HomeMy WebLinkAboutOrdinance 13069Ordinance No. ,3(l ,6 /
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER CAPITAL PROJECTS FUND IN THE AMOUNT OF $28,952.00 AND IN THE SEWER
CAPITAL PROJECTS FUND IN THE AMOUNT OF $69,701 75 FROM AVAILABLE FUNDS FOR
THE PURPOSE OF FUNDING A CONTRACT TO LARRY H. JACKSON CONSTRUCTION, INC.,
FOR RECONSTRUCTION OF DEWEY AND RELATED WATER AND SANITARY SEWER LINE
REPLACEMENT, PROVIDING FOR A SEVERABILITY CLAUSE, MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN
CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1996-97 and in the Budget of
the City Manager, there shall also be increased estimated receipts and appropriations in the Water Capital Projects Fund in the
amount of $28,952.00 and in the Sewer Capital Projects Fund in the amount of $69,701 75 from available funds for the
purpose of funding, a contract to Larry H. Jackson Construction, Inc., for reconstruction of Dewey Street and related water and
sanitary sewer line replacement.
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by a
court of competent jurisdiction, such decision, opinion or judgement shall in no way impair the remaining portions, sections, or
parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 12629 and all other ordinances and appropriations amending the
same except m those instances where the provisions of this ordinance are in direct conflict with such other ordinances and
appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly
repealed.
SECTION 4
This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
Assistant City Attorney
~-f y ~9~'
Date
Adopted
~v~y/. X997
Effective
City of Fort Wordy Texars
Mayor and Council Communication
DATE ItEFBRENCB NUND3LR LOG NAME PAGE
07/01 /97 **C-16152 30DEWEY 1 of 3
sIISJSCT APPROPRIATIONS ORDINANCES AND AWARD OF CONTRACT TO LARRY H '
~- ~ JACKSON CONSTRUCTION INC ,FOR RECONSTRUCTION OF DEWEY STREET
FROM DECATUR AVENUE TO DEEN ROAD AND RELATED WATER AND SANITARY
SEWER LINE REPLACEMENT
RECOMMENDATION
It is recommended that the City Council
Authorize the transfier of 598,653 75 from the Water and Sewer Operating Fund to
the Water Capital Projects Fund (528,952 00) and to the Sewer Capital Projects
Fund (569,701 75), and-
2 Adopt the attached appropriations ordinance increasing estimated receipts and
appropriations in the Water Capital Projects Fund in the amount of 528,952 00 and
the Sewer Capital Projects Fund in the amount of 569,701 75 from available funds.,
and `~
3 Adopt the attached appropriations ordinance increasing estimated receipts and
appropriations by 54,181 43 in the Special Assessments Fund from available funds,
and
4 Authorize the transfer of 54,181 43 from the Special Assessments Fund to the
Street Improv,_e,ments Fund, and '
5 Adopt the attached appropriations ordinance increasing estimated receipts and
approprations by 54,181 43 in the Street Improvements Fund from available funds,
and
6 Authorize the City Manager to execute a contract with Larry H Jackson
Construction, Inc , in the amount of 5459,537 50 for the reconstruction of Dewey
Street from Decatur Avenue to Deen Road, and related work and sanitary sewer line
improvements
DISCUSSION
The 1993 Capital Improvement Program included funds for the reconstruction of Dewey
Street from Decatur Avenue to Deen Road This street was not previously constructed
to City standards On October 22, 1996, the City Council held a benefit hearing and
levied assessments for this project The Water Department has determined that water and
sanitary sewer lines in this street are in need of replacement prior to street reconstruction
There are no assessments against adjoining properties
Printed on Bagdad Paper
City of Fort Worth, Texas
Mayor and Council Communication
07/01 /97
**C-16152
30DEWEY I 2 of 3
svsJSCx APPROPRIATIONS ORDINANCES AND AWARD OF CONTRACT TO LARRY H
JACKSON CONSTRUCTION INC., FOR RECONSTRUCTION OF DEWEY STREET
FROM DECATUR AVENUE TO DEEN ROAD AND RELATED WATER AND SANITARY
SEWER LINE REPLACEMENT
The street improvements include the construction of standard concrete pavement,
driveway approaches and sidewalks where shown on the plans Water and sanitary sewer
replacements will also be made
This project is located in COUNCIL DISTRICT 2, Mapsco 62D and 63A
The project was advertised on January 16 and 23, 1997 The following bids were
received on February 13, 1997
BIDDERS AMOUNT TIME OF COMPLETION
Larry H. Jackson Construction, Inc. 5459,537.50 85 Working Days
Walt Williams Const Inc 460,764 80
J L Bertram Construction, Inc 474,235 81
Ed. Bell Construction Company 493,802 85
McClendon Construction Co , lnc 512,638 50
Ed Wilson, Inc 530,461 28
Funding in the amount of__$8,500 00 is included for associated water and sanitary sewer
construction inspection and survey Contingency funds to cover change orders total
$8,500 00 _
,.
Larry H Jackson Construction, Inc ,committed to 9°lo M/WBE participation The City's
goal on this project is 17% Due to an error in providing availability information by City
staff, it is recommended that Larry H Jackson Construction, inc , be considered in
compliance with Ordinance No 11923 by having made a good faith effort
The contingency for possible change orders for street reconstruction is $18,894.00
>~ Printed on Hetyded Pager
City of Fort Worth Texas
Mayor and Council Communication
DATE RSF$R8NC8 NIII~ER LOG NAME PAGl3
07/01 /97 **C-16152 30DEWEY 3 of 3
svs~cT APPROPRIATIONS ORDINANCES AND AWARD OF CONTRACT TO LARRY H.
JACKSON CONSTRUCTION INC ,FOR RECONSTRUCTION OF DEWEY STREET
FROM DECATUR AVENUE TO DEEN ROAD AND RELATED WATER AND SANITARY
SEWER LINE REPLACEMENT
FISCAL INFORMATION/CERTIFICATION
The Director of Fiscal Services certifies that upon completion of recommendation 1, and
the adoption of the attached appropriations ordinances, funds will be available in the
current capital budgets, as appropriated, of the Water and Sewer Capital Projects Funds
and the Street Improvements Fund
MG m
Office by:
Mike Groomer 6140
ppPRO UNC1L
CITY CO
~~~ ~ ~~
A. Douglas Rademaker 6157
Contact:
A. Douglas Rademaker 6157
Panted on Reayded Paper
A~~pt~d Ordinatiice PJo. ~~ f Ndoptecl Or~~n~~1~~ N~eI.~~C~