HomeMy WebLinkAboutOrdinance 12481Ordinance No AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE WATER CAPITAL PROJECTS FUND IN THE AMOUNT OF $19,188 00 FOR THE PURPOSE OF FUNDING THE PROPOSED CHANGE ORDER NO 3 FOR THE CONTRACT WITH JRB CONSTRUCTION, INC , FOR REHABILITATION OF WATER MAINS ON LOWDEN STREET, BOWIE STREET, RYAN AVENUE, CHAPARRAL LANE AND STADIUM DRIVE; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS SECTION 1 That in addition to those amounts allocated to the various City departments for the Fiscal Year 1995-96 and in the Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water Capital Projects Fund in the amount of $19,188 00 for the purpose of funding Proposed Change Order No 3 for the contract with JRB Construction, Inc , for Rehabilitation of Water Mains on Lowden Street, Bowie Street, Ryan Avenue, Chaparral Lane, and Stadium Drive SECTION 2 Should any portion, section or part of a section of this ordinance b.e declared invalid, inoperative or void for any reason by a court of competent jurisdiction, such decision, opinion or judgement shall in no way impair the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and effect SECTION 3 That this ordinance shall be cumulative of Ordinance No 12074 and all other ordinances and appropriations amending the same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed SECTION 4 This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained APPROVED AS TO FORM AND LEGALITY ~~ Assistan 'ty Attorney ~~~o /96 Date ~~ Adopted Effective Cit~V of Fort 6Yorth, Texas Mayor and Council Communication TE 04/09/96 NUMBER **C-15385 30WOOTEN I 1 of 2 SUBJECT APPROPRIATION ORDINANCE AND PROPOSED CHANGE ORDER NO 3 FOR THE CONTRACT WITH JRB CONSTRUCTION, INC ,FOR REHABILITATION OF WATER MAINS ON LOWDEN STREET, BOWIE STREET, RYAN AVENUE, CHAPARRAL LANE AND STADIUM DRIVE RECOMMENDATION It is recommended that the City Council 1 Authorize the City Manager to transfer $19,188 00 from. Water and Sewer Operating Fund to the Water Capital Projects Fund, and 2 Adopt the attached appropriations ordinance increasing. estimated receipts and appropriations in the Water Capital Projects. Fund in the amount of 519,1.88 00, and 3 Authorize Change Order No 3 in the amount of $38,376 00 to the Water Main Rehabilitation Contract Z, Part II (City Secretary Contract No 21327) with JRB Construction, Inc ,revising the total contract cost to 5586,634 85 DISCUSSION On August 15, 1995 (M&C C-12085), the City Council authorized the award of this contract to JRB Construction, Inc for the rehabilitation of the water mains on Lowden Street, Bowie Street, Ryan Avenue, Chaparral Lane and Stadium Drive It is recommended that the resurfacing of Wooten Drive between Wedgway and Trail Lake be added to this contract This is based on the need to repair a street badly damaged by numerous water main repairs This contractor has previously performed similar work on Chaparral Lane The additional cost for repair of Wooten Drive will be shared equally between the Water Department and Transportation and Public Works The net effect of the proposed changes is summarized below • Original Contract Cost 5483,809 10 • Extras to Date 5 64,449 75 • Proposed Change Order No 3 5 38,376 00 • Revised Contract Cost 5586,634 85 • Original Contract Time -Calendar (days) 120 • Additional Approved Time to Date 35 • Additional Time per Change Order No 3 30 • Revised Contract Time 185 Printed on Recycled Paper City of Fort Worth, Texas Mayor and Council Communication DATE REFERENCE NUMBER LOG NAME PAGE 04/09/96 **C-15385 30WOOTEN 2 of 2 SUBJECT APPROPRIATION ORDINANCE AND PROPOSED CHANGE ORDER NO 3 FOR THE CONTRACT WITH JRB CONSTRUCTION, INC ,FOR REHABILITATION OF WATER MAINS ON LOWDEN STREET, BOWIE STREET, RYAN AVENUE, CHAPARRAL LANE AND STADIUM DRIVE Wooten is located in COUNCIL DISTRICT 6 (Mapsco 89Q) The Department of Engineering has reviewed and recommends the above changes FISCAL INFORMATION/CERTIFICATION The Director of Fiscal Services certifies that upon approval and completion of recommendation 1 and the adoption of the attached appropriations ordinance, funds will be available in the current capital budget of the Water Projects Fund Capital and the Contract Street Maintenance Fund MG a Submitted for City Manager's FUND ACCOUNT CEN'T'ER AMOUNT CITY SECRETARY Office by: (to) 1&2) PW53 472045 060530173070 $19 188.00 ~~~j~ Mike Groomer 6140 2) PW53 531200 060530173070 $19 188.00 :t~,~ ~ I i.~~...~a ~~~~ Originating Department Head: rn( A. Douglas Rademaker 6157 (from) 3) PW53 531200 060530173070 $19,188.00 ~~ "" ,l~r.~ ~-A}' For Additional Information 1) PI:45 538070 0609020 $19,188.00 `'rty 5.scr~trry c't th~i City of Fort VYtrrth :'et~t~ Contact: 3) GS93 541200 020930355020 $19,188.00 , A. Douglas Rademaker 6157 Printed on Recyded Paper i° ~ :,".d ~ ~?''+ ;~ '~ , a i , ~ ~ ~i ~ ~ ` .. ,