AN ORDINANCE INCREASING THE ESTIMATED RECEIl'TS AND APPROPRIATIONS IN THE
WATER CAPITAL PROJECTS FUND IN THE AMOUNT OF $91,323 00 AND IN THE SEWER
CAPITAL PROJECTS FUND IN THE AMOUNT OF $108,152.60 FROM AVAILABLE FUNDS FOR
THE PURPOSE OF FUNDING A CONTRACT WITH J D VICKERS CONSTRUCTION, INC., FOR
WATER AND SANITARY SEWER LINE REPLACEMENTS IN HERVIE STREET AND
LITTLEPAGE AVENUE, PROVIDING FOR A SEVERABILITY CLAUSE, MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR
ORDINANCES IN CONFLICT HEREWITH, AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS
SECTION 1.
That in addition to those amounts allocated to the various City departments for the Fiscal Year 1995-96 and in the Budget
of the City Manager, there shall also be increased estimated receipts and appropriations in the Water Capital Project Fund
in the amount of $91,323 00 and in the Sewer Capital Projects Fund in the amount of $108,152.60 from available funds
for the purpose of funding a contract with J D Vickers Construction, Inc., for water and sanitary sewer line replacement
in Hervie Street and Littlepage Avenue.
SECTION 2.
Should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void for any reason by
a court of competent jurisdiction, such decision, opinion or judgement shall in no way impair the remaining portions,
sections, or parts of sections of this ordinance, which said remaining provisions shall be and remain in full force and
effect.
SECTION 3
That this ordinance shall be cumulative of Ordinance No. 12074 and all other ordinances and appropriations amending
the same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances
and appropriations, in which instance said conflicting provisions of said prior ordinances and appropriations are hereby
expressly repealed.
SECTION 4
This ordinance shall take effect and be in full force and effect and after the date of its passage, and it is so ordained.
APPROVED AS TO FORM AND LEGALITY
"~
Assistant Ci ttorney
~'//~~9G
Date
~L~ ~'~ -!
Adopted
Effective
City of Fort Worth, Texas
Mayor and Council Communication
DAIS RSFSRSNCS NUMBER LOG NAMS PAGN
It 10/01 /96 **C-15667 30MCAR ~ 1 of 2
sUBJ$cT APPROVAL OF SUPPLEMENTAL APPROPRIATIONS ORDINANCE AND CONTRACT
WITH J D VICKERS CONSTRUCTION, INC ,FOR WATER AND SANITARY SEWER
LINE REPLACEMENTS IN HERVIE STREET (WEST VICKERY TO BONNELL) AND
LITTLEPAGE AVENUE (LIBBEY TO KILPATRICK)
RECOMMENDATION
It is recommended that the City Council
1 Authorize the City Manager to transfer 5199,475 60 from Water and Sewer
Operating Fund to the Water Capital Projects Fund in the amount of $91,323 00 and
Sewer Capital Projects Fund in the amount of 5108,152 60, and
2 Adopt the attached appropriations ordinance increasing estimated receipts and
appropriations in the Water Capital Projects Fund in the amount of 591,323 00 and
the Sewer Capital Projects Fund in the amount of 5108,152 60 from available
funds, and
3 Authorize the City Manager to execute a construction contract with J D Vickers
Construction, Inc , in the amount of 5178,102 60 for water and sanitary sewer line
replacements in Hervie Street (West Vickery to Bonnell) and Littlepage Avenue
(Libbey to Kilpatrick)
DISCUSSION
The 1990 CIP provided funds for the reconstruction of Hervie Street (West Vickery to
Bonnell) and Littlepage Avenue (Libbey to Kilpatrick) The Water Department has
determined that the water and sanitary sewer lines in these streets are seriously
deteriorated and should be replaced prior to the reconstruction of the streets
The work to be performed under this contract includes the replacement of 650 L F of
water lines, 1,596 L F of sanitary sewer lines and related appurtenances
The project was advertised on January 18, 1996 and January 25, 1996 Bids for the
-project were received on February 22, 1996 However, the award of contract was
delayed for the Assessment Paving Benefit Hearing The bids were as follows
BIDDERS AMOUNT TIMEOFCOMPLETION
J D Vickers Construction, Inc $178,102 60 40 Working Days
Larry H Jackson, Const $179,787 50
Tri-Tech Construction, Inc $182,955 00
JRB Construction, Inc $188,507 34
Printed on Recyded Paper
City of Fort Worth, Texas
Mayor and Council Communication
DATE REIeERENCE NUMBER LOG NAME PAGE
10/01 /96 *'~C-15667 30MCAR 2 of 2
SUBJECT APPROVAL OF SUPPLEMENTAL APPROPRIATIONS ORDINANCE AND CONTRACT
WITH J D VICKERS CONSTRUCTION, INC ,FOR WATER AND SANITARY SEWER
LINE REPLACEMENTS IN HERVIE STREET (WEST VICKERY TO BONNELL) AND
LITTLEPAGE AVENUE (LIBBEY TO KILPATRICK)
This project is located in COUNCIL DISTRICT 7, Mapsco 74V and 75E
Funding in the amount of 512,467 00 is included for associated water and sanitary sewer
construction inspection and survey Contingency funds to cover change orders total
58,906 00
J D Vickers Construction, Inc , by committing to 13 00% M/WBE participation, is in
compliance with the City's M/WBE Policy The stated goal for this project was 13 00%
FISCAL INFORMATION/CERTIFICATION
The Director of Fiscal Services certifies that upon approval and completion of
recommendation 1, and the adoption of the attached appropriations ordinance, funds will
be available in the current capital budgets, as appropriated, of the Water Capital Projects
Fund and Sewer Capital Projects Fund
MGf
u mrtte or uy anager s
Office by: (to)
1) PW53 472045 060530173180 91,323.
1) PS58 47 045 070580172680 108,152.
APPROVED
Mike Groomer 6140 CIT Y CO~NCf L
Originating partment ea 2) PW 541200 060530173180 85,616.
PW 531 50 0305301 3180 5,707.
1 ocT ~ 1996
2) PS58 531350 030580172680 6,760.
A. Douglas Rademaker 6157 (from) ~,~,~~ ~~,~,~y,4, ~ J
1) PFAS 538070 0609020 199,475. City.Secreii~~yyof the
. City of Fort R2fth, ?eras
For Additiomil Information 3) PW53 531350 030530173590 5707.
Contact: )PS58 41200 070580172100 101,392.
A. Douglas Rademaker 6157 )PS58 531 50 030580172100 6,760.
Printed on Aegded Paper