AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS
IN THE STREETS IMPROVEMENTS FUND IN THE AMOUNT OF $138,614 82 FOR
THE PURPOSE OF FUNDING CONTRACT WITH J L BERTRAM CONSTRUCTION AND
ENGINEERING, INC , FOR ASSESSMENT PAVING OF FITZHUGH FROM STALCUP
TO CASS; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS
ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL PRIOR
ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS
SECTION 1
That in addition to those amounts allocated to the various City departments
for the Fiscal Year 1994-95 and in the Budget of the City Manager, there shall
also be increased estimated receipts and appropriations in the Streets
Improvements Fund in the amount of $138,614 82 for the purpose of funding
contract with J L Bertram construction and Engineering, Inc for assessment
paving of Fitzhugh from Stalcup to Cass
SECTION 2
Should any portion, section or part of a section of this ordinance be declared
invalid, inoperative or void for any reason by a court of competent
jurisdiction, such decision, opinion or judgement shall in no way impair the
remaining portions, sections, or parts of sections of this ordinance, which
said remaining provisions shall be and remain in full force and effect
SECTION 3
That this ordinance shall be cumulative of Ordinance No 11645 and all other
ordinances and appropriations amending the same except in those instances
where the provisions of this ordinance are in direct conflict with such other
ordinances and appropriations, in which instance said conflicting provisions
of said prior ordinances and appropriations are hereby expressly repealed
SECTION 4
This ordinance shall take effect and be in full force and effect and after the
date;of its passage, and it is so ordained
APPROVED AS TO FORM AND LEGALITY
~~
-City Atto ey
3 /~~ y,~"
,Date
~f` ~ ~~
Adopted J ~ _
~~
Effective
:;
~' City of Fort Worth, Texas
Mayor and Council Communication
DATE
04/04/95
20FITZ I 1 of 2
SUBJECT ADOPTION OF SUPPLEMENTAL APPROPRIATIONS ORDINANCE AND AWARD OF
CONTRACT TO J L. BERTRAM CONSTRUCTION AND ENGINEERING, INC ,FOR
ASSESSMENT PAVING OF FITZHUGH FROM STALCUP TO CASS (PROJECT NO 67-
040264)
RECOMMENDATION
It is recommended that the City Council
1 Approve a 5138,614 82 fund transfer for the property owner's share of construction costs
from the Special Assessments Fund to the Street Improvements Fund, and
2 Adopt the attached appropriations ordinance increasing estimated receipts and
appropriations by 5138,614 82 in the Streets Improvements Fund from increased
revenues, and
3 Approve a 560,727 85 fund transfer from the Streets Assessments Project to the Street
Construction Project in the Grants Fund, and
4 Authorize the City Manager to execute a contract with J L Bertram Construction and
Engineering, Inc , in the amount of $404,852 31 for the assessment paving of Fitzhugh
from Stalcup to Cass
DISCUSSION
The 19$6 Capital Improvement Program included funds for the improvement of Fitzhugh from
Stalcup to Cass The street has previously been constructed to City standards Community
Development Block Grant (CDBG) funds will provide a portion of the construction costs
On May 26, 1992 (MC BH-0095), the City Council held a benefit hearing and levied assessments
for this project
The street improvements will include the construction of standard concrete pavement, driveway
approaches, and sidewalks where shown on the plans
The project was advertised on January 19 and 26, 1995 The following bids were received on
February 16
NUMBER **C-14747
~~~ Printed on recycled paper
City of Fort Worth, Texas
Mayor and Council Communication
DATE REFERENCE
NUMBER **C-14747 LOG NAME PAGE
04/04/95 20FITZ 2 of 2
SUBJECT ADOPTION OF SUPPLEMENTAL APPROPRIATIONS ORDINANCE AND AWARD OF
CONTRACT TO J L BERTRAM CONSTRUCTION AND ENGINEERING, INC ,FOR
ASSESSMENT PAVING OF FITZHUGH FROM STALCUP TO CASS (PROJECT NO 67-
040264)
BIDDERS AMOUNT TIME OF COMPLETION
J L Bertram Construction & Eng Inc 5404,852 31 45 Working Days
Specified
Walt Williams Construction, Inc 413,896 70
Ed A Wilson, Inc 440,487 40
The engineer's estimated cost of construction was 5410,890
The contingency for possible change orders is 520,242 62
J L Bertram Construction and Engineering, Inc ,based on a good faith effort and 12 42 percent
DBE participation, is in compliance with the City's DBE Policy
This project is located in DISTRICT 5
FISCAL INFORMATION/CERTIFICATION
The Director of Fiscal Services certifies that upon completion of recommendations 1 and 3 and
adoption of the attached appropriations ordinance, funds required for this project are available
in the current capital budgets, as appropriated, of the Grants Fund and the Street Improvements
Fund
MG a
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by• (tol
11- GS67 488993 020670402640 5138,614.8
Mike Groomer 614 (3) R76 541210 020206094810 S 60,727 85
Originating Department Head: 121 GS67 488993 020670402640 5138,614 82
121 67 541200 020670402640 S 138, 614 82
Hugo A Malanga 780 (from)
11- GS94 538070 020940099050 5138,614 82
For Additional Information (31 GR76 541210 005206094350 S 60,727 85
Contact: (4) GS67 541200 020670402640 5344,124 46
Hugo A Malanga 780 (4) GR76 541210 020206094810 5 60,727.85
' q.
•='~ Printed on recycled paper