Projects Fund and Sewer Capital Projects Fund
MG•j
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by• (to)
1 &2) PW53 472045 060530173190 $237,641.60 }. ~,.~,; , ,.,,~t, ..
~
Mike Groomer 6140 1&2) PS58 472045 070580172690 $143,688.50 ~~~~?~~').}
Originating Department Head. 2) PW53 541200 060530173190 $216
641.60 ~~°( ~~ `
Gt~~,){
d~ )
, ~.
~;
2)PW53 531350 030530173190 $ 21,000.00
2) PS 58 541200 070580172690 $130,688.50 5~~~ ~ 5 `~~~~
2) PS58 531350 030580172690 $ 13,000 00
A. Douglas Rademaker 6157 (from) (la ~%., ~-
3) PW53 541200 060530173190 $205,641.60 .~
~~
,
~;~,,~~~~
z~ya~:.~;
Additional Information Contact: 3) PS58 541200 070580176690 $123,688.50 F
'
`
y
Cd~~ ~x?bAt.?~E.e,.;+.p~t~;t~
1)PE45 538070 0609020 $237,641 60
A. Douglas Rademaker 6157 1) PE45 538070 0709020 $143,688.50 -