HomeMy WebLinkAboutOrdinance 11929Ordinance No ~p~
AN ORDINANCE INCREASING THE ESTIMATED RECEIPTS AND APPROPRIATIONS IN
THE WATER CAPITAL PROJECTS FUND IN THE AMOUNT OF $143,258 00 FOR THE
PURPOSE OF FUNDING WATER AND SEWER IMPROVEMENTS IN ELLIS AVENUE FROM
NW 29TH STREET TO LONG AVENUE; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES AND REPEALING ALL
PRIOR ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE
DATE
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS
SECTION 1
That in addition to those amounts allocated to the various City departments for
the Fiscal Year 1994-95 and in the Budget of the City Manager, there shall also be
increased estimated receipts and appropriations in the Water Capital Projects Fund
in the amount of $143,258 00 for the purpose of funding water and sewer
improvements in Ellis Avenue from NW 29th to Long Avenue
SECTION 2
Should any portion, section or part of a section of this ordinance be declared
invalid, inoperative or void for any reason by a court of competent jurisdiction,
such decision, opinion or judgement shall in no way impair the remaining portions,
sections, or parts of sections of this ordinance, which said remaining provisions
shall be and remain in full force and effect
SECTION 3
That this ordinance shall be cumulative of Ordinance No 11645 and all other
ordinances and appropriations amending the same except in those instances where
the provisions of this ordinance are in direct conflict with such other ordinances
and appropriations, in which instance said conflicting provisions of said prior
ordinances and appropriations are hereby expressly repealed
SECTION 4
This ordinance shall take effect and be in full force and effect and after the
date of its passage, and it is so ordained
APPROVED AS TO FORM AND LEGALITY
1 ~
~L City Atto y
T ~ ~ l l ~QS
Date _
~-~-5
Adopted _
/~-~~
Effective
City of Fort Worth, Texas
Mayor and Council Communication
DATE
04/ 18/95
30ELLIS I 1 of 2
SUBJECT APPROPRIATION ORDINANCE AND CONTRACT WITH CIRCLE "C" CONSTRUCTION,
INC ,FOR WATER AND SEWER IMPROVEMENTS IN ELLIS AVENUE FROM NW 29TH
STREET TO LONG AVENUE
RECOMMENDATION
It is recommended that the City Council
~ >-~z~
- ~ ~ 1 X30
Authorize the City Manager to transfer 5206,501 00 from Water and Sewer Operating
Fund to the Water Capital Projects Fund in the amount of S 143,258 00 and to the Sewer
Capital Projects Fund in the amount of 563,243 00, and
2 Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Water Capital Projects Fund in the amount of S 143,258.00 and the
Sewer Capital Projects Fund in the amount of 563,243 00 from increased revenue, and
3 Authorize the City Manager to execute a construction contract with Circle "C"
Construction, Inc , in the amount of S 181,163 00 for the water and sewer construction
of Ellis Avenue from NW 29th Street to Long Avenue allowing fifty (50) working days
DISCUSSION
The 1990 Capital Improvement Program included funds for the reconstruction of Ellis Avenue
from NW 29th Street to Long Avenue The Water Department has determined that the water
and sewer mains in this street require replacement prior to street reconstruction
This project was advertised on February 9, 1995 and February 16, 1995 The following bids
were received March 2, 1995
BIDDERS AMOUNT TIME OF COMPLETION
Circle "C" Construction, Inc
J D Vickers, Inc.
Conatser Construction, Inc
Dyer Materials
Tri-Tech Construction, Inc
Atkins Brothers
The Engineer's Estimate was 5208,262 00
5181,163 00 50 Working Days
187,968 58
195,595 50
203,268 50 ~" ~-"
228,923 50
285,189 00
The low bidder (Circle "C" Construction Co) based on a Good Faith. Effort and committing to
12 13% DBE participation, is in compliance with the City's DBE Policy '` :.
REFERENCE
NUI~ER *#`''-14778
~.,Prfrrted on recyded paper
City of Fort Worth, Texas
Mayor and Council Communication
DATE REFERENCE
NUMBER **C-14778 LOG NAME PAGE
04/18/95 30ELLIS 2 of 2
SUBJECT APPROPRIATION ORDINANCE AND CONTRACT WITH CIRCLE "C" CONSTRUCTION,
INC ,FOR WATER AND SEWER IMPROVEMENTS IN ELLIS AVENUE FROM NW 29TH
STREET TO LONG AVENUE
This project is located in DISTRICT 2, Mapsco 48X & 62B
In addition to the contract cost, 56,367 00 and 55,383 00 are required for possible change
orders for water and sewer respectively
The water contingencies for associated construction inspection and survey are 59,551 00 The
sewer contingencies for associated construction inspection and survey are 54,037 00
FISCAL INFORMATION/CERTIFICATION
The Director of Fiscal Services certifies that upon approval and completion of recommendation
1, and the adoption of the attached appropriation ordinance, funds required for the construction
phase of the water and sewer facilities will be available in the current operating budget of the
Water and Sewer Capital Project Funds
MG a
Submitted for City Manager's FUND ACCOUNT CENTER AMOUNT CITY SECRETARY
Office by (tot
(1) PW53 472045 060530173270 S 143,258 0
Mike Groomer 614 4 45 1
(2) PW53 472045 060530173270 S143,258.0
12- PS58 472045 070580172770 S 63,243 0 gppRpVEO
(21 PW53 541200 060530173270 S133,707 0 Cf TY CO UN C fL
(21 PW53 531350 030530173270 S 9,551 0
Originating Department Head: (2) PS58 541200 070580172770 S 59,206.0 ~R 18 19~
12- P 58 531350 030580172770 S 4,037.0
A. Douglas Rademaker 615 (from) ~~ ~
111 PE45 538070 0609020 S 143,258.0 C
y o
Fo~W
hf ?
m
11- PE45
538070
0709020
S 63,243.0 i
f
rt
e
s
(3) PW53 541200 060530 5133,707 0
For Additional Information (3) PW53 531350 060530 S 9,551.0
Contact: 3) PS58 541200 070580 S 59,206.0
A. Douglas Rademaker 615 131 PS58 531350 030580 S 4,037.0