Ordinance No
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF $21,000 00 FROM INCREASED
REVENUE FOR THE PURPOSE OF FUNDING AN ENGINEERING AGREEMENT WITH HALFF
ASSOCIATES, INC., FOR SANITARY SEWER LINE 278A MARY'S CREEK SIPHON EMERGENCY
REPLACEMENT, PROVIDING FOR A SEVERABILITY CLAUSE, MAKING THIS ORDINANCE
CUMULATNE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN
CONFLICT HEREWITH, AND PROVIDING AN EFFECTNE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS.
SECTION 1
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1996-97 and in the Budget of
the City Manager, there shall also be increased estimated receipts and appropriations in the Sewer Capital Projects Fund in the
amount of $21,000 00 from increased revenue for the purpose of funding an engineering agreement with Halff Associates,
Inc., for Sanitary Sewer Line 278A Mary's Creek Siphon Emergency Replacement
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by a
court of competent jurisdiction, such decision, opinion or judgement shall in no way impair the remaining portions, sections, or
parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 12629 and all other ordinances and appropriations amending the
same except m those instances where the provisions of this ordinance are in direct conflict with such other ordinances and
appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly
repealed.
SECTION 4
This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
K°~ / ,
Assis//tant A(~ttorney
Date ~-
Adopted
Effective
C~t~v of Fort 9~orth, 7"excss
1D11~~~~r° ~¢~u~l c~"~un~~a~ ~'~~au~a¢ua~a~~¢~a~~¢
07/08/97 ~~ _ 1 4 30-278A 1 of 2
SUBJECT APPROPRIATIONS ORDINANCE AND AWARD OF ENGINEERING AGREEMENT TO
HALFF ASSOCIATES, INC ,FOR SANITARY SEWER LINE 278A MARY'S CREEK
SIPHON EMERGENCY REPLACEMENT
RECOMMENDATION
It is recommended that the City Council
1 Authorize the transfer of $21,000 00 from the Sewer Operating Fund to the Sewer
Capital Project Fund, and
2 Adopt the attached appropriations ordinance increasing estimated receipts and
appropriations in the Sewer Capital Project Fund in the amount of $21,000 00 from
increased revenue, and
3 Authorize the City Manager to execute an engineering agreement with Halff
Associates, Inc , for a fee not to exceed 520,000 00 for Sanitary Sewer Line 278A
Mary's Creek siphon emergency replacement
DISCUSSION
The Water Department has determined that the existing siphon sanitary (sewer creek
crossing) on Sanitary Sewer Main M-278A located on Mary's Creek, approximately 300'
east of Old Benbrook Road, has been exposed due to bank erosion This siphon section
is constantly being monitored and the bank refilled after each wash-out After the rain fall
of May 9, 1997, further bank erosion caused the exposed section to shift and wastewater
was discharged into the creek Several repair attempts were undertaken with a successful
repair completed on May 13, 1997 Further concrete encasement and bank stabilization
were completed this same week Replacement of the siphon and provisions for erosion
protection are necessary to implement a permanent repair
The work for this project includes the preparation of plans and specifications for
replacement of this siphon
Halff Associates, Inr , located at 4000 Fossil Creek Blvd , Fort Worth, TX 76137,
proposes to perform the design work for a fee not to exceed $20,000 00, based on
established hourly rates Staff considers this fee to be fair and reasonable for the scope
of services proposed
This project is located in COUNCIL DISTRICT 3, Mapsco 87D
Printed on Recyded Paper
City of Fort Worth, Texas
Mayor and Council Communication
DATE REFERENCE NUMBER LOG NAME PAGE
07/08/97 **~-16154 30-278A 2 of 2
SUBJECT APPROPRIATIONS ORDINANCE AND AWARD OF ENGINEERING AGREEMENT TO
HALFF ASSOCIATES, INC ,FOR SANITARY SEWER LINE 278A MARY'S CREEK
SIPHON EMERGENCY REPLACEMENT
In addition to the contract amount, S 1,000 00 is required for plan review by the
Department of Engineering
FISCAL INFORMATION/CERTIFICATION
The Director of Fiscal Services certifies that upon approval and completion of
recommendation 1 and the adoption of the attached appropriations ordinance, funds will
be available in the current capital budget, as appropriated, of the Sewer Capital Project
Fund
MGf
Su uutte or ity anager's FUND F,NTER M T IT ECRET RY
Office by: cam)
~ APPROVED
Mike Groomer 6140 > CI TY COON
riginatmg epartment ea )PS58 531350 030580173160 1,000,00
~~~
A. Douglas 12ademaker 6157 om `
~ Z~~
3) PS58 531200 070580173160 20,000.00 ,
or dittona ormation 1) PF,45 53807 0709020 21